Cleveland Street Elementary School |
|
The project will include the construction of an approximately 11,500 square-foot addition and renovations to the existing Cleveland Street Elementary School to accomodate a Pre-Kindergarten to 8th grade program.
|
CURRENT STATUS - As of May 1, 2021: The project is in construction. The first phase of structural steel work is complete with underground utility and masonry work ongoing. Phase I interior structural renovations in the existing building are complete. Phase II renovation work in the existing building is in progress.
|
PROJECT INFORMATION
|
Key Parties:
|
Site Preparation/Demolition Construction Contractor |
Two Brothers Construction |
|
General Contractor |
Brockwell & Carrington Contractors |
|
Architect |
Kliment Halsband Architects |
|
Construction Manager |
EPIC Management. |
Schedule*:
|
Site Preparation Construction Activities |
Completed May 2019 |
|
Design |
Design NTP 12/3/2017 |
|
Start of Building Construction |
October 2019 |
Costs:
|
Total Estimated Project Costs |
$33.2 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|