Rose Lopez Elementary School |
The new Rose M. Lopez Elementary School is a 128,000 square-foot facility designed to educate approximately 800 students and is being utilized by the district for students in grades Kindergarten through second. The 3-story
building was constructed on District-owned land and includes 38 classrooms, six Small Group Instruction Rooms,
four Basic skills/ESL/Resource rooms, a Science Demonstration Room, a speech room, vocal and instrumental
music rooms, a computer lab, a gymnasium, a media center, a cafeteria, a multipurpose room with stage, as well
as outdoor play and learning areas.
|
CURRENT STATUS - The project is substantially complete and the school is occupied. A ribbon cutting ceremony was held on September 24, 2019. |
PROJECT INFORMATION
|
Key Parties:
Design-Build Contractor |
EPIC Management |
Design-Build Architect |
DIGroup Architects |
Construction Manager |
GREYHAWK North America, LLC |
Schedule*:
Design |
Design NTP issued 8/5/16 |
Start of Building Construction |
March 2017 |
School Opening |
Anticipated for September 2019 |
Costs:
Total Estimated Project Costs |
$56.4 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|