South Street Elementary School |
|
The new 103,000 square-foot school was designed to accommodate approximately 600 students in pre-kindergarten through eighth grades and opened to students in 2018. The new school was built using a design-build approach.
|
CURRENT STATUS - The project is substantially complete and the school is occupied.
|
PROJECT INFORMATION
|
Key Parties:
|
Site Preparation/Demolition Construction Contractor |
USA Environmental Management, Inc. & Luzon, Inc. |
|
Design-Build Contractor |
Ernest Bock & Sons |
|
Design-Build Architect |
SSP Architectural Group |
|
Construction Manager |
STV Construction, Inc. |
Schedule*:
|
Site Preparation Construction Activities |
Completed January 2015 |
|
Design |
Design NTP issued 11/23/15 |
|
Start of Building Construction |
3rd Quarter 2016 |
|
School Opening |
September 2018 |
Costs:
|
Total Estimated Project Costs |
$69.9 Million |
|
Total Construction Costs |
$30.8 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|