Patricia M. Noonan Elementary School |
The new 123,000 square-foot school educates approximately 770 students in grades pre-kindergarten through five. The school includes 30 general education classrooms, 10 pre-kindergarten classrooms, four self-contained special education classrooms, cafeteria, gymnasium, assembly/multi-purpose room and a media center.
|
CURRENT STATUS - The project is substantially complete and the school is occupied.
|
PROJECT INFORMATION
|
Key Parties:
Site Preparation Construction Contractor |
Tricon Enterprises, Inc. |
Design-Build Contractor |
Dobco, Inc. |
Design-Build Architect |
Rivardo, Schnitzer, Capazzi, dba RSC Architects |
Construction Manager |
Epic Management, Inc. |
Schedule*:
Site Preparation Construction Activities |
Completed April 2013 |
Design |
Design NTP issued July 19, 2013 |
Start of Building Construction |
November 2014 |
School Opening |
April 2017 |
Costs:
Total Project Costs |
$54 Million |
Total Construction Costs |
$33.5 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|