Oliver Street Elementary School |
Located in the East Ward, the new 137,000 square-foot Oliver Street Elementary School will replace the current antiquated school which was constructed in 1869. The new school will provide approximately 930 students in pre-kindergarten through eighth grades with 30 general use classrooms, four kindergarten classrooms, six pre-kindergarten classrooms, specialized instruction classrooms and labs, a media center, separate cafeteria, gymnasium and a multipurpose room with stage. The new school will be built using a design-build approach.
|
CURRENT STATUS - The project is substantially complete and the school is occupied. A ribbon cutting ceremony was held in June 2016. |
PROJECT INFORMATION
|
Key Parties:
Site Preparation/Demolition Construction Contractor |
Silverlands Services, Inc. |
Design-Build Contractor |
Epic Management, Inc. |
Design-Build Architect |
NK Architects |
Construction Manager |
Gilbane Building Company |
Schedule*:
Site Preparation Construction Activites |
Completed April 2013 |
Design |
Design NTP issued April 17, 2013 |
Start of Building Construction |
March 2014 |
School Opening |
May 2016 |
Costs:
Total Estimated Project Costs |
$73.6 Million |
Total Construction Costs |
$38.8 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|