Construction Work - June 2019



Millville Senior High School
The project includes the construction of a 228,544 square-foot addition and 54,950 square feet of renovations/alterations. The additions/renovations will increase student capacity to accommodate a maximum of approximately 2,380 students in 9th to 12th grade.

CURRENT STATUS - As of October 15, 2020: The west addition is substantially complete and occupied. The design-builder continues with exterior brick veneer work and mechanical rough-in work on the Phase III addition.

PROJECT INFORMATION

Key Parties:
Design-Build Contractor Hall Construction
Design-Build Architect RSC Architects
Construction Manager Greyhawk North America, LLC

Schedule*:
Design Design NTP 2/11/2016
Start of Building Construction 5/24/2017
Anticipated School Opening Phased until 2022

Costs:
Total Estimated Project Costs $137.5 Million






*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.