New Grade 7 to 9 School |
The New Grade 7-9 School project scope calls for construction of an approximately 132,000 square-foot, six-story facility for more than 900 students in grades 7 through 9. |
CURRENT STATUS - As of March 1, 2024: This project is in construction. Steel erection is complete. Slab-on-deck installation is complete and building enclosure activities will commence this month.
|
PROJECT INFORMATION
|
Key Parties:
Design-Build Contractor |
Dobco, Inc. |
Design-Build Architect |
NK Architects, P.A. |
Construction Manager |
Anser Advisory Management |
Schedule*:
Design |
Design NTP July 2022 |
Start of Building Construction |
TBD |
Anticipated School Opening |
September 2025 |
Costs:
Total Estimated Project Costs |
$93.7 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|