Millville
High School

MILLVILLE, NJ 08332-2206

(856)327-6040

Construction Work - June 2019



Millville Senior High School
The project includes the construction of a 228,544 square-foot addition and 54,950 square feet of renovations/alterations. The additions/renovations will increase student capacity to accommodate a maximum of approximately 2,380 students in 9th to 12th grade.

CURRENT STATUS - As of May 1, 2021: The Phase II West addition is complete. Exterior brick veneer work is complete on the Phase III North addition. Interior mechanical and finish work is nearly complete. The Phase III addition (Science classrooms, a gymnasium, dance studio, and additional spaces) is on target for a September 2021 opening.

PROJECT INFORMATION

Key Parties:
Design-Build Contractor Hall Construction
Design-Build Architect RSC Architects
Construction Manager Greyhawk North America, LLC

Schedule*:
Design Design NTP 2/11/2016
Start of Building Construction 5/24/2017
Anticipated School Opening Phased until 2022

Costs:
Total Estimated Project Costs $137.5 Million






*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.