Gloucester City Middle School |
The new 122,000 square-foot school was designed to educate approximately 685 students in grades 4 through 8. The school includes 27 general classrooms, eight special education classrooms, three science classrooms, a cafetorium with stage, gymnasium, media center, computer lab and administrative offices. The new school was built using a design-build approach.
|
CURRENT STATUS - The project is substantially complete and the school is occupied. |
PROJECT INFORMATION
|
Key Parties:
Design-Build Contractor |
Terminal Construction Corporation |
Design-Build Architect |
Manders Merighi Portadin Farrell Architects, LLC |
Construction Manager |
GREYHAWK North America, LLC |
Schedule*:
Design |
Design NTP issued August 6, 2014 |
Start of Building Construction |
NTP issued June 25, 2015 |
School Opening |
2017 |
Costs:
Total Project Costs |
$65.3 Million |
Total Construction Costs |
$42 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|