Orange
Cleveland Street E.S.

335 CLEVELAND ST

ORANGE, NJ 07050-1916

(973)677-4100



Cleveland Street Elementary School
The project will include the construction of an approximately 11,500 square-foot addition and renovations to the existing Cleveland Street Elementary School to accomodate a Pre-Kindergarten to 8th grade program.

CURRENT STATUS - As of October 15, 2020: The project is in construction. Underground utility and masonry work is ongoing, and structural steel erection is scheduled to begin next month. Interior structural renovations in the existing building have started.

PROJECT INFORMATION

Key Parties:
Site Preparation/Demolition Construction Contractor Two Brothers Construction
General Contractor Brockwell & Carrington Contractors
Architect Kliment Halsband Architects
Construction Manager EPIC Management.

Schedule*:
Site Preparation Construction Activities Completed May 2019
Design Design NTP 12/3/2017
Start of Building Construction October 2019

Costs:
Total Estimated Project Costs $33.2 Million






*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.