James Madison Elementary School |
The new 53,000 square-foot, three-story school is designed to educate approximately 275 students in grades kindergarten through 5. The school includes 13 general use classrooms, two special education classrooms, four small group instruction rooms, a cafeteria, a multipurpose room with stage that will be utilized as the gymnasium and for large group assembly, a music room, an art room, a computer room and a media center. The new school was built using a design-bid-build approach.
|
CURRENT STATUS - As of January 1, 2019: The project is substantially complete and the school is occupied. |
PROJECT INFORMATION
|
Key Parties:
Site Preparation/Demolition Construction Contractor |
Tricon Enterprises, Inc. |
General Contractor |
Brockwell & Carrington Contractors, Inc. |
Architect |
Fraytak, Veisz, Hopkins, Duthie PC |
Construction Manager |
The McCloud Group |
Schedule*:
Site Preparation Construction Activities |
Completed 1st Quarter 2015 |
Design |
Completed 3rd Quarter 2014 |
Start of Building Construction |
NTP issued April 29, 2016 |
Anticipated School Opening |
September 2018 |
Costs:
Total Estimated Project Costs |
$29.7 Million |
Total Construction Costs |
$15 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|