Dr. Maya Angelou Elementary School #20 |
The new 108,800 square-foot, three-story school is designed to educate approximately 700 students in grades kindergarten through five. The school includes 30 general education classrooms, four self-contained special education classrooms, technology lab, cafeteria, gymnasium, assembly/ multi-purpose room and a media center.
|
CURRENT STATUS - The project is substantially complete and the school is occupied. A ribbon cutting ceremony was held on September 8, 2016. |
PROJECT INFORMATION
|
Key Parties:
Site Preparation Construction Contractor |
Silverlands Services, Inc. |
General Contractor |
Dobco, Inc. |
Architect |
SSP Architectural Group |
Construction Manager |
Gilbane Building Company |
Schedule*:
Site Preparation Construction Activities |
Completed November 2012 |
Start of Building Construction |
February 2014 |
School Opening |
September 2016 |
Costs:
Total Estimated Project Costs |
$49.3 Million |
Total Construction Costs |
$28.7 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|