Irvington Township
Madison Avenue E.S.

163-167 MADISON AVE.

IRVINGTON, NJ 07111

(973)399-6870

Construction Work - June 2019



Madison Avenue Elementary School
The new Madison Avenue Elementary School is being built on the site of the former school. The new 73,000-square-foot elementary school is designed to educate approximately 500 Pre-Kindergarten to 5th Grade students. The new school will include 26 general education classrooms, small group instruction rooms, a cafeteria, a multipurpose room with stage, music and art rooms, a science/computer lab, and a media center. The school will also have an outdoor play space that includes a basketball/volleyball court and running track.

CURRENT STATUS - As of June 1, 2019: The project is in the final stages of construction. Interior finish work, exterior site work including installation of playground equipment, paving and sidewalks is ongoing. Final inspections are in process for issuance of a Temporary Certificate of Occupancy. The school is on schedule to open to students in September.


PROJECT INFORMATION

Key Parties:
Site Preparation Construction Contractor D&K Construction Co., Inc.
Design-Build Contractor Ernest Bock & Sons, Inc.
Design-Build Architect SSP Architectural Group, Inc.
Construction Manager EPIC Management

Schedule*:
Site Preparation Construction Activities Completed November 2017
Design Design NTP 10/19/2017
Start of Building Construction July 2017
Anticipated School Opening September 2019

Costs:
Total Estimated Project Costs $38.6 Million






*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.