Vineland
Lincoln Ave Middle School

3133 SOUTH LINCOLN AVENUE

VINELAND, NJ



Vineland Middle School
The new 99,000 square-foot, single-story school will be designed to educate approximately 620 students in grades 6 through 8. The new school will be built using a design-build approach.

CURRENT STATUS - As of July 1, 2018: The project is in the final stages of construction. The school will open to students in September 2018.


PROJECT INFORMATION

Key Parties:
Design-Build Contractor Ernest Bock & Sons Inc.
Design-Build Architect SSP Architectural Group
Construction Manager Joseph Jingoli & Sons

Schedule*:
Design Design NTP issued February 16, 2016
Construction Start Anticipated 4th Quarter 2016
Anticipated School Opening September 2018

Costs:
Total Estimated Project Costs $49.8 Million



*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.


Last Updated: 08/14/2018
SDA Managed Projects Detail
# Project Number Description Project Type Construction Type
1 5390-N02-02-0245 New Construction of a new Middle School to educate 558 students in grades 6 to 8. School Facility Project New Construction