PS Number 16 Elementary School |
The new 109,500 square-foot, three-story facility is designed to educate approximately 700 students in grades Pre-kindergarten through eight. The new school will replace the existing building which was demolished. Demolition activities of the former school and surrounding properties were completed in April 2014. The school will include 22 general use classrooms, three kindergarten classrooms, four pre-kindergarten classrooms, specialized instruction classrooms and labs, a media center, a cafetorium, a gymnasium, as well as administrative and support facilities.
|
CURRENT STATUS - As of June 10, 2014: The demolition of the existing school has been completed. A limited NTP was issued in April 2014 for site mobilization and soil erosion activities. Preliminary design is under review.
|
PROJECT INFORMATION
|
Key Parties:
Site Preparation Construction Contractor |
USA Environmental Management, Inc. |
General Contractor/Design-Build Contractor |
Hall Construction Co, Inc. |
Architect/Design-Build Architect |
DIGroup Architecture, LLC |
Construction Manager |
GREYHAWK North America, LLC |
Schedule*:
Site Preparation Construction Activities |
Completed April 2014 |
Design |
Design NTP issued January 17, 2014 |
Start of Building Construction |
September 2014 |
Anticipated School Opening |
September 2016 |
Costs:
Total Estimated Project Costs |
$62.3 Million |
Total Construction Costs |
$33.3 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|