NJSDA Processed Change Orders Detail Report #04400a
CA-0001
CA-0001-C02
Henderson Corporation (The)
61
61
Change Order
4/20/2009
($40,000.00)
Hendersons Scope Change #59 - Delete projection screens.
CA-0001
CA-0001-L01
Friedmutter Group
2
2
Change Order
3/8/2004
($274,610.00)
Reduction in scope. Consultant is no longer requried to provide remainder of services for the documentation and the administration / oversight of the Design Build Contractor for the School as previously amended in Amendment #1 dated 3/3/03. NJSCC has
CA-0001
CA-0001-C02
Henderson Corporation (The)
13
13
Change Order
4/21/2008
$114,697.00
Henderson's Scope Change #26 - Tri-State loss of Productivity due to DCA issues.
CA-0001
CA-0001-C02
Henderson Corporation (The)
29
29
Change Order
7/30/2008
$10,223.00
Install additional electrical receptacles in muli-purpose room per sketch SKA-40. Justification: NJSDA determined the multi-purpose room required additonal receptacles. Change Order given to Tony Sassine for review and signature on 6/16/08.cl Change
CA-0001
CA-0001-C02
Henderson Corporation (The)
19
19
CCD-Authorization
2/26/2008
$500,000.00
Refer to Primavera
CA-0001
CA-0001-C02
Henderson Corporation (The)
24
24
Resolving CCD
8/1/2008
$17,028.00
Hendersons Scope Change #33 is finalized and CCD #2 written to cover part of the direct costs is hereby reconciled. Justification: CCD#2 was written for $500,000 to cover a portion of the costs associated with the direct costs for Bulletin #6 that i
CA-0001
CA-0001-C02
Henderson Corporation (The)
2
2
Change Order
9/8/2006
$544,080.00
Delay impact to Henderson.
CA-0001
CA-0001-C02
Henderson Corporation (The)
33
33
CCD-Authorization
10/2/2008
$75,000.00
Remove ceiling grid as required to access adn cut mechanical piping and plumbing piping passing through the firewall and install flexible connections on both sides of teh wall on the 1st level only so that the pipe can move independently from the pip
CA-0001
CA-0001-A01
Hillier Group Architecture, NJ, Inc.
00004
4
Change Order
10/15/2008
$95,000.00
Description: Additional Testing and inspections: increase the allowance for construction for construction phase testing and inspections over the initial allowance. This is allowance and will require bckup when invoiced, unused allowance will be cre
CA-0001
CA-0001-C02
Henderson Corporation (The)
21
21
CCD-Authorization
2/26/2008
$300,000.00
Refer to Primavera
CA-0001
CA-0001-C02
Henderson Corporation (The)
12
12
Change Order
10/29/2007
$179,646.00
Dhimant Dave approved 10/03/07 and Zac Brown approved 8/28/07. 11/16/07: Change Order amount was reduced from $181,528 to $179,646 remove bond charged by the subcontractor.
CA-0001
CA-0001-A01
Hillier Group Architecture, NJ, Inc.
2
2
Change Order
12/26/2006
$255,890.00
Continued Environmental Inspection and Monitoring: 1. In relation to previous scope modification #1 for unforeseen soil conditions beyond what was identified during the feasibility studies of the project: A. Monitoring and testing and determining
CA-0001
CA-0001-C02
Henderson Corporation (The)
8
8
Change Order
9/19/2007
$7,334.00
General Contractor claim for cost associated with Hardware Upgrades.
CA-0001
CA-0001-K11
Keaton Transport Services
1
1
Change Order
1/21/2009
($438.75)
Full Services quoted not needed
CA-0001
CA-0001-C02
Henderson Corporation (The)
42
42
Change Order
10/14/2008
$6,947.00
Description: Hendersons Scope Change #50 - Upgrade Keying to Schlage Primus System. Justification: The CBOE requested teh upgraded keying system to meet the security offered adn support they will continue to need from Schlage as it relates to repa
CA-0001
CA-0001-C02
Henderson Corporation (The)
30
30
Change Order
8/13/2008
$36,476.00
Installation of firewrap insulation for radon piping. Justification: NJSDA Bulletin #36 was issued to have a radon mitigation system added to the project. The piping is required to be insulated in plenum areas. Change Order given to Tony Sassine fo
CA-0001
CA-0001-C02
Henderson Corporation (The)
23
23
Resolving CCD
8/1/2008
$29,049.00
Hendersons Scope Change #29 is finalized and CCD #1 written to cover part of teh direct costs in hereby reconciled. Justification: CCD#1 was written for $450,000.00 to cover a portion of the costs associated with direct costs for Bullitin #5R that
CA-0001
CA-0001-A01
Hillier Group Architecture, NJ, Inc.
00007
7
Change Order
12/22/2009
$12,600.00
This amendment is for final Testing and Inspection allowance an increace over previous allowance required for project.
CA-0001
CA-0001-C02
Henderson Corporation (The)
35
35
Change Order
10/7/2008
$6,689.00
Description: Hendersons Scope Change #42 - Miscellaneous detail revisions as indicated in sketches SKA 33 through SKA 35 issued by Hillier, Also the toilet paper dispensers are being supplied by the CBOE adn deleted from Henderson contract. Justific
CA-0001
CA-0001-C02
Henderson Corporation (The)
22
22
Change Order
6/25/2008
$426,672.00
Extended General Conditions costs ($137,647), Plumbing delay ($53,025), and Escalation charges ($236,000), are incorporated for Henderson to proceed immediately with work associated with Scope Change 29, 34 and 39. This covers the costs associated m
CA-0001
CA-0001-C02
Henderson Corporation (The)
41
41
Change Order
10/7/2008
$2,358.00
Hendersons Scope Change #47 - Replacement of Stolen Installed Hot Water Piping. Justification: Hot water pipe installed on the 2nd floor was reported stolen on 6/25/08. Henderson was instructed by NJSDA to issue as a change order because the cos
CA-0001
CA-0001-C02
Henderson Corporation (The)
52
52
Change Order
3/5/2009
$8,171.00
HC Scope Change #44 - Dect Routing Revison in Nurses Area. Justification Bulletin #6 was issued after ductwork had been fabricated. The ductwork was fabricated according to approved shop drawings. The revison of steel adn elevation changes of Bul
CA-0001
CA-0001-A01
Hillier Group Architecture, NJ, Inc.
1
1
Change Order
1/23/2006
$70,000.00
Addition of environmental inspection and monitoring to project scope.
CA-0001
CA-0001-C02
Henderson Corporation (The)
18
18
Settlement
9/11/2007
$1,419,695.00
During the course of the Camden Early Childhood Development Center project, Henderson Corporation filed a claim against NJSDA seeking compensation in the aggregate amount of $1,574,405. An agreement was reached in which the NJSDA agreed to pay and H
CA-0001
CA-0001-C02
Henderson Corporation (The)
7
7
Change Order
9/19/2007
$4,963.00
General Contractor claim for rusted reinforcing steel due to suspension of construction from soil contamination.
CA-0001
CA-0001-C02
Henderson Corporation (The)
11
11
CCD-Authorization
7/11/2007
$450,000.00
Henderson is hereby directed to proceed immediately with the work as indicated in Bulletin #5R 1 for Sectors B&C dated June 4, 2007. The work consist of the changes reflected on drawings S1.00R, S2.01C-R, S2.02B-R, S2.02C-R, S2.03B-R, S2.03C-R, S3.0
CA-0001
CA-0001-C02
Henderson Corporation (The)
51
51
Change Order
3/13/2009
$17,554.00
HC Scope Change #55 - Replacement of Stolen Domestic Water Piping and VAV Hose Kits. Justification: Install plumbing piping had to be replace after being stolen on 6/13/08. The costs does not exceed teh deductible for the OCIP coverage and the ins
CA-0001
CA-0001-C02
Henderson Corporation (The)
49
49
Change Order
10/27/2009
$51,858.00
HC Scope Change #52 - Playground Poured -in -Place Surfacing JUSTIFICATION: The contract documents did not include specifications or details for a poured in place playground surface. The specifications and sketch SKA-61 was issued by RMJM-Hillier f
CA-0001
CA-0001-C02
Henderson Corporation (The)
45
45
Change Order
4/29/2009
$25,000.00
The Pine street lighting was revised adn resulted in four additional poles being added. In addition Henderson had to install conduit underground to bck feed the existing transformer from the new pole location to keep the existing lights active until
CA-0001
CA-0001-C02
Henderson Corporation (The)
54
54
Change Order
4/13/2009
$43,236.00
HC Scope Change #54 - Field Conditions for Steell Construction This Architect does not accept the characteration of the costs as noted above and the cause of the change order.
CA-0001
CA-0001-C02
Henderson Corporation (The)
59
59
Change Order
4/13/2009
$46,768.00
HC Scope Change #59 - Providing the Underlayment for the Sports Flooring. This Architect does not accept the characterization of the costs as noted above and we dispute the cause of the change order.
CA-0001
CA-0001-P01
Mazzocchi Wrecking, Inc.
1
1
Change Order
5/2/2006
($104,382.48)
Credit for the unused contract allowance for demolitionof existing school - ECDC.
CA-0001
CA-0001-C02
Henderson Corporation (The)
38
38
Change Order
10/7/2008
$2,185.00
Hendersons Scope Change #43 - Relocate Sprinkler Riser in Multi-purpose room. Justification: Teh Sprinkler pipe was installed in teh multi-purpose as designed by teh Architect. A design was later issued for teh location of the scoreboard and the i
CA-0001
CA-0001-C02
Henderson Corporation (The)
10
10
Change Order
9/19/2007
$6,641.00
General Contractor claim for escalation on electrical scope changes due to suspension of the work.
CA-0001
CA-0001-C02
Henderson Corporation (The)
60
60
Change Order
4/20/2009
$2,815.00
Hendersons Scope Change #60 - Electrical Subcontractor Premium Time.
CA-0001
CA-0001-C02
Henderson Corporation (The)
16
16
Change Order
10/1/2007
$2,165.00
Henderson's Scope Change #31 - Removal of Uncovered Hazardous Lead (Purple Soil) Excavated and drum soil identified as hazardous lead and properly dispose.
CA-0001
CA-0001-C02
Henderson Corporation (The)
20
20
CCD-Authorization
2/26/2008
$400,000.00
Refer to Primavera
CA-0001
CA-0001-C02
Henderson Corporation (The)
27
27
Change Order
7/30/2008
$5,074.00
DESCRIPTION: Hendersons Scope Change #32 - Architectural Sketches SKA-25 through SKA-20 and SKA-29. Replacement of curtain wall and cafeteria glass by metal closures, two roof to curb expansion joint covers and metal coping cap, and the addition of
CA-0001
CA-0001-C02
Henderson Corporation (The)
3
3
Change Order
9/10/2007
$192,945.94
This change order is for additional construction work necessary for a two month extended schedule impact on general conditions required for the remediation of contaminated soil found on the construction site during excavation and for the escalation o
CA-0001
CA-0001-C02
Henderson Corporation (The)
58
58
Change Order
4/13/2009
$3,173.00
HC Scope Change #58 - Artroom Casework Revisions. This Architect does not accept the charaterration of the costs as noted above and we dispute the cause of the change order.
CA-0001
CA-0001-C02
Henderson Corporation (The)
25
25
Resolving CCD
8/1/2008
$72,000.00
Escalation costs due to the structural engineer (Schoor Depalma) issurance of Bulletin #5 & 6 that included revisions to sectors A,B.C D & E structure. Justification: During Schoor Depalmas review of the steel shop drawings they discovered some orror
CA-0001
CA-0001-C02
Henderson Corporation (The)
57
57
Change Order
4/13/2009
$7,503.00
HC Scope Change #56 - Added concrete step at the Music Room
CA-0001
CA-0001-C02
Henderson Corporation (The)
31
31
Change Order
8/4/2008
($23,534.00)
Domestic Water filtration system equipment purchase and installation. Justification: Water filtration allowance reconcilliation. Change Order given to Tony Sassine for review and signature on 6/16/08.cl Change Order given to Dhimant Dave for review
CA-0001
CA-0001-C02
Henderson Corporation (The)
14
14
Change Order
10/5/2007
$16,113.00
During the course of the Camden Early Childhood Development Center project, Henderson Corporation filed a claim against NJSDA seeking compensation in the aggregate amount of $1,574,405. An agreement was reached in which the NJSDA agreed to pay and H
CA-0001
CA-0001-C02
Henderson Corporation (The)
56
56
Change Order
4/20/2009
$12,652.00
Henderson s Scope Change #61 - Install gas meter adn sanitary ift station fence enclosures. JUSTIFICATION: It was necessary to enclose both the gas meter (PSE&G requirement) and sanitary lift station (public acces to the pump controller) which were
CA-0001
CA-0001-L01
Friedmutter Group
1
1
Change Order
3/26/2003
$819,400.00
Proposed design services will be based on development of a design build package for the construction of the new ECDC.
CA-0001
CA-0001-C02
Henderson Corporation (The)
15
15
Change Order
10/18/2007
$70,226.00
Henderson's Scope Change #30 - increased disposal rate due to soil contaminate levels exceeding ID027. Dispose of stockpile materials identified with high levels of Benzo
CA-0001
CA-0001-C02
Henderson Corporation (The)
43
43
Settlement
10/15/2008
$139,241.00
Description : Henderson Construction Corporation filed a claim seeking compensation for a 12 month delay in the project. NJSDA agreed to pay Henderson Construction Corporation and Henderson Construction Corporation agreed to accept $139,241.00 as fu
CA-0001
CA-0001-C02
Henderson Corporation (The)
28
28
Change Order
8/1/2008
$53,804.00
Drawing SW28.01 was revised to reflect the increased asphalt depth in Pine Sreet due to the City of Camden requirements. Justifications: The change is due to the City of Camden requirements. Change order given to Isaac Brown/Tony Sassine for review
CA-0001
CA-0001-C02
Henderson Corporation (The)
9
9
Change Order
10/18/2007
$69,161.00
General Contractor claim for subcontractor insurance coverage cost to transport contaminated soil form site. Justification: Contaminated soil discovered subsequent to contractors notice to proceed which required an upgrade to their insurance to tra
CA-0001
CA-0001-C02
Henderson Corporation (The)
34
34
Change Order
10/7/2008
$7,742.00
Description: Henderson s Scope Change #41 Providing 1 1/2" Acoustic deck in lieu of the 3" per documents. Justification The acoustic deck installed per the documents created a step to the roof deck transition where Sector E and D meet. RFI #138 was
CA-0001
CA-0001-C02
Henderson Corporation (The)
40
40
Change Order
10/7/2008
$5,328.00
Description: Hendersons Scope Change #46 - Rework fo already fabricated RTU-1 supply duct. Justification - RTU -1 supply duct had to be reworked due to steel revisions in Bulletin #5. The duct was fabricated prior to the issurance fo the bulletin
CA-0001
CA-0001-C02
Henderson Corporation (The)
44
44
Change Order
10/7/2008
$9,737.00
This amendment has been re-entered after cancellation because of error in numbering sequence with the system. BIC in court to Dhimant Dave to certify and forward to AP on 11/6/08.cl Description: Hendersons Scope Change #40 - Provide 33 Remote Access
CA-0001
CA-0001-C02
Henderson Corporation (The)
1
1
Change Order
9/8/2006
$2,181,644.00
Contractor is to provide all labor and material to excavate and dispose all contaminated soil in accordance with all work described below in accordance with Bulletin #3 dated April 10, 2006 prepared by Langan Engineering and Hillier Architecture plus
CA-0001
CA-0001-C02
Henderson Corporation (The)
50
50
Change Order
3/5/2009
$2,225.00
HS Scope Change 354 - Scoreboard Relocation and Conduit Re-routing Justification: Henderson installed the electrical conduit for the scoreboard per the construction documents. RMJM-Hillier later issued a sketch relocating the scoreboard and the con
CA-0001
CA-0001-L01
Friedmutter Group
3
3
Change Order
7/11/2007
($3,878.72)
The purpose of this 321 is to return unused funds from this Category 2 (A-Z) project to the general fund for other uses. Since this contract is an A-Z project, there is not a task order assigned.
CA-0001
CA-0001-C02
Henderson Corporation (The)
4
4
Change Order
2/13/2007
$2,201,210.00
This change order is for subcontractor's escalation labor and material costs resulting from the delays caused by remediation of contaminated soil found on the construction site.
CA-0001
CA-0001-C02
Henderson Corporation (The)
46
46
Resolving CCD
3/25/2009
$60,132.00
HC Scope Change #48 - Flexible Connections to address the building seperation for mechanical and plumbing piping at the firewall. Justification: Per the DCA requirements RMJM-Hillier issued documents for the installation fo flexible connections at t
CA-0001
CA-0001-C02
Henderson Corporation (The)
48
48
Change Order
3/5/2009
$2,784.00
HC Scope Change #51 - Custom Deep Sinks to meet ADA requirements. Justification: The casework drawings approved by RMJM-Hillier did not address Hendersons note that the sink depth may exceed ADA requirement. The sink were not ordered and RFI #179
CA-0001
CA-0001-C02
Henderson Corporation (The)
39
39
Change Order
10/7/2008
$2,161.00
Description: Hendersons Scope Change #45 - Extension of KEF -3 & EF-2 duct due to Kitchen Entry Soffit. Justification: Architectural and Mechanical drawings coordination during design failed to reveal a louver would be installed above the soffit th
CA-0001
CA-0001-C02
Henderson Corporation (The)
47
47
Change Order
3/5/2009
$38,000.00
HC Scope Change #49 - Add Tele/Data Room in Sector C(Room 166.1) which includes painted walls, a door, exhaust fan and associated ductwork, electrical and IT equipment. JUSTIFICATION: Per the CBOE requirements RMJM-Hillier issued documents for adding
CA-0001
CA-0001-C02
Henderson Corporation (The)
62
62
Change Order
10/27/2009
$1,788.00
HC Scope Change #65 - Removal of Magnetic Lock Hardware.
CA-0001
CA-0001-A01
Hillier Group Architecture, NJ, Inc.
00003
3
Change Order
6/20/2007
$182,236.00
Extended Construction Administration Services: The Design Consultant Construction Services was amended t ocover 11 months of extended Construction Administration services due to the suspension of construction as a result of contamination of soils at
CA-0001
CA-0001-C02
Henderson Corporation (The)
5
5
Change Order
9/18/2007
$4,242.00
General Contractor claim for relocating temorary fence entry gate.
CA-0001
CA-0001-C02
Henderson Corporation (The)
6
6
Change Order
10/11/2007
$60,305.00
General Contractor claim for additional cost of extended general conditions.
CA-0001
CA-0001-K07
ePlus Technology Inc
1
1
Change Order
2/3/2009
($916.25)
Amendment due to product not needed.
CA-0001
CA-0001-C02
Henderson Corporation (The)
26
26
Resolving CCD
8/1/2008
$760.00
CCD #4 is written to cover part of the Extended General Conditions Costs associated with hendersons Scope changes 29 & 33 for Sectors A, B,. C, D. The CCD #4 is herby reconciled. Justification: CCD #$ was written for $300,000 to cover a protion of t
CA-0002
CA-0002-L01
Maser Consulting P.A.
 
2
Change Order
3/22/2004
$16,237.75
Budget increase under contract CA-0002-L01 for the following: 1. Lump Sum Fee: Site Investigation per MC req. letter dated January 28, 2004.* 2. Lump Sum Fee: Laboratory per MC req. letter dated January 28, 2004* 3. Lump Sum Fee: Historica
CA-0002
CA-0002-L01
Maser Consulting P.A.
 
4
Change Order
7/11/2007
($81,762.55)
The purpose of this 321 is to return unused funds from this Category 2 (A-Z) project to the general fund for other uses. Since this contract is an A-Z project, there is not a task order assigned.
CA-0002
CA-0002-L01
Maser Consulting P.A.
 
1
Change Order
3/5/2003
$10,000.00
As outlined in NJEDA's scope
CA-0002
CA-0002-L01
Maser Consulting P.A.
 
3
Change Order
6/14/2004
$51,246.00
Budget increase under contract for the following: 1. Allowance increase: site investigation per MC req. letter 4/21/04 2. Allowance increase: site investigation per MC req. letter 5/14/04 3. Allowance increase: laboratory per MC req. letter 4/21/
CA-0003
CA-0003-L01
Van Note-Harvey Associates, P.C.
 
1
Change Order
9/3/2003
$13,600.00
Budget increase for Traffic and Air Quality Engineering allowance.
CA-0003
CA-0003-A01
Sykes O'Connor Salerno Hazaveh, PA t/a SOSH Arch.
 
3
Change Order
6/10/2005
$72,000.00
SOSH Architects is directed by SCC to perform revised services per revised site specifications: from four (4) blocks to three (3) blocks. Due to the timing of the revisions, this represents duplication of the design consultant's work and additional
CA-0003
CA-0003-L01
Van Note-Harvey Associates, P.C.
 
3
Change Order
7/11/2007
($128,012.33)
The purpose of this 321 is to return unused funds from this Category 2 (A-Z) project to the general fund for other uses. Since this contract is an A-Z project, there is not a task order assigned.
CA-0003
CA-0003-L01
Van Note-Harvey Associates, P.C.
 
2
Change Order
11/17/2003
$88,752.00
Project site was changed from one site to another site from a single property owner to multiple property owners.
CA-0003
CA-0003-A01
Sykes O'Connor Salerno Hazaveh, PA t/a SOSH Arch.
 
1
Change Order
2/6/2004
$3,877.50
Conceptual Site Feasibility Studies in response to Camden Redevelopment Agency's proposed Cramer Hill Redevelopment Project, consistent with attached (SOSH) letter dated 1/30/04 and fee schedule documented below. Architect-SOSH Architects Sr. Assoc
CA-0003
CA-0003-A01
Sykes O'Connor Salerno Hazaveh, PA t/a SOSH Arch.
 
2
Change Order
5/19/2004
$169,000.00
Revised Schematic Design Proposal.
CA-0004
CA-0004-K04
Dell
1
1
Change Order
8/25/2009
$388.16
Amendment is for a tax assessment due to the technology equipment being shipped to integrators warehouse located in New York because the school is not ready to receive the equipment
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
91
91
Change Order
5/29/2009
$9,000.00
The Contractor is directed to furnish and install 9 fire dampers, as required by code, in the following rooms: 151B(2) 150B(2) 147(1) 149(1) 144(3) For the sum of $9,000.00. (Nine thousand dollars) All work must be completed to the satisfact
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
37
37
Change Order
2/27/2009
$17,505.00
The Contractor was directed to add sheer wall reinforcing to all CMU walls in Block C that currently do not require sheer walls as per structural engineer’s response to RFI#H0057. The response requires all CMU walls in Block C that are shown with a f
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
77
77
Resolving CCD
6/25/2009
$39,683.00
Furnish all material labor and equipment to complete the following work: Furnish and install all additonal work shown on the amended drawings and associated with Specification Section No. 16400, Distribution Ssytem adn Specification No. 16750 Fire Al
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
129
129
Change Order
12/16/2009
$21,960.00
Ernest Bock & Sons #30-R This Change Order is for Asphalt material price increase frominstallation date shown on the approved baseline schedule (Oct. 2008) to the actual installation of date (Aug. 2009). For the suml of $21,960.00 (Twenty one thousan
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00015
15
Change Order
9/3/2008
$2,680.00
On 5/28/08 the General Contractor submitted RFI #068. This RFI requested clarificaton from teh engineer of record on deck spans and deck gauge requirements. Existing contract documents require the contractor to use 22 gauge "B" deck. The contractor
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
112
112
Change Order
8/27/2009
$96,717.00
On 7/16/09 Mr. Hasmukh Shah of the NJSDA met with Ernest Bock & Sons and Simplex Grinnell (sprinkler contractor) to review EBS COR#056 for $102, 559. Mr. Shah reviewed the information provided by the Contractor. Mr. Shah requested additional back-up
CA-0004
CA-0004-K02
Hewlett-Packard Company
1
1
Change Order
7/31/2009
($5,375.00)
Amendment due to Camden district techonologists provided printer specs of an HP printer, P1005, that did not include a built in network interface. In light of their error, the district has requested that the printer model be changed to an HP P1505N.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
68
68
Change Order
4/27/2009
$11,522.00
The Contractor will furnish all material, labor and equipment necessary to complete all work shown on Gensler & Associates’ Sketch SKA-29, dated October 17, 2009. This work includes deleting some masonry, furnishing and installing a trench drain and
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
109
109
Change Order
8/26/2009
$25,710.00
The Contractor was directed to make the following changes to the Contract. This work has been completed. On 7/16/09 Mr. Hasmukh Shan of the NJSDA met with the contractor to review these open Change Orders. The following Change Order requests were a
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00022
22
Change Order
12/8/2008
$40,684.00
The General Contractor is directed as follows: Furnish all material, labor and equipment necessary to complete the following work to the satisfactory of the NJSDA, Gensler and Hill International, Inc. 1. Furnish and install (1) gym dividing curtain
CA-0004
CA-0004-K10
Hewlett-Packard Company
1
1
Change Order
8/24/2009
($10,320.00)
Amendment due to cancellation of purchase order due to back order of Part II CB413A#ABA
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
111
111
CCD-Authorization
9/9/2009
$80,000.00
Ernest Bock & Sons is directed to provide all material, labor and equipment necessary to complete the following work: COR#136 �???�??�?�¢?? Booster Heater Changes $8,010.00 COR#141 �???�??�?�¢??
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00010
10
Change Order
7/22/2008
$67,906.00
The General Contractor is directed to furnish all material, labor and equipment necessary to repave 8th Street between Woodland Ave. and Bulson Street per the attached Hill International Sketch. The Contractor is directed to remove the remaining road
CA-0004
CA-0004-K11
Dell
1
1
Change Order
9/10/2009
$235.63
Amendment for tax assessment due to the technology equipment being shipped to the integrator's warehouse located in NY because school is not ready to receive the equipment
CA-0004
CA-0004-K12
Dell
3
3
Change Order
1/14/2010
$367.16
Addition due to the delivery of purchased items to Integrator's Ronkonkoma, NY facility, which resulted in the addition of NY taxes.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00024
24
Change Order
12/24/2008
$8,524.00
BIC to Claire for review and approval on 12/16/08.cl BIC to Dhimant for review and approval on 12/22/08.cl The contractor is directed to furnish all material, labor and equipment necessary to complete the following work: 1) Additional signage per
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
79
79
Change Order
4/28/2009
$10,773.00
The NJSDA agree and pre-approved the Contractor working on Saturday March 7, 2009. The Masonry Contractor had 19 masons and 11 laborers on site (8 hours each) placing brickwork at the exterior west wall of Block A. This Saturday work kept masonry
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
120
120
Resolving CCD
12/17/2009
$33,586.00
In CCD#15, Change Order #099 the NJSDA approved $200,000 for Premium Time (Saturday,Sunday & 2nd Shift). Please see attached CCD. Ernest Bock & Son forwarded the following backup for premium time work: COR#120 - Premium Time incurred for Jun
CA-0004
CA-0004-K07
Dell
1
1
Change Order
8/25/2009
$1,142.81
Amendment is for tax assessment due to the technology equipment being shipped to integrators warehouse located in New York because the school is not ready to receive the equipment
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
121
121
Resolving CCD
12/17/2009
$18,272.00
In CCD#21, Change Order #106 the NJSDA approved $150,000 for Premium Time (Saturday, Sunday & 2nd Shift). Please see attached CCD. Ernest Bock & Son forwarded the following backup for premium time work: COR#146 - Premium Cost from 7/26/09 to 8
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00004
4
Resolving CCD
1/17/2008
$20,722.00
In CCD#2, the Contractor was directed to furnish all material, labor and equipment necessary to excavate and remove from site the buried foundation debris of former houses on the site. (The debris from houses demolished many years ago was placed in t
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
38
38
Change Order
2/26/2009
$10,606.00
On 9/5/08 PSE&G and Hill met on site to review the location of the gas meter shown on the contract drawings. PSE&G informed Hill that the meter cannot be located where shown. Hill & PSEG reviewed alternated locations. PSEG also informed Hill that fen
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
116
116
Resolving CCD
11/10/2009
$2,361.00
CCD Notification CA-0004-C01 CO#116 Close Out CCD #17 in the amount of $2,361.00 for CCD #17 Change Order #101 dated 6/24/09 the NJSDA approved $75,000 to complete the following work. -Misc MEP work -Misc Carpentry (soffits, fascias, column) -Additio
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
103
103
Change Order
7/15/2009
$16,155.00
The Contractor was directed to furnish and install the following work: CCR# 0078 – COR#110-The Contractor was directed to provide tamper resistant receptacles in all Pre-K and K classrooms, as noted in Bulletin #2. (Amended drawings)
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
127
127
Change Order
1/23/2010
$13,087.00
The General Contractor was directed by the NJSDA to purchase new panic hardware for doors #198B,199B,298 and 299. The Contractor was also directed by the NJSDA to purchase bottom rods for the exiting Von Duprin hardware. The Contractor purchased adn
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
93
93
Change Order
6/4/2009
$36,609.00
The NJSDA directed Ernest Bock & Sons to work on Saturdays. The Contractor worked the following Saturdays: 4/18/09, 4/25/09, 5/2/09, and 5/16/09. The Contractor provided the following COR for the permimum time. COR #96 - dated 5/18/09 $20,288.00
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
122
122
Resolving CCD
11/30/2009
$18,496.00
In CCD #8 The Contractor was directed to proceed withthe additonal plumbing work at the Pre-K bathrooms. Hill signed daily time tickets for this work. The actual total costs associated with this work is as follow: Eagle PCM 7005-015-1=$13,025.00 Ea
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
0050
50
Change Order
4/27/2009
$6,457.00
The Contractor provided structural steel erection labor past the June 30, 2008 date of their union labor contract. The structural steel erection contractor provided 1,085 hours after the June 30, 2008 date. These additional hours are at a higher r
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
47
47
CCD-Authorization
3/27/2009
$100,000.00
The Contractor is directed to provide all material labor and equipment necessary to complete the following work noted on the amended DCA drawings and specification section #16723, Public Address System. For the sum of $100,000.00
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
46
46
Change Order
3/16/2009
$7,494.00
Furnish and install prefinished aluminum panels per Gensler’s response to RFI #00140 and Proposal Request #0024. For the sum of $7,494.00 (seven thousand four hundred ninety-four dollars). All work to be completed to the satisfaction of Gensler Ass
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
102
102
CCD-Authorization
7/21/2009
$538,876.00
Refer to Primavera
CA-0004
CA-0004-K01
Centre Business Products Inc
1
1
Change Order
11/24/2009
($163,406.00)
Company names has changed from Centre Business Products to Xerox Audio Visual Solutions effective 8/3/09. To be able to process the invoices for this PO, we are canceling this Purchase Order and issuing a new PO # CA-0004-K01 under the new company n
CA-0004
CA-0004-K12
Dell
1
1
Change Order
12/23/2009
($1,799.98)
Reduction due to canceling of 37" TV item
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
60
60
Change Order
4/27/2009
$49,085.00
Hill International, Inc. notified the New Jersey Schools Development Authority that Kid-Course Playground Equipment is not part of Ernest Bock & Sons’ existing contract with the NJSDA. This playground equipment is shown as part of Phase 2 work (Demo
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
96
96
Change Order
6/11/2009
$34,680.00
The NJSDA directed the Architect to provide sketches for additional work in stairwells A, B, C & D. The Architect also provided sketch to close off above bathroom CMU partitions.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
90
90
Change Order
6/5/2009
$37,887.00
Furnish and materials, labor and equipment necessary for a water filtration system as noted in Gensler A.E. Bulletin #6 and Ernest Bock and Sons COR #089 dated 5/11/09. For the sum of $37, 887. (Thirty seven thousand, eight hundred eighty seven do
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
108
108
Change Order
8/21/2009
$39,404.00
On 7/16/09 Mr. Hasmukh Shah of the NJSDA met Ernest Bock & Sons, Hill International, Inc. to review open Change Orders. Mr. Hasmukh Shah approved Ernest Bock & Sons proposed Change Orders at the values noted below. Ernest Bock & Sons COR# 11 -
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
0036
36
CCD-Authorization
2/20/2009
$6,000.00
The Contractor is directed to furnish and install all structural steel work as noted on CEC’s Sketch SK37 dated 1/19/09 and CEC-SK36R 1/05/09. For the sum of $6,000.00
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00007
7
Change Order
6/24/2008
($5,382.00)
Amendment forwarded to CMD for review as per Dhimant Dave SPM on 4/21/08.cl Description: The General Contractor is directed to furnish all material, labor and equipment necessary to complete all changes to the contract documents noted on drawings E
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
115
115
CCD-Authorization
10/16/2009
$43,000.00
10-07-09-BIC to Tony S. for review and signature authoi The Contractor is directed to proceed with the following work: 1. Add supply air in Corridor #184 per Gensler Sketch (EBS COR #144)
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
101
101
CCD-Authorization
6/25/2009
$75,000.00
CO#101 - CCD 17 - In a meeting on June 16, 2009 (Eric Goldmen, Vic Perla, Tony Sassine SDA, Tom Bock, Bob Eagleson, John Lemly EBS, Joe George, Joe Donnelly Hill International, Inc.) Hill was directed by the NJSDA to write up a CCD for $75,000. Th
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00001
1
CCD-Authorization
9/12/2007
$2,500.00
Furnish all material, labor and equipment to install a 20' wide temporary asphalt apron from 9th street to the existing school fence adjacent to the existing well. Provide a 20' long x 4" diameter steel pipe at curb to allow for proper movement of r
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
95
95
Change Order
7/21/2009
$241,467.33
The General Contractor�????�???�??�?�¢??s existing substantial completion date is April 20, 2009. This Change Order adds 102 calendar days to the April 20, 2009 date. The revised substantial completion date is July 31, 2009. The cost to exte
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
0033
33
Change Order
2/17/2009
$4,144.00
Furnish all material, labor and equipment necessary to complete the following work (EBS COR #031) 1. Provide and install a dedicated circuit for the wheel chair lift at the stage in accordance with Concord Engineer’s Submittal comment (Attached)
CA-0004
CA-0004-L13
Calvin Brooks
1
1
 
10/9/2008
($16,380.00)
Calvin Brook's eligibility expired on June 11, 2005; therefore, the current TRS obligation of $16,380.00 in SIMS is being deobligated.
CA-0004
CA-0004-M01
Hill International, Inc.
2
2
Change Order
7/23/2009
$0.00
Section 3.1.3 of contract #CA-0004-M01 between SDA and Hill International shall be deleted in its entirety and replaced with the following: 3.1.3 CM shall submit invoices for its services monthly upon commencement of construction of the project. CM
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00025
25
Change Order
12/24/2008
$4,490.00
BIC to Claire for review and approval on 12/16/08.cl BIC to Dhimant Dave for review and approval on 12/22/08.cl Provide labor and equipment to excavate and stockpile trash. Place clean fill and provide test holes throughout site as directed by Hill I
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
123
123
Resolving CCD
12/7/2009
$21,707.00
In CCD #24 Change Order 3113 the NJSDA approved $60,000.00 to complete the following work. Ernest Bock & sons completed the following work and forwarded back-up. COR#178 - Additional Carpentry work performed $29,495.00 COR#150 - Additional
CA-0004
CA-0004-K05
Dell
1
1
Change Order
8/25/2009
$13,064.12
Amendment is for a tax assessment due to the technology equipment being shipped to integrators warehouse located in New York because the school is not ready to receive the equipment
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
110
110
Change Order
8/21/2009
$11,377.00
Ernest Bock & Sons is directed to provide all material, labor and equipment necessary to complete the following work. 1. Furnish and Install wall pads in gym per PR#060, Gensler Sketch SKAâ??53 dated 7/17/09, and EBS COR#130.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
48
48
CCD-Authorization
3/12/2009
$73,000.00
The contractor is directed to provide all material, labor and equipment necessary to add a perimeter security system as noted in Bulletin 32 ((Amended Drawings and Specification Section 16710). For the sum of $73,000.00. Justification: The amended dr
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
43
43
Change Order
3/10/2009
$39,246.00
The Contractor is directed to furnish and install all material, labor adn equipment necessary to complete the changes to the Pre-K and K bathrooms per teh revised sketches by Gensler Associates. Hill forwarded Proposal Request #20 on 11/17/08. Thi
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
0119
119
Resolving CCD
12/7/2009
$333.00
In CCD#23, Change Order #111 the NJSDA approved $80,000. Please see attached CCD. The Contractor has completed the following work. This work was inspected and approved by the NJDCA. This work includes the following: COR# 136- Booster Heater Cha
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
44
44
Change Order
3/10/2009
$14,380.00
The Contractor will provide all material, labor and equipment necessary to add a footing, foundation and CMU wall between the electrical transformer and diesel generator per the CMX Sketches dated 3/3/08 and 3/13/08 attached. Per EBS COR#18 This wo
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
52
52
CCD-Authorization
3/25/2009
$66,000.00
Furnish and install all Specification Section 16770, Telecommunication System work, as required in the specification and as shown on the amended drawings. For the sum of $66,000.00 (sixty-six thousand dollars).
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
53
53
Change Order
4/7/2009
$10,014.00
On May 13, 2008, the NJDCA shut down this project because they had not received signed and sealed foundation sketches, as requested. Ironworkers, crane operator and crane rental were affected. The NJSDA, Hill International and Consulting Engineers
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
105
105
CCD-Authorization
7/22/2009
$75,000.00
CCD Notification CA-0004-C01 CO#105 CCD#20 in the amount of $75,000.00. On July 14, 2009 the NJSDA directed Hill International, Inc. to issue a CCD for $75,000.00. This CCD will cover additional costs incurred due to RFI responses and /or DCA requi
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
30
30
CCD-Authorization
1/30/2009
$75,000.00
The Contractor is directed to furnish al materials labor and equipment required for all switchgear revised as noted in "Bulletin #2 (Amended Drawings) and forwarded to the General Contractor on 9/29/08. This work inclused but not limited to addition
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00020
20
Change Order
11/25/2008
$265,000.00
Ernest Bock & Sons (EBS), the General contractor, was given Notice to Proceed on June 28, 2007. EBS Approved Baseline Schedule shows footings starting on September 25,2007. However, a building permit was not received until November 7, 2007. Additi
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00012
12
Change Order
9/3/2008
$380.00
The Contractor is directed to make the necessary changes to the structural steel base plate at column C.2 - 14.1 as shown on the structural engineer's (CEC) sketch SK12 dated 3/20/08. This change is due to the existing field condition and a conflict
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
28
28
Change Order
2/20/2009
($66,441.00)
The Contractor is directed to delete the original contract required 600KW natural gas generator and furnish and install a 500 KW diesel generator per Gensler Bulletin #1. The 500 KW diesel generator will include as LSI adjustable breaker and a criti
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
94
94
Change Order
6/1/2009
$12,962.00
Furnish all material, labor and equipment necessary to complete the following work noted per the folloing CORs: EBS COR# 85-R Dated 5/20/09 Add Boc Header/Bracing at front stage wall per Architects response to RFI#065. EBS COR# 98 Dated 5/18/09 - Add
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00011
11
Change Order
9/10/2008
$7,349.00
Over the June 20-23 weekend, the H. B. Wilson project had material stolen from the site. The thief gained access to the site by cutting a hole in the fence along the north property line. Stored structural steel angles were removed from the site. The
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
0029
29
Change Order
2/13/2009
($588.00)
The Contractor provided COR #053 as requested in RFI #135. The Contractor is directed to Delete the installation of door, frame, and hardware for door 185B and associated electrical work for the sum of CREDIT ($588.00). Five hundred eighty eight dol
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00013
13
Change Order
9/3/2008
$1,885.00
On 4/10/08 the General Contractor forwarded RFI #0078. This RFI noted that drawing M02.02B does not show all end of branch loop bypas in Block B-Room 227 and asked if one would be required. The Design Consultant (Gensler) provieded sketch CSK-M1 dat
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00005
5
Change Order
1/30/2008
$70,000.00
Description: Furnish all material, labor and equipment necessary to complete all work noted on the civil engineers (CMX) site visit memorandum letter and sketch dated Jan. 10, 2008 and email of Jan. 14, including associated sketches which show the
CA-0004
CA-0004-M01
Hill International, Inc.
7
7
Change Order
1/19/2010
$239,985.74
1. ACTUAL COST to provide extended adn additional CM services for HB Wilson School Project due to a delay in the date of Substantial Completion of the project. The contractural date for Substantial Completion was April 20, 2009. The actual date of
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
113
113
CCD-Authorization
8/27/2009
$60,000.00
The Contractor is directed to furnish and install the following: Install metal studs, drywall, caulking or pre fabricated aluminum corners as required to “Close Off” the gap between structural steel columns and exterior CMU wall per revised sketch
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
92
92
Change Order
5/29/2009
$6,530.00
1. Complete all work as required per EBS COR#0087. This work adds manual pull handles at both smoke hatches located above the stage. For the sum of $3,312.00. (Three thousand three hundred twelve dollars). 2. Furnish and install a 4” water mete
CA-0004
CA-0004-P01
Site Contractors Inc.
1
1
Change Order
9/13/2005
($105,500.00)
CCR1: Credit unused allowance funds CCR2: Credit for utility disconnects provided by others
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
114
114
Change Order
10/20/2009
$156,517.00
On 8/20/09, Hasmukh Shah of the NJSDA met with Bob Eagleson, (EBS) Henry Stronski (Eagle) and Joe Donnelly (Hill International, Inc.) to review Ernest Bock & Sons Change Order Request #37 dated 9/5/08. This COR is for material and labor, cost increas
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
73
73
CCD-Authorization
4/27/2009
$15,000.00
The Contractor will rovide all material labor and equipment necessary to complete the follwoing work not currently required by contract: 1. Framing at 9th Street canopy per Gensler & Associates attached sketch. 2. Gypsum board/metal framing at pier
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
62
62
Change Order
4/30/2009
$5,547.00
Furnish all material, labor and equipment necessary to complete the additional work noted in the following Ernest Bock & Sons’ Change Order Requests: • COR #051 Plastic Laminate Caps Add $372.00 • COR #071 Condensate Pum
CA-0004
CA-0004-K09
Dell
1
1
Change Order
8/25/2009
$1,985.60
Amendment is for a tax assessment due to the technology equipment being shipped to integrators warehouse located in New York because the school is not ready to receive the equipment.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00021
21
CCD-Authorization
11/26/2008
$10,000.00
The Contractor is directed to provide a Proposal Request for the following Structural steel work: Install approx. 90 Nelson Studs on the top and bottom of the existing structural steel beams in stairwells B & D. Cut back the existing 2nd floor roof
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
0032
32
Change Order
2/17/2009
$15,875.00
Furnish and install all material, labor and equipment necessary to complete all work as noted per Hill’s Proposal Request #018 and Gensler’s Bulletin #4. This work includes, but not limited to the following: 1) Furnish & install scoreboard in gym
CA-0004
CA-0004-Q02
Interior Systems Inc.
1
1
Change Order
5/1/2009
($1,197.18)
Cafeteria tables and benches
CA-0004
CA-0004-K02
Hewlett-Packard Company
2
2
Change Order
8/25/2009
$465.58
Amendment for tax assessment due to the technology equipment being shipped to the Integrator's warehouse located in New York
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
78
78
Resolving CCD
4/27/2009
$636.00
CCD#5 for $10,000 was previously forwarded to the General Contractor. The General lContractor performed Additonal structural steel work at stairs B, and D and at teh top of teh elevator shaft per teh structural engineers sketches. The Contractor f
CA-0004
CA-0004-K06
Dell
1
1
Change Order
8/25/2009
$2,471.29
Amendment is for a tax assessment due to the technology equipment being shipped to integrators warehouse located in New York because the school is not ready to receive equipment
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00055
55
Change Order
3/10/2009
$42,192.00
The Contractor is directed to furnish all material, labor and equipment necessary to complete all additional work required in Specification Section 11130-RF Distribution System- Cable TV shown on the Amended Drawings (Bulletin #2) and per the typical
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00008
8
CCD-Authorization
4/14/2008
$8,000.00
CCDA #3 - Ext. Active Sanitary Line
CA-0004
CA-0004-K08
Dell
1
1
Change Order
8/25/2009
$141.20
Amendment is for a tax assessment due to the technology equipment being shipped to integrators warehouse located in New York because the school is not ready to receive the equipment
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00006
6
Change Order
3/5/2008
$2,258.00
Description: Furnish all material, labor and equipment necessary to relocate the existing Pre-K and Kindergarten drop off at Woodland Avenue as shown on the Civil Engineers (CMX) Sketch dated September 26, 2007. FOR THE SUM $2,258.00. This relocati
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
0031
31
Change Order
2/13/2009
$4,644.00
Provide all material, labor and equipment necessary to complete all additional work per the NJSDAs Proposal Request #0014 dated 9/29/08. This work includes, but not limited to, the following: All additional HVAC duct work in the fire pump room, ele
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
70
70
Resolving CCD
6/22/2009
$25,745.00
Furnish all material, labor and equipment to complete the following work: Furnish and install all Specification Section No. 16770, Telecommunication System work noted in Bulletin No. 2 (Amended Drawings) and detailed in Ernest Bock & Sons Change Orde
CA-0004
CA-0004-K03
Dell
1
1
Change Order
9/30/2009
$4,460.71
Amendment for tax assessment due to the technology equipment shipment to the integrators warehouse (Computer Logic, Inc) located in NY. Since the school site was not ready for acceptance of the equipment. Adjustments were made by Dell as per credit
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
106
106
CCD-Authorization
8/3/2009
$150,000.00
After July 30, 2009 meeting Hill International, Inc. was directed to write up a CCD for $150,000.00 This CCD is for additonal cost associated with the rate diffeential associated with working Saturday, Sunday or 2nd shift. These additional costs inc
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
99
99
CCD-Authorization
7/28/2009
$200,000.00
In a meeting on June 11, 2009, (EBS, NJSDA and Hill International) all parties agreed that the NJSDA will pick up all additional costs (differential) associated with working Saturday and/or second shift. These additional costs include additional supe
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00003
3
Resolving CCD
1/18/2008
$698.00
The CCDA was entered into Expedition as a final change order in the amount of $2,500.00. The CCDA is in SIMS as change record #1. This final change order should resolve CCDA1 in SIMS In CCD#1, the Contractor was directed to furnish and install a te
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00018
18
CCD-Authorization
8/26/2008
$7,500.00
CMU wall
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
41
41
Change Order
2/27/2009
$2,356.00
Refer to Primavera
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
118
118
Resolving CCD
11/10/2009
$11,400.00
CCD#20/Change Order #105 dated 7/24/09 the NJSDA approved $75,000. Please see attached CCD. TOTAL: $75,000.00 The Contractor has completed the following work. This work was inspected and approved by the NJDCA. This work includes: COR#155 - Misc.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00014
14
Change Order
8/29/2008
$2,345.00
On 5/28/08 the Gensler Constractor submitted RFI #025. The Constractor requested the Architect review and provide direction on the additional structural steel needed to support masonry at the roof transition. The architect and engineer reviewed te
CA-0004
CA-0004-G01
TRC Environmental Corporation/Energy Services
 
1
Liquidated Damages
2/1/2010
($12,921.00)
Smart Start Rebate
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
0034
34
Change Order
2/17/2009
$4,387.00
Furnish all material, labor and equipment necessary to install 4 fire dampers at the second floor deck at the following locations as noted on the Amended Permit Drawing M-01.01B dated 7/24/08. 2 Fire dampers required at approx. Column line 3 & D
CA-0004
CA-0004-M01
Hill International, Inc.
5
5
Change Order
8/9/2009
$3,569.00
H.B. Wilson Project Allowance to provide second shift superintendent per NJSDA request dated 6/16/09. (In a June 16, 2009 meeting with E. Goldman, V. Perla, T. Sassine, J. Lemly, B. Eagleson, J. George., J. Donnelly, EBS informed teh SDA that they wo
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
107
107
CCD-Authorization
8/5/2009
$50,000.00
Ernest Bock & Son is directed to provide the following additonal site work. Provide all material, labor, delevery and spread & equipment necessary to complete teh following approx. 800cy certified clean topsoil. Scrape previsouly spread topsoil at fr
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
126
126
Change Order
12/16/2009
$34,000.00
On 11/13/09 a meeting was held in Hills project office. Bob Eagleson (EBS) Tony Sassine (NJSDA) Joe Van Story (NJSDA) and Joe Donnelly (Hill) were attendees. We discussed the following "Open structural steel Change Orders. COR #073 Added Masonry A
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00009
9
Change Order
8/22/2008
$31,511.00
The General Contractor is directed to furnish all labor as noted on the Approved As Noted finished Hardware Schedule. (Attached). This Change Order is a result of the hardware consultants comments/changes/requirements on the approved hardware sched
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
125
125
Change Order
12/4/2009
$71,404.00
The Contractor was directed by the NJSDA to furnish all material and labor necessary to open the new school by September 7 20009. The contractor worked overtimle from 8/25/09 to 9/2/09 to complete the project. The Contractor provided additonal securi
CA-0004
CA-0004-M01
Hill International, Inc.
00001
1
Change Order
3/25/2009
$192,625.02
Description: Provide extended CM services for HB Wilson project from original (12/13/08) completion date to new (4/20/09) completion date. (159 calendar days) NJSDA issues an extension of time to the general contractor to 4/20/09 due to to change cir
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
97
97
Change Order
6/29/2009
($601.00)
Provide all materials, labor and equipment for all work required in Ernest Bock & Sons Change Order Request(s): • COR#100 – Change fence along northern property line to chain link. Add chain link gates at Trash Room
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
35
35
Change Order
2/17/2009
$980.00
Furnish & Install 2 Knox Boxes per Ernest Bock & sons COR#074. Part #3274 Dark Bronze, Recessed. Justification: Fire department Knox Boxes are required under the existing contract. The City of Camden Fire Marshall will require Knox.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
130
130
Change Order
1/25/2010
$9,107.00
Ernest Bock & Sons COR #193: The general contractor was directed by the NJSDA to re-clean the new school before August 31st. The cleaning contractor moblized manpower and re-cleaned the new school building on Sunday August 30, 2009. This change Orde
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
98
98
Change Order
6/29/2009
$11,320.00
Furnish all material, labor and equipment to add an IDF Cabinet at the Auditorium stage per engineer’s revised response to RFI 0039 and Proposal Request #0039. This proposal includes all work noted in the RFI and Proposal Request and all work noted i
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00016
16
Change Order
10/21/2008
$20,223.00
Description: The General contractor is directed to furnish and install all material labor and equipment necessary to complete all work noted on Gensler Associates sketch #SKAA-001 dated 3/31/08. This work is required by code. All work to be comple
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
42
42
CCD-Authorization
3/5/2009
$20,000.00
Furnish and install all material, labor and equipment necessary to complete the revisions to the Pre-K and K bathrooms, as required by the NJDCA. The work includes, but not limited to additional water lines, drain lines, addditional sink, hangers c
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
49
49
Resolving CCD
3/25/2009
$5,399.00
Description ] The contractor is directd to furnish and supply all switchgear and panel board per teh latest reviewed and approved submittlas. These changes were required to meet life safety codes. This Changel Order will close out CCD#006/CO#0030
CA-0004
CA-0004-M01
Hill International, Inc.
6
6
Change Order
7/30/2009
$27,551.00
1. ALLOWANCE to provide additonal CM services for H.B. Wilson School Project by providilng Supervison for SDA Authorized overtime for the project. (It is expected that the contractor will work Saturdays through the remainder of teh project and the
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00023
23
Change Order
12/8/2008
$1,478.00
Furnish all material, labor and equipment necessary to provide and install one 30” wide cast iron manhole cap, in lieu of the previously approved concrete cap, at the exterior grease trap for the sum of $1,478.00 per EBS Change Order Request #047 da
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00017
17
Change Order
9/19/2008
$916.00
Description: Provide all material labor and equipment to install 4" cast iron pipe in lieu of 4" PVC where pipe is located in a phenum chase for teh sum of $916.00. Complete all work to teh satisfaction of the NJSDA, NJSCC, Gensler Associates and Hi
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
69
69
Resolving CCD
6/25/2009
$37,429.00
Furnish all material labor and equipment to complete the following work: Furnish and install a complete public address system per the Amendmended Drawings and Specification Section No. 16732 and as detailed in Ernest Bock & Sons Change Order Request
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
104
104
CCD-Authorization
7/22/2009
$8,662.00
Furnish and instll all white boards, marker boards, tackboards as shown on Bulletin #2 (Amended Drawings). For the sum of - $8,662.00 (Eight Thousand Six hundred sixty two dollars) This CCD was reviewed by ;Mr.l Hasmukh Shah of the NJSDA on 7/17/09.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
75
75
Resolving CCD
7/6/2009
$28,554.00
Furnish all material labor and equipment to complete the following work: Furnish and install all additional work shown in Bulletin No. 2 (Amended Drawings) and associated with Specification No. 16710 Perimeter Security System and noted in Ernest Boc
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00026
26
Change Order
12/24/2008
$3,017.00
BIC to Claire for review and approval on 12/16/08.cl BIC to Dhimant for review and approval on 12/22/08.cl Furnish and Install 7 (seven) ceiling mounted electrical Exit Signs in the administration area per the electrical engineer’s sketch dated 11-11
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00056
56
Change Order
3/18/2009
$50,390.00
The existing contract drawings and specification requested the contract to furnish and install 16 CCTV security cameras. The amended drawing (Bulletin #2) added 32 security cameras to the project. These additional security cameras are shown on the
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
61
61
Change Order
4/27/2009
$7,269.00
Provide all material, and equipment necessary to complete all work noted on Gensler & Associates Sketch SKA-35, rev. 1, datd March 26, 2009. The work includes, but is not limited to the following: add vision panel glazing CMU lintels gypsum drywall
CA-0004
CA-0004-L01
French & Parrello Associates, P.A.
2
2
Change Order
3/14/2005
$83,040.47
Additional services including the remediation of the on-site soil contamination, the documentation of the asbestos containing material and lead based paint within section 3 to satisfy the DCA submission requirements, abatement monitoring and administ
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00027
27
Change Order
1/22/2009
$2,627.00
Provide all materials, labor and equipment necessary to provide a watertight assemble at 6 expansion joint locations at the perimeter of the building. The contractor will furnish and install a closed cell backer rod (approved by Gensler Associates) a
CA-0004
CA-0004-L01
French & Parrello Associates, P.A.
1
1
Change Order
3/22/2003
$10,000.00
HB Wilson ES - Site feasibility investigations. Traffic and air quality engineering analysis as revised and added to the current consultant's SOW.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
58
58
CCD-Authorization
4/27/2009
$10,000.00
The Contractor is directed to remove all installed sprinkler pipe currently located under the HVAC unit ventilators throughout the first floor, Blocks A, B and C. Re-route the sprinkler pipe above or around the unit ventilators as required. Meet al
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
51
51
CCD-Authorization
3/27/2009
$105,000.00
Furnish and install all additional electrical work associated with Specification Section 16400, Distribution System, and Specification Section 16750, Fire Alarm system. This additional work is a result of changes noted on the amended drawings.
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
124
124
Change Order
11/19/2009
$11,043.00
Furnish all material labor and equipment necessary to complete the following work: Add Exit Devise Trim VD990LDT at the following doors 1 at Door 189A 1 at Door 183D 2 at Door 136A 2 at Door 188A Add a double cylinder, cylindrical lockset at door #
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00001
2
CCD-Authorization
10/16/2007
$49,480.00
Excavate and remove from the site the recently discovered buried foundation debris. The GC will follow the written directions provided by CMX, the civil engineer for this project. The GC will import soil, as required, to repolace the removed founda
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00019
19
Change Order
10/21/2008
$26,120.00
Description: Provide all material, labor and equipment necessary to remove existing concrete and install new burb in 8th street per the attached sketch. Work includes but not limited to the following: 1. Saw cut adn remove existing curb (approx. 25
CA-0004
CA-0004-C01
Ernest Bock & Sons, Inc.
00057
57
Change Order
3/20/2009
$7,236.00
Delete all previously approved 8’ long exterior wall lighting fixtures and replace with wall packs per the Architect’s revised drawing and specification. Add breaker, conduit, MC cable and fixtures required to light exterior wall-mounted school sign
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
61
61
CCD-Authorization
6/25/2009
$350,000.00
Increase in contract price to cover the costs for premium time labor hours for acceleration in lieu of time extension from impacts resulting from Bulletin No. 1 and Bulletin No. 4. The scope includes premium time rate differential for trade staffing
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00064
64
Change Order
7/20/2009
$8,149.00
Costs for all labor material and equipment for revisions alterations credits etc. to perform revisions to the roof deck closure on the main roof adjacent to the tower, per instructions conveyed under RFI-198 and CEC sketches SK-40R2 adn SK-42.
CA-0005
CA-0005-L01
JCA Associates, Inc.
3
3
Change Order
7/18/2003
$16,000.00
Budget increase under the contract for reimbursable allowances.
CA-0005
CA-0005-M01
Hill International, Inc.
00004
4
Change Order
9/18/2009
$89,592.00
Provide extended and additional CM services for Dudley School Project due to a delay in the completion date of the project. The delay was caused by Bulletin no. 1 (change of scope form construction bid set to DCA permit set) and Bulletin no.4 (additi
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00043
43
Change Order
6/11/2009
$4,247.00
6-5-09 CTO recv & approved, however due to Expedition #-ing issue, CTO has to meet w/ Lillie to resolve before the input of the change order. cto 6-8-09 CTO met w/ Lillie and resolved the Expedition #-ing issue; JW sign-off; 6-9-09 CTO approved; BIC
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00048
48
Resolving CCD
8/4/2009
$0.00
This Resolving change order for the Bulletin #4 Direct Construction Costs is necessary because: Pre-bid Addendum No.4 removed all items contained in the "USAC Schools & Libraries Draft Eligible Services List Schools and Libraries Support Mechanism f
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
026
26
Change Order
3/26/2009
$15,583.00
CCR-026: Auditorium foundation walls changed from CIP concrete to CMU - Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. for all material and labor to delete cast-in-place foundation walls in the Audit
CA-0005
CA-0005-K08
Dell
1
1
Change Order
8/25/2009
$388.16
Amendment is for a tax assessment
CA-0005
CA-0005-K02
Dell
1
1
Change Order
8/26/2009
$1,985.60
Amendment is for a tax assessment
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
69
69
Resolving CCD
11/2/2009
$23,088.00
Water Filtration System to be built per Bulletion #8 (dated 4/13/09 in Spec section 15471 and sketches SK-P25 and P24), as well as Bulletion #8 supplement #1-R1 revised 6/19/09 (Sketch SK-P25A-R1) Justification Reason for this change: Per Bulletin
CA-0005
CA-0005-L02
Fidelity National Title Insurance Company
1
1
Change Order
7/12/2007
$4,820.00
Title services as per Exhibit B of the Title Contract. Title Work performed in connection with Dudley School Project that is included in the Corporation's Capital Construction Plan (list of 59) and the funds required for land acquisition are availabl
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00042
42
Change Order
6/11/2009
$3,128.00
Justification - The entrance to the gang bathrooms do not have a door and frame foe egress protection, but rather utilize pass-through openings to the corridor. All parties (CM, SDA Sr. Mgmt, A/E and GC) agreed it will benefit to the project to inst
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
025
25
CCD-Authorization
3/17/2009
$963,551.00
Adjustment in contract price for the work contained in Bulletin #4 which includes RF Distribution Security System, CCTV Security System, Perimeter Security System, Public Adderss System, Voice Over Internet Protocol Unified Communications, Telecommu
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00059
59
Change Order
7/10/2009
$2,316.00
CCR-042: Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. for the additional door thresholds for the Gymnasium and Stage doors in accordance with RFI 118 (Cobra PCO No.027) JUSTIFICATION: Sketch SKA-1
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00041
41
Change Order
6/9/2009
$6,584.00
Modify the roof over mechanical and electricalrooms per RFI #172 and sketch SKP-23. The directive to Contractor after roof and drain system were installed. Due to the roof pitch and drain placement, as designed, did not drain all rain water from the
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
73
73
Change Order
10/15/2009
$75,000.00
The included Proposed Change Orders as submitted by the General Contractor, Cobra Construction were negotiated by CMD staff on 7/31/09 and 8/4/09, for a total cost of $75,000.00 (aka Roll-up #4). The negotiated values are summarized on teh attach
CA-0005
CA-0005-P01
Mazzocchi Wrecking, Inc.
1
1
Change Order
7/10/2008
($27,487.56)
Contract allowance reduction
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
005
5
Change Order
11/15/2008
$32,105.73
CO-005: Add for all labor, material, and equipment for revisions, additions, alterations, credits, etc. as final settlement for the installation of a standard manhole for manhole 1001 located in 20th St. Justification (Reason for Change): The Contra
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
001
1
Change Order
7/25/2008
$125,000.00
CCR-001: Not to exceed, time and materials change order for the removal of unsuitable soils and the replacement with suitable structural fill in areas under the proposed building as defined in the geotechnical report by Schoor Depalma Engineers and C
CA-0005
CA-0005-L01
JCA Associates, Inc.
5
5
Change Order
7/11/2007
($87,986.22)
The purpose of this 321 is to return unused funds from this Category 2 (A-Z) project to the general fund for other uses. Since this contract is an A-Z project, there is not a task order assigned.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
62
62
Change Order
7/2/2009
$5,127.00
Costs for all labor, material, and equipment for revisions, additioons, alterations, credits etc. to furnish and install metal housings over the recessed lighting fixtures located in the plaster exterior soffit at the underside of the Medial Center.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00063
63
Change Order
8/20/2009
$185,000.00
CO#63 Description The included Proposed Change Orders as submitted by the General Contractor, Cobra Construction were negotiated as a lump sum collectively. For descriptions of the work and the respective justifications refer to the associated Const
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
71
71
Change Order
9/22/2009
$31,587.00
CCR-088: The following five PCOs submitted by the Contractor, Cobra Construction were reviewed by Hill staff, and negotiated with Cobra. (Roll-up #5) Ref PCO-168, PCO-169, PCO-174, PCO-178 and PCO-181. The negotiated values are summarized on the att
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
003
3
Change Order
10/21/2008
$4,658.85
CO -003: Add for expedited fabrication adn delivery of teh hollow metal door frames scheduled to be sent in masonry opening on the first floor of Area B. This represents a total of 29 door frames adn are as follows: 113A, 113B, 115,116,117,118,119,
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
036
36
Change Order
5/20/2009
$11,410.00
CCR-040 $10,125: Costs for all labor material and equipment for revisions additions alterarions credits etc. for the addition of masonry bond beams in openings in width that are less than 24" and greater than 12". (Cobra PCO No. 040). CCR-041 $1,285
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00053
53
Change Order
6/22/2009
$1,306.00
Temporary off-site storage fee for Auditiorium Seatings. Installation for Auditiorium seating was scheduled on 6/22/09. However, the following 2 issues delayed the completion of the ceiling over the area which was to receive seating. 1) Delay by NJ-
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00056
56
Change Order
7/10/2009
$3,035.00
Cost for all labor, material, and equipment for revisions, additions, alterations, credits, etc. to: a. Construct a soffit aroundt he exposed steel beam in corridor #187 per RFI#142 dated 10/14/2008 and sketch CED-SK31; and b. Extend soffit/bulkhead
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
020
20
Change Order
1/22/2009
$20,000.00
The Contractor is directed to make the following changes to the contract: CCR-021: Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. for the removal and legal disposal of the existing temporary fence al
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
70
70
Change Order
9/11/2009
$10,217.00
PCO-166: Costs for all labor material and equipment for revisions additons alterations credits etc. to add a replacement CO2 sensor to each of the 32 CMU return air chases per Concord Engineering sketch titled "Return Air Shaft Option #2 dated 7/14/
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00049
49
Change Order
6/12/2009
$1,200.00
Construct curbs along Federal Street and Marlton Pike in accordance with CAMDEN COUNTY standards.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00060
60
CCD-Authorization
6/19/2009
$45,000.00
Water Filtration System to be built per Bulletion #8 (dated 4/13/09 in Spec section 15471 and sketches SK-P25 and P24), as well as Bulletion #8 supplement #1-R1 revised 6/19/09 (Sketch SK-P25A-R1) Reason for this change: Per Bulletin #8, as directe
CA-0005
CA-0005-Q12
Krueger International
1
1
Change Order
6/3/2009
($34,372.18)
Amendment due to change made to chairs, bookcases and cabinets
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
38
38
Change Order
6/4/2009
$15,774.00
CCR-049: Costs for all labor, material and equipment for revisions, additions, alterarions, credits, etc. for the addition of a motorized projection screen in the Cafeteria, Room 151A adn a scoreboard in the Gymnasium, Room 146. Scope of work shall
CA-0005
CA-0005-L01
JCA Associates, Inc.
2
2
Change Order
7/21/2003
$30,465.70
Budget increase under the contract for reimbursable allowances.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00040
40
Change Order
5/29/2009
$13,780.00
CCR-037: In Room 263 drawing A02.02A illustrated that the duct chase was to be constructed for a single duct however, according to the HVAC drawing there were two ducts. Sketch SKE-001 revised the duct chase to enclose both ducts which caused a recon
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
010
10
Change Order
12/8/2008
$7,067.00
Description CCR-010 ($5,975.00): Costs for all labor, material, and equipment for revisions, additons, alterations, credits, etc. for the removal and disposal of the three existing tree inside of teh curb line along 20th Street and Federal St. CCR-01
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00065
65
Change Order
8/13/2009
$240,936.00
Reassign the “AV Contractor” scope shown on the bid set AV drawings (previously for use as reference) to the GC’s Electrical sub-contract, as directed under Bulletin #4 Supplement #1 dated 6/15/09. Ref. Contractor’s three PCO’s dated 6/18/09: PCO-109
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00052
52
Change Order
6/22/2009
$2,293.00
Costs for all labor, material and equipment for a masonry chase at column line intersection N & 10 for both first and second floor locations, as defined in answer to RFI 187 and attached sketch provided on 1/28/09. Ref PCO-072, as adjusted per Hills
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00047
47
Change Order
6/15/2009
$2,054.00
Add outside air source to the heat pump at room 227B per the Engineer’s reply to RFI-203 and Engineer’s sketches CSK-M01.01B-3 and CSK-M01.01C-1. Ref Contractor’s PCO-091 dated 4/13/09 adjusted by Hill 6/4/09. Justification: The original design did
CA-0005
CA-0005-M01
Hill International, Inc.
00001
1
Change Order
2/25/2009
$8,769.00
For a not -to-exceed amount of $8,769.00 Provide additional CM services for Dudley school project by providing supervision for SDA authorized overtime for the project NJSDA issued a change order to the general contractor to work 10 consecutive saturd
CA-0005
CA-0005-K21
Xerox Audio Visual Solutions, Inc
1
1
Change Order
12/30/2009
$2,988.00
Cables were pulled through end caps and terminated. Move of Smart Board. 42 smart board tested after normal working hours.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
37
37
Change Order
6/1/2009
$66,883.00
The Contractor is directed to make the following changes to the contract: Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. to perform the revisions to the Media Center parapet per Proposal Request #24
CA-0005
CA-0005-K03
Dell
1
1
Change Order
8/26/2009
$141.20
Amendment is for a tax assessment
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
031
31
Change Order
4/27/2009
$3,208.00
CCR-030 $2,097.00: Construct CMU back-up, brick return and window jambs per SDA adopted International Masonry Institute recommendations. Cost for all labor material and equipment for revisions additions alterations, credits etc. for the adddition of
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
008
8
Change Order
11/14/2008
$16,627.00
CO-008: Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. for the additional spray fireproofing and masonry to achieve the required fire rating not originally included in the Contract Documents in accor
CA-0005
CA-0005-K06
Dell
1
1
Change Order
8/26/2009
$13,064.12
Amendment is for a tax assessment
CA-0005
CA-0005-G01
TRC Environmental Corporation/Energy Services
 
1
Liquidated Damages
2/9/2010
($7,350.00)
Smart Start Rebate.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
39
39
Change Order
6/8/2009
$51,309.00
Costs for alll labor material and equipment to provide a second security guard for teh period from 6/1/09 through 8/31/09, and extend teh serivces of teh original 1st guard from 6/30/09 through 8/31/09. Reference Contractors PCO - 96 revised 5/27/09,
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
009
9
Change Order
12/8/2008
$1,298.00
CCR-009-: Cost for all labor material and equipment for revisions, additons alterations, credits, etc. for providing a dedicated electrical circuit for teh wheelchair lift as required by the manufacture. Justification: The contract Documents detaile
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
002
2
Change Order
10/21/2008
$6,337.77
Description: CCR-002 Add for the replacement of plumbign materials stolen after the close of business of August 14, 2008 adn the start of work on August 15, 2008. Vlaue of loss was less than the minimum amount covered under OCIP. Justification: Be
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
34
34
Change Order
5/21/2009
$14,969.00
Dudley Elementary School (CA-0005-C01): Change Order #36 / CCR #45 & CCR #46 Description: CCR-045 $12,468.00: Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. for the extended duration of tempor
CA-0005
CA-0005-L03
J. McHale & Associates, Inc.
1
1
Change Order
7/7/2003
$1,000.00
Consultant prepared and delivered appraisals under original Contract. Two additional properties are required. Consultant will provide the additional property appraisals at the agreed upon amount of $500 ea ($1000 ea).
CA-0005
CA-0005-K04
Dell
1
1
Change Order
8/26/2009
$1,142.81
Amendment is for a tax assessment
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
013
13
CCD-Authorization
1/7/2009
$238,082.00
Description of Work: The Contractor was directed to furnish and install the additional scope of work, defined in the issuance of the 200 drawings and the related specification sections issued under Bulletin #1 via Proposal Request # PR-001 dated 5/
CA-0005
CA-0005-K07
Hewlett-Packard Company
2
2
Change Order
8/25/2009
$465.58
Amendment is for a tax assessment
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
004
4
Change Order
11/13/2008
($68,348.00)
CO-004: Add for all labor, material, and equiment for revisions, additons, alterations, credits, etc. as detailed in Bulletin Number 2. Justification: Bulletin Number 2 revises the emergency generator to diesel fuel from duel fuel. New Jersey School
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
030
30
Change Order
5/20/2009
$20,578.00
CCR-029: While conducting earthwork activities under the base contract, the sitework contractor unearthed soils that contained debris from unknown razed buildings. A geotechnical investigation by CMX (Geotech Consultant) determined the debris must be
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00054
54
Resolving CCD
8/4/2009
$0.00
This is a $0 dollar RESOLVING change order for CCD #4 On March 13th, 2009, NJSDA issued a CCD No. 2 (Change Order No. 25) to Cobra for the 70% of its initial proposal of above referenced work. Cobra’s electrical subcontractor was not able to release
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
024
24
Change Order
3/6/2009
$35,909.00
DESCRIPTION: CCR-025 : Cable Tray and Large Conduit - Costs for all labor, material, and equipment for revisions, additons, alterations, credits, etc. for alllmaterial and labor to supply and install the cable tray and large diameter conduit which wa
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
019
19
Change Order
1/22/2009
$21,515.00
The Contractor is directed to make the following changes to the contract: CCR-019 ($10,515.00): Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. as detailed on the "Typical Meter Vault Fire & Domestic
CA-0005
CA-0005-P03
Mazzocchi Wrecking, Inc.
1
1
Change Order
7/10/2008
($39,918.71)
It was unnecessary to do final grading and restoration for the Kelly Drum area as the main construction contract has been awarded. The construction contractor accepted the site as is. No RCRA hazardous waste was created or identified during demolit
CA-0005
CA-0005-L01
JCA Associates, Inc.
4
4
Change Order
9/26/2003
$34,964.00
Monitoring wells & baseline ecological evaluation per JCA letter dated 7/17/03.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
027
27
Change Order
3/26/2009
$21,430.00
CCR-027: Costs for all labor, material, and equipment for revision, additons, alterations, credits, etc. for all material and labor for: (1) Auditorium & gymnasium - change from adjustable anchor and steel clip to welded angle and Hilti fastener as
CA-0005
CA-0005-M01
Hill International, Inc.
00002
2
Change Order
7/7/2009
$74,655.00
1. ALLOWANCE to provide additional CM services for Dudley School project by providing Supervision for SDA Authorized overtime for the project. (It is expected that the contractor will work Saturdays through the remainder of the project. And has reque
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
028
28
CCD-Authorization
4/23/2009
$96,220.00
CCD Notification CA-0005-C01 CO#28 CCD#3 in the amount of $96,220.00 for CCR-032: Increase in contract price to cover the costs for premium time labor hours for acceleration in lieu of time extension from impacts resulting from Bulletin No.1 and Bull
CA-0005
CA-0005-K11
Dell
1
1
Change Order
9/11/2009
$235.63
Amendment for tax assessment due to the technology equipment being shipped to the integrator's warehouse located in NY, because school was not ready to receive the equipment
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
006
6
Change Order
11/15/2008
$3,908.70
The Contractor is directed to make the following changes to the contract: CO-006: Add to the General Contractor’s contract for the removal of unsuitable soils and the replacement with suitable structural fill in areas under the proposed building as d
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
017
17
Change Order
1/22/2009
$30,455.00
The Contractor is directed to make the following changes to the contract: CCR-017: Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. for expedited four week shipment of the primary electrical switchgear
CA-0005
CA-0005-K01
Centre Business Products Inc
1
1
Change Order
12/18/2009
($163,406.00)
PO and invoice retracted and resubmitted under new CA-0005-K21
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
029
29
Change Order
4/27/2009
$13,033.00
`CCR-033: CBOE Requested revisions to the Trash Room Enclosure. Costs for all labor, material and equipment for revisions additions alterations credits etc. for the additional work as detailed on SkA-27 for the Trash Room Enclosure. (Cobra PCO No. 00
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00058
58
Change Order
7/10/2009
$2,532.00
Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. to cable and pull-handles for remote operation of smoke hatches above Auditorium stage, per Gensler sketch 34 dated 3/24/09 conveyed under PR-0027 dated
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
75
75
Change Order
12/16/2009
$30,824.00
The included Proposed Change Orders as submitted by the General Contractor, Cobra Construction were negotitated by CM staff on 10/12/09 and 10-26-09 for a total cost of $30,824.00 (ada Roll-up #7). The negotiated value are summarized on teh attached
CA-0005
CA-0005-K09
Dell
1
1
Change Order
10/13/2009
$4,460.71
Amendment for tax assessment due to technology equipment shipment to the interator's warehouse (Computer Logic Group) located in NY, since the school site was not ready for acceptance of the equipment, adjustment were made by Dell as per credit memo
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
33
33
Resolving CCD
8/13/2009
$145,505.00
Refer to Primavera
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
35
35
Change Order
6/15/2009
$73,045.00
CCR-044 $73,045.00: Costs for all labor, material, and equipment for revision, additons, alternations, credits etc. for the down time costs resulting for the City of Camden delay for the storm water work in 20th Street. (Cobra PCO No. 083)
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
007
7
Change Order
11/25/2008
$220,361.00
CCR-007: Add to the General Contractor’s contract the cost for: Acceleration in Lieu of Time Extension for Schedule Impacts Resultant from Bulletin #1 and Related RFI’s. The scope includes premium time rate differential for trade staffing on ten (
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00057
57
Change Order
7/23/2009
$24,130.00
CCR-039 ($21,867): Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. forthe revised scope to provide an expansion joint along column line 3.8, and to furnish and install expansion joint covers along col
CA-0005
CA-0005-K05
Dell
1
1
Change Order
8/26/2009
$2,471.29
Amendment is for a tax assessment
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
67
67
Change Order
7/31/2009
$87,632.00
Costs for all labor, material and equipment for revisions additions, alterations credits etc. to construct "Return Air Shaft Option #2" as detailed in concord Engineering Sketch dated 7/14/09, and as mocked -up in room #208, in all 39 rooms which wer
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
022
22
Change Order
2/17/2009
$37,866.00
BIC to Claire on 2/4/09.cl The Contractor is directed to make the following changes to the contract: CCR-023: Costs for all material revisions to the door hardware from Bulletin #1 to which was revised during the submittal review by the Architect.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
74
74
Change Order
12/16/2009
$62,708.00
The included Proposed Change Orders as submited by the General Contractor, Cobra Construction were negotiated by CM staff on 10/12/09 and 10/26/09 for a total cost of $62,708.00 (aka Roll-up #6). The negotiated values are summarized on the attached s
CA-0005
CA-0005-K10
Hewlett-Packard Company
1
1
Change Order
8/24/2009
($10,320.00)
Amendment due to cancellation of purchase order due to back order Part II CB413A#ABA
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00051
51
Change Order
7/20/2009
$5,655.00
Install a moisture sealer on the concrete slab on grade prior to placing the resinous flooring system - at rooms 154A, K, J, L, M, west half of Servery, dish room and walk-in cooler.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
32
32
CCD-Authorization
5/13/2009
$436,449.00
THIS CCD#4 (= 2A) FOR PURPOSE OF Supplementary CCD No. 2 in order to cover 100% of the direct cost for the subcontractors. This construction change directive is for additional construction necessary to re-insert all items contained in the “USAC Scho
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
023
23
Change Order
3/6/2009
$6,505.00
CCR-015 ($2,426.00) Cost for all labor, material and equipment for revisions, additions, alterations, credits, etc. for the revisions to the Plumbing Equipment Schedule as detailed in RFAI #061. CCR-016 ($284.00) Cost for all labor, material and equi
CA-0005
CA-0005-L22
Jeannette Morales
1
1
 
10/9/2008
($8,100.00)
Jeanette Morales's eligibility expired on June 5, 2007; therefore, the current TRS obligation of $8,100.00 in SIMS is being deobligated.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00050
50
Change Order
6/15/2009
$5,234.00
Install receptacles and circuits to provide a duplex receptacle within 6 ft of each condensate pump location (total 9 location) as shown on sketches SKE-080903 - A, B, C and D, per Engineers 8/9/08 review of shop drawing submittal 15185-06 Auto Conde
CA-0005
CA-0005-L01
JCA Associates, Inc.
1
1
Change Order
3/12/2003
$12,600.00
 
CA-0005
CA-0005-K07
Hewlett-Packard Company
1
1
Change Order
7/31/2009
($5,375.00)
Amendment due to Camden District Techonologists provided printer specs of an HP printer P1005 that did not include a built in network interface. In light of their error, the District has requested that the printer model be changed to an HP #P1505N.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00044
44
Change Order
6/11/2009
$11,199.00
Provide top of wall enclosure for bar joists in Cafeteria and Music Rooms, Specifically, provide additional diagonal braces at shear walls in Area C, per sketch CEC-SK43R, dated 4/17/09; and close opening in joist web between Rooms 150-A and 151/15
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00046
46
Change Order
6/15/2009
$1,258.00
Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. to provide portable temporary fencing to secure the southern end of Area A while the drop-off area is constructed. Justification: This minor change i
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00055
55
Change Order
7/10/2009
$12,325.00
Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. to furnish and install additional FireTrol columns as detailed in RFI24. JUSTIFICATION: Through the shop drawing review the A/E revised the drawing to
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
00045
45
Change Order
6/15/2009
$5,952.00
Costs for all labor, material and equipment for revisions, additions, alterations, credits, etc. to relocate the sprinkler piping from below the heat pumps. This is an Owner request. Justification: Per SDA and Camden Board of Education request, conv
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
016
16
Change Order
1/22/2009
$6,877.00
The Contractor is directed to make the following changes to the contract: CCR-014: Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. for the additional work as detailed in RFI No. 134 for the parapet re
CA-0005
CA-0005-Q02
Interior Systems Inc.
1
1
Change Order
5/1/2009
($55.06)
Reduction of up charges.
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
015
15
Change Order
12/26/2008
$88,000.00
BIC to Dhimant Dave on 12/16/08.cl Description: CCR-012: costs for all labor, material and equipment for revisions additons alterations credits etc. for providing security guards during all off hours of normal operation includingholidays. The durat
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
014
14
Change Order
12/18/2008
$31,612.00
Description: CCR-013: costs for all labor, material and equipment for revisions additons alterations credits etc. for the additonal work as detailed in Architectural Bulletin No. 3 dated 8/25/08. Justification: CCR-013: Bulletin No. 3 added gymanas
CA-0005
CA-0005-M01
Hill International, Inc.
00005
5
Change Order
11/23/2009
$9,450.00
Provide additional building commissioning services per NJSDA request, dated 6/17/09. Hill Internationals (Hill) sub-consultant, Miller-Remick Corp (MRC), is to conduct a second commissioning process for the heat pump water loop system. MRC Proposal
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
021
21
Change Order
2/20/2009
$56,616.95
Justification (Reason for Change): The Contract Documents provided a sink immediately outside of the toilet rooms located in the subject classrooms, which was in compliance of the NJ Uniform Construction Code Bulletin #00-3. This design was reviewed
CA-0005
CA-0005-C01
Cobra Construction Co., Inc.
018
18
Change Order
1/28/2009
$78,472.00
The Contractor is directed to make the following changes to the contract: CCR-018: Costs for all labor, material, and equipment for revisions, additions, alterations, credits, etc. for the work contained in Bulletin 2-Revision 1. Justification (Reas
CA-0005
CA-0005-K12
Dell
1
1
Change Order
11/16/2009
$522.41
Price increase due to NY State Taxes on shipment of product to Integrator's (CGL) facility, as the school was not ready for delivery.
CA-0006
CA-0006-A01
Smithco. Group, Inc. (The)
 
1
Change Order
7/11/2003
$0.00
Install Automatic Flushing Systems at the Jerrothia Riggs Adult Center consisting of approximately 25 flushing stations, comprised of solenoid valves and a 24 hour timer, installed on the domestic water lines to drinking fountains. The valves are no
CA-0006
CA-0006-A01
Smithco. Group, Inc. (The)
 
2
Change Order
7/1/2003
$23,320.00
Provide inspection, coordination, field work, equipment and supplies, administration, reporting, and commissioning associated securing the water consumption points within the thirty seven (37), approximately 300 designated points, in accordance with
CA-0006
CA-0006-A01
Smithco. Group, Inc. (The)
 
5
Change Order
11/5/2004
$8,730.00
SmithCo will perform the additional inspections and asbestos managemeent services including amending construction permits from DCA, emergency letters to contractors, monitoring of the abatement work, final clearance sampling, and report.
CA-0006
CA-0006-A01
Smithco. Group, Inc. (The)
 
4
Change Order
3/21/2004
$39,340.00
Provide Asbestos Management Services associated with the demolition of the Early Childhood Development Center including prestests, inspections, sampling, collection of clerance samples, reports, preparation of specifications, air monitoring, acqusiti
CA-0006
CA-0006-A01
Smithco. Group, Inc. (The)
 
3
Change Order
7/30/2003
$39,330.00
Provide Asbestos Inspection, Smapling, Findings & Observations, Reports, Spectification Design, Air Monitoring, Coordination of Asbestos Abatement, and Final Reports for Health & Safety work associated with Challenge Square School in accordance with
CA-0007
CA-0007-P01
Thornton Tomasetti , Inc.
 
2
Change Order
7/11/2007
($2,832.00)
The purpose of this 321 is to return unused funds from this Category 2 (A-Z) project to the general fund for other uses. Since this contract is an A-Z project, there is not a task order assigned.
CA-0007
CA-0007-P01
Thornton Tomasetti , Inc.
 
1
Change Order
11/5/2003
$48,000.00
This amendment represents a change in scope for the consultant. The original contract was for structural feasibility only. It is proposed to add providing invasive investigation and a report of the concrete structure at Coopers ES. LZA in it's visual
CA-0008
CA-0008-A01
Skidmore, Owings & Merrill, Architects, P.A.
 
2
Change Order
1/9/2004
$18,335.60
Expansion of site investigation services due to the expansion of additional sites.
CA-0008
CA-0008-A01
Skidmore, Owings & Merrill, Architects, P.A.
 
3
Change Order
6/22/2004
$97,900.00
Parking study options for multi-level above grade parking scheme and underground parking scheme.
CA-0008
CA-0008-A01
Skidmore, Owings & Merrill, Architects, P.A.
 
4
Change Order
10/26/2004
$87,100.00
Complete a feasibility study for the program expansion.
CA-0008
CA-0008-A01
Skidmore, Owings & Merrill, Architects, P.A.
 
1
Change Order
8/13/2003
$170,455.00
Consultant scope increased to incorporate developing & documenting the District Wide Technology Plan for the Camden Schools. An allowance has been added for expanding scope to include Damiano Long, LLC engineers for developing and coordinating the c
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
25
25
Change Order
11/24/2009
$63,872.00
New Construction projects, the new HB Wilson & Dudley Elementary Schools, are currently received Temporary Certificate of Occupancy (TCO). This Amendment #25 is additional construction administration (CA) service from Gensler and its MEP sub-consulta
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
4
4
Change Order
2/14/2007
$447,246.00
This is amendment is for additional design services necessary to provide additional construction administration for both Dudley ES and HS Wilson ES due to the following items: Separation of foundation & building package for HB Wilson ES: In March
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
00018
18
Change Order
7/30/2009
$11,445.00
New Construction projects, HB Wilson and Dudley ES are currently 90% completed. On June 29, 2009, NJSDA requests additional site representation from Genslers sub-consultant, Concord Engineer Group (CEG), on site at both HB Wilson and Dudley Es for on
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
1
1
Change Order
12/22/2003
$74,878.60
The above total compensation is for fees and expenses for additional services tasks that were needed to respond to requests for redesign tasks after approvals were obtained and corresponding revisions to Agency Submittal packages after packages were
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
7
7
Change Order
8/5/2008
$17,000.00
On or about April 7, 2008, Gensler Associates (A/E) learned that Ernest Boxk and Sons Inc. (EBS) - installed anchor bolts at approximately 68 column locations in a method of installation not authorized by A/E or as documented in A/Es construction doc
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
8
8
Change Order
1/29/2009
$210,000.00
Per the Design Agreement with Gensler & Associates (Gensler), dated June 13, 2003, the original scope of work for HB Wilson and Dudley Elementary school projects did not include telephone, PA system and Security system. In addition, the original desi
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
24
24
Change Order
12/9/2009
$1,144.00
HB Wilson No Fee $0.00 value. New Construction projects, the new HB Wilson & Dudley Elementary Schools, are currently received Temporary Certificate of Occupancy. This Amendment #24 is additional site visit by Concord Engineering Group (CEG) at ne
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
14
14
Change Order
4/24/2009
$1,071.00
The new installed roof deck for the new HB Wilson School project was damaged by the subcontractor of General Contractor, Ernest Bock & Sons (EBS). Gensler (A/E) and its sub-consultant was out on jobsite to do the observation, to issue sketches and t
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
00011
11
Change Order
11/4/2008
$35,000.00
Description: The original allowance for testing and inspections under the Contract has been exhausted due to the increase frequency of inspections and reports which were requested by NJDCA. Therefore, Gensler and its sub-consultant, CMX, are requesti
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
00024
24
Change Order
12/9/2009
$1,144.00
HB Wilson No Fee $0.00 value. New Construction projects, the new HB Wilson & Dudley Elementary Schools, are currently received Temporary Certificate of Occupancy. This Amendment #24 is additional site visit by Concord Engineering Group (CEG) at ne
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
13
13
Change Order
4/27/2009
$14,887.39
Per the request from Camden Board of Education on 2/6/2009, a Water Filtration system is to be add into the new HB Wilson Elementary School (ES) project during the construction phase. This filtration system is consist of a carbon filtration system, i
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
2
2
Change Order
4/1/2005
$170,566.20
The Architect is directed to prepare additional elevation schemes.
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
00017
17
Change Order
6/25/2009
$148,000.00
New Construction Pojects, HB Wilson & Dudley Elementary Schools are currently 80 - 85% complete. In order to accomodate the acceleration efforts from general contractors, Cobra Constructio an Ernest Bock & Sons, and their electrical sub-contractors,
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
3
3
Change Order
5/14/2005
$160,000.00
Gensler Associates is directed to prepare additional elevation schemes to respond to review comments received. Due to the timing of the comments this represents duplication of the architect work and additional compensation is granted. Muliple schemes
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
6
6
Change Order
7/2/2008
$20,000.00
DESCRIPTION: Per Original Design Agreement with Gensler & Associates (Gensler), dated June 13, 2003, the "Testing and Inspection" allowance with total of $100,000 was for both school projects, HB Wilson and Dudley Elementary School in Camden School D
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
23
23
Change Order
12/9/2009
$1,184.00
New Construction projects, the new HB Wilson & Dudley Elementary Schools, are currently received Temporary Certificate of Occupancy. This Amendment #23 is for additional Consulting Engineers Collaborative (CEC) site visit at HB Wilson Elementary S
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
00008
8
Change Order
1/29/2009
$210,000.00
Per the Design Agreement with Gensler & Associates (Gensler), dated June 13, 2003, the original scope of work for HB Wilson and Dudley Elementary school projects did not include telephone, PA system and Security system. In addition, the original desi
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
000018
18
Change Order
7/30/2009
$11,445.00
New Construction projects, HB Wilson and Dudley ES are currently 90% completed. On June 29, 2009, NJSDA requests additional site representation from Genslers sub-consultant, Concord Engineer Group (CEG), on site at both HB Wilson and Dudley Es for on
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
00025
25
Change Order
11/24/2009
$63,872.00
New Construction projects, the new HB Wilson & Dudley Elementary Schools, are currently received Temporary Certificate of Occupancy (TCO). This Amendment #25 is additional construction administration (CA) service from Gensler and its MEP sub-consulta
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
00021
21
Change Order
11/27/2009
$55,000.00
New Construction projects, new HB Wilson & Dudley Elementary Schools, are currently 98% complete Due to additional 3rd party inspections which is required by NJDCA, NJSDA requested additional inspection and testing service from Gensler and its sub-co
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
17
17
Change Order
6/25/2009
$148,000.00
New Construction Pojects, HB Wilson & Dudley Elementary Schools are currently 80 - 85% complete. In order to accomodate the acceleration efforts from general contractors, Cobra Constructio an Ernest Bock & Sons, and their electrical sub-contractors,
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
000019
19
Change Order
10/29/2009
$8,736.00
New Construction projects, HB Wilson & Dudley Elementary Schools, are currently 90% complete. NJSDA requested additional design service from Gensler and its sub-consultant, Concord Engineer Group (CEG), to provide additional drawings, details and doc
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
00012
12
Change Order
4/28/2009
$15,794.39
Per the request from Camden Board of Education on 2/6/2009, a Water Filtration system is to be add into the new Dudley Elementary School (ES) project during the construction phase. This filtration system is consist of a carbon filtration system, incl
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
00005
5
Change Order
7/11/2007
$45,000.00
The service described are the responsibility of the Project Management Firm(PMF) and are an additional service to the Design Consultant's Agreement for Gensler Architects & Associates.
CA-0009
CA-0009-A01
Gensler and Associates/Architects, Inc.
10
10
Change Order
10/31/2008
$23,000.00
Per NJDCAs request, the third party inspection for structural steel and CMU wall inspections are required. The original allowance for testing and inspections under the Contract has been exhausted due to the increase frequency of inspections and repo
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00002
2
CCD-Authorization
7/22/2009
$680,000.00
Per the FTAE bullentin #2, additional work is required to complete the project.
CA-0010
CA-0010-A01
Rothe-Johnson-Fantacone
1
1
Change Order
6/8/2004
$329,598.63
The Project is a new replacement of the existing Morgan Village Junior High School to meet capacity and program space objectives identified in Camden School District Model Program "Junior High School (7-9) Model #1" as approved by NJDOE (Model).
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00008
8
Change Order
2/19/2010
$6,200.00
Steel Costs Per sketches issued by FTAE. Note: Each change will be referred to by the subcontractors X-number. X-4 FTAE issued sketch SK-S302-1 which modifies details 18A/S302 & 17/S302 to accommodate sloping beams at the music rooms and the cafeter
CA-0010
CA-0010-A01
Rothe-Johnson-Fantacone
00005
5
Change Order
2/28/2010
$5,692.00
Include a domestic water carbon filtration system including, but not limited to duplex activated filter media tank, media and automatic backwash. JUSTIFICATION: NJSDA requested additional scope.
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00001
1
Change Order
5/18/2009
$35,841.00
This Contractor Proposal Request is to provide all labor, materials and equipment required to pave the new temporary Teachers Parking Lot located at the Southeast corner along Morgan Boulevard. The paving will consist of 2" of FABC over the existin
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00009
9
Change Order
2/19/2010
$18,000.00
Overtime required to excavate and install contract concrete, forms and rebar to footings and foundations in Areas A thru D that were stopped until the Urban fill was removed. Typically two hours of overtime during the normal work week was added each
CA-0010
CA-0010-L27
Clerk of the New Jersey Superior Court
1
1
TaskOrder
6/4/2008
$23,854.09
 
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00013
13
CCD-Authorization
3/3/2010
$24,000.00
Provide and install underground and above slab cast iron storm piping in every area of the building.
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00012
12
Change Order
2/19/2010
$3,008.00
This change will provide all labor and materials to complete work related to Joist/Bridging size changes and added uplift loads as a result of ocmments made by FTAE EOR on the shop drawings JE1. Changes in Joists from: 4-44LH15 to 6-32LH13 3-44LH14 t
CA-0010
CA-0010-P01
Tricon Enterprises, Inc.
2
2
 
11/18/2008
($46,656.56)
Change Order is to reconcile the contract values for the actual work on the site.
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00003
3
Change Order
1/13/2010
$27,321.20
This recommendation will provide all materials labor and equipment necessary to install 1118 cubic yards of approved structural fill to be placed in the southeast hole left from a prior construction contract. As per Addendum #3,2500 cubic yards of so
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00004
4
Change Order
1/13/2010
$4,447.04
AS a result of requests made by the DCA safety inspector SDA and URS concrete aprons/sidewalks are to be installed at two construction entrances 2-10 x 30x 4. Excavation stone an dconcrete work was required. Amount of request change is $4,447.04
CA-0010
CA-0010-P01
Tricon Enterprises, Inc.
1
1
CCD-Authorization
12/23/2008
$125,000.00
Excavate, transport and dispose of non-hazardous soil containing ceramic debris and a peat layer from a prehistoric creek.
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00011
11
Change Order
2/19/2010
$2,981.00
As per the NJDCA the radon pipe located in the footings was required to be edtended so that they are located in stone approximately 3-4 away from the footing. This work would be performed in approximately 41 locations adding 80 of PVC 3 pipe and 24
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00007
7
CCD-Authorization
7/16/2009
$533,145.90
Stock pile existing structural fill in areas as designated by teh locations of the existing demolished structures Demolish existing footing and foundations as directed by FTAE in Area A. All additonal PP +40 testing as required per the 500CY limit.
CA-0010
CA-0010-P01
Tricon Enterprises, Inc.
3
3
Resolving CCD
8/5/2009
$161,147.50
Remove clean overburden to a stockpile. Excavate, transport, and dispose of non-hazardous soil containing ceramic debris. Rent temorary fence.
CA-0010
CA-0010-A01
Rothe-Johnson-Fantacone
00003
3
Change Order
3/28/2008
$80,000.00
C/O given to SPM for review and signature on 4/16/08.cl Additional Scope due to result of adaptation of new building codes in State of NJ additional Scope due to additional DEP requirements homeland security adn other techonology bulletins issued by
CA-0010
CA-0010-A01
Rothe-Johnson-Fantacone
2
2
Change Order
6/22/2005
$0.00
This modification of the Scope of services is to provide a reallocation of the allowance amounts for the Morgan Village JHS. This Amendment is requesting that a total of $5,000 from the Site Investigation Allowance (reducing it to a total of $35,000)
CA-0010
CA-0010-A01
Rothe-Johnson-Fantacone
00004
4
Change Order
10/8/2008
$11,609.00
The Camden School District has elected to revise their Technology Standards adn include interactive Whiteboards ("SmartBoards") in their classrooms, in lieu of ceiling mounted projectors with manual screens, and televisions. As the Contract Document
CA-0010
CA-0010-C01
Chanree Construction Co Inc
00010
10
Change Order
2/19/2010
$5,299.00
Camden School District /NJSDA requested to included 2 slab depressions for 2-6 x 12 recessed mats at school entrances as per FTAE sketch SK-S101.1-1 dated 8/24/09. (see attached)
CA-0011
CA-0011-K12
Avectus
 
1
Change Order
9/4/2007
($186,405.00)
Amendment due to Vendor is unable to obtain Smart Boards from Smart Technology.
CA-0012
CA-0012-A01
Skidmore, Owings & Merrill, Architects, P.A.
2
2
Change Order
3/1/2005
$5,430.00
Construction documentation of the window repairs.
CA-0012
CA-0012-C02
W.J. Gross, Inc.
2
2
Change Order
10/20/2008
$7,141.00
Description In order to reach the 90 MPH basic wind speed load reuired ments for the scaffolding system, provide labor and materials to perform the following activities: -Double the bracing on the debris catch and lag bolt attachments. -Double the
CA-0012
CA-0012-C02
W.J. Gross, Inc.
1
1
Change Order
2/1/2008
$18,941.00
1. Provide cantilevered framing and netting on both sides of main entrance scaffolding. $5,481.00 2. Provide 8 feet high chain link fence wired to scaffolding frame on both sides of main entrance and to existing chain link fence. $2,918.00 3. Pr
CA-0012
CA-0012-A01
Skidmore, Owings & Merrill, Architects, P.A.
1
1
Change Order
5/9/2004
($1,874,225.75)
Reduction in Scope of Work. The historical restoration scope of work will continue in full through the post occupancy phase of the work as per the contract. All other activity and scope will no longer be required as part of contract CA-0012-A01.
CA-0012
CA-0012-A01
Skidmore, Owings & Merrill, Architects, P.A.
4
4
Settlement
6/23/2009
($405,495.57)
Description : Credit Change Order resulting from termination of contract. A copy of the Settlement Agreement and Release is attached
CA-0013
CA-0013-A01
Skidmore, Owings & Merrill, Architects, P.A.
 
1
Change Order
5/9/2004
($2,011,138.50)
Reduction in Scope of Project: Woodrow Wilson High School scope will be completed as per scope of work through the Program Phase and Schematic Phase as required to complete the Ed Specifications and Ed Schematic submittal for the Department of Educat
CA-0014
CA-0014-C03
B&N&K Restoration Co., Inc.
00003
3
Change Order
10/17/2007
($154.96)
This CCR is to incorporate credit for remaining balance of the unused contract allowance for the final invoice closeout.
CA-0014
CA-0014-C02
John D. Lawrence, Inc.
00003
3
Change Order
4/28/2008
$34,151.00
Description: The Contractor will proceed with the change to the contract work to furnish and install sixty-four (64) 48"x48" window security grilles adn sixteen (16) vision panels 5: x 20" to cover all exterior door windows to teh TCUs. All work to
CA-0014
CA-0014-A01
Design Resources Group, Architects, AIA
00006
6
Change Order
5/11/2008
$13,740.00
Description:Design Resources Group completed the contract documents in 2005 and the drawings were approved by DCA in 2006. Since then the project was placed on hold because fo lack of funding. On 2/25/08, the NJSDA met with DRG to go over the proce
CA-0014
CA-0014-A01
Design Resources Group, Architects, AIA
4
4
Change Order
2/13/2007
$65,000.00
The projects was to include design and documentation inclusing engineering of a community feature defined as a facility for the Cam Care Health Services. This 2000 s.f. additional scope would house a health services suite in conjuction with the schoo
CA-0014
CA-0014-A01
Design Resources Group, Architects, AIA
1
1
Change Order
10/29/2004
$7,500.00
Provide a study for placing TCU's on the site. The study will determine the exact number of TCU's to be installed on the site and circulation patterns required to access classrooms. In addition, the presentation should also include the identification
CA-0014
CA-0014-C02
John D. Lawrence, Inc.
2
2
Change Order
6/2/2006
$8,980.54
CCR12: Credit for unused construction manager field office. CCR13: Cast in place headwall structure. CCR15: Advanced payment to PSE&G Co. for off hours shutdown.
CA-0014
CA-0014-C01
Modular Space Corporation
00001
1
Change Order
10/28/2008
($13,000.00)
This credit CCR is issued to deduct the total unused contract allowance for the closure of this contract in accordance with the contract documents. Justification This CCR is issued to deduct and return the total unused contract allowance as a savings
CA-0014
CA-0014-C03
B&N&K Restoration Co., Inc.
00002
2
Change Order
10/23/2007
$44,619.90
Reroute existing vent & heating lines within the crawl space below the coorridor slab.
CA-0014
CA-0014-A01
Design Resources Group, Architects, AIA
2
2
Change Order
10/29/2004
$55,737.50
The development of the current Pyne Poynt ES requires the submission of an Upland Waterfront Development permit to the NJDEP. This amendment includes all work necessary to file for the permit and the the cost of obtaining the permit if approved by t
CA-0014
CA-0014-C02
John D. Lawrence, Inc.
1
1
Change Order
12/12/2005
$122,323.67
Storm filter installation & deletion of dry wells. As indicated in Bulletin #1 dated June 13, 2005.
CA-0014
CA-0014-C03
B&N&K Restoration Co., Inc.
00001
1
Change Order
10/3/2007
$0.00
Change outlied in Bulletin #01, dated Jully 13, 2005, PR #01. See attached for detailed description of changes made from the BID SET to the BULLETIN/CONFORMED SET. Identification numbers are identified only the first time they appear in the set.
CA-0014
CA-0014-A01
Design Resources Group, Architects, AIA
00005
5
Change Order
4/15/2008
$400,218.00
Amendment given to Isaac on 3/6/08 for review and signature.cl Description: DRG Architects (DRG) was given a Notice To Proceed (NTP) on August 22, 2003 to provide designa nd construction administration services for the new Pyne Poynt Junior High Scho
CA-0014
CA-0014-A01
Design Resources Group, Architects, AIA
3
3
Change Order
3/31/2005
$245,000.00
In order to meet the model program and DOE education adequacy, the interior partitions had to be reconfigured to a much larger degree than the initial project had anticipated
CA-0014
CA-0014-C01
Modular Space Corporation
00002
2
Change Order
2/25/2009
$40,000.00
This change order issued to cover all labor, materials and associated taxes required for providing additional site security, which was required due to several delays, caused by others for period of four or five months. This change order is in accord
CA-0015
CA-0015-A01
Design Resources Group, Architects, AIA
 
1
Change Order
5/25/2004
$0.00
Modification of the projects scope of work. Change from a Renovation School to a replacement school.
CA-0015
CA-0015-A01
Design Resources Group, Architects, AIA
 
2
Change Order
11/23/2004
$22,400.00
DRG Architects will be completing an analysisi of various options for placing the new elementary school on the existing site without the constraint of keeping the existing school opening during construction and modifying the building layout in respo
CA-0015
CA-0015-A01
Design Resources Group, Architects, AIA
 
3
Change Order
3/8/2005
$212,500.00
Community Features; DRG will prepare plans and elevations for the conceptual design and presentation of a proposed Community feature at RC Molina School.
CA-0015
CA-0015-A01
Design Resources Group, Architects, AIA
 
4
Change Order
6/22/2005
$45,000.00
Addition of Documenting Community Feature as an Alternate: The Project is to include design and documentation including engineering of a Community Feature defined as a Facility for the Fair Share Housing. The 2000 sf additional Scope that includes a
CA-0016
CA-0016-L33
Bernard Brown
 
1
 
10/9/2008
($13,705.00)
Bernard Brown's eligibility expired on July 18, 2006; therefore, the current TRS obligation of $13,705.00 in SIMS is being deobligated.
CA-0016
CA-0016-L10
Stacey Stafford
 
1
 
10/9/2008
($14,430.00)
Stacey Stafford's eligibility expired on March 28, 2006; therefore, the current TRS obligation of $14,430.00 in SIMS is being deobligated.
CA-0016
CA-0016-A01
Design Resources Group, Architects, AIA
 
1
Change Order
5/25/2004
$0.00
Modification of the project's Scope of Work. Change from a renovation school to a replacement school.
CA-0016
CA-0016-L48
Maria Medina
 
1
TaskOrder
9/14/2009
$500.00
 
CA-0016
CA-0016-A01
Design Resources Group, Architects, AIA
 
3
Change Order
3/8/2005
$212,500.00
DRG is directed to prepare additional elevation schemes to respond to review comments received.
CA-0016
CA-0016-A01
Design Resources Group, Architects, AIA
 
2
Change Order
10/29/2004
$22,400.00
Building site analysis, LRFP amendments. Placing of new school on site without constraint of keeping existing school open.
CA-0018
CA-0018-L22
City of Camden / Water Department
35
35
TaskOrder
1/8/2010
$59.94
Refer to RESDB
CA-0018
CA-0018-L22
City of Camden / Water Department
28
28
TaskOrder
1/4/2010
$240.32
 
CA-0018
CA-0018-L01
Chicago Title Insurance Company
7
7
TaskOrder
11/9/2009
$565.00
Refer to RESDB
CA-0018
CA-0018-A01
Nadaskay Kopelson Architects
3
3
Change Order
2/27/2009
$37,000.00
NK Architects has modified the site layout per the request of SCC for the Lanning ES project. The site design changed as follows: - Redesign Clinton Ave from a through street to a dead end - Redesign Clinton Ave to the original alignment NK A
CA-0018
CA-0018-L22
City of Camden / Water Department
31
31
TaskOrder
1/8/2010
$2,238.93
Refer to RESDB
CA-0018
CA-0018-L38
Courier-Post
1
1
 
1/14/2010
$81.51
 
CA-0018
CA-0018-L22
City of Camden / Water Department
5
5
TaskOrder
9/24/2009
$346.63
 
CA-0018
CA-0018-L22
City of Camden / Water Department
25
25
TaskOrder
1/4/2010
$61.60
 
CA-0018
CA-0018-L22
City of Camden / Water Department
12
12
TaskOrder
9/24/2009
$16.52
 
CA-0018
CA-0018-L22
City of Camden / Water Department
10
10
TaskOrder
9/24/2009
$59.00
 
CA-0018
CA-0018-L22
City of Camden / Water Department
27
27
TaskOrder
1/4/2010
$12.03
 
CA-0018
CA-0018-J01
USA Environmental Manag, Inc.
1
1
Change Order
1/21/2010
$38,825.94
 
CA-0018
CA-0018-L05
Hilda M. Vera-Luciano
1
1
TaskOrder
9/4/2009
$8,253.24
 
CA-0018
CA-0018-L22
City of Camden / Water Department
26
26
TaskOrder
1/4/2010
$5.68
 
CA-0018
CA-0018-L01
Chicago Title Insurance Company
4
4
TaskOrder
7/24/2009
$387.00
Refer to RESDB
CA-0018
CA-0018-L22
City of Camden / Water Department
33
33
TaskOrder
1/8/2010
$52.74
Refer to RESDB
CA-0018
CA-0018-L22
City of Camden / Water Department
1
1
TaskOrder
7/23/2009
$99.16
Refer to RESDB
CA-0018
CA-0018-A01
Nadaskay Kopelson Architects
4
4
Change Order
5/6/2009
$49,560.00
Based on the 2008 NJSDA Capital Plan and subsequent review by NJDOE the overall program for the Lanning Square Elementary School was revised at the request of the Camden Board of Education. This revision to the approved program from K-5 grade to Pre
CA-0018
CA-0018-L22
City of Camden / Water Department
30
30
TaskOrder
1/8/2010
$1,906.78
Refer to RESDB
CA-0018
CA-0018-L22
City of Camden / Water Department
22
22
TaskOrder
10/16/2009
$45.17
 
CA-0018
CA-0018-L22
City of Camden / Water Department
29
29
TaskOrder
1/4/2010
$473.06
 
CA-0018
CA-0018-A01
Nadaskay Kopelson Architects
5
5
Change Order
10/27/2009
$953,000.00
This amendment is for additional disign services necessary to completely redesign the ALanning Square Elementary School. The original project was an 84,000 sq. ft. pre K to 5th grade buidling. NJ Architects had completed drawings through to 95% Co
CA-0018
CA-0018-L04
Ernest Oglesby
1
1
TaskOrder
8/20/2009
($540.00)
 
CA-0018
CA-0018-L22
City of Camden / Water Department
6
6
TaskOrder
9/24/2009
$384.68
 
CA-0018
CA-0018-L02
Hilda M. Vera-Luciano
1
1
TaskOrder
5/27/2009
($1,520.00)
 
CA-0018
CA-0018-L22
City of Camden / Water Department
16
16
TaskOrder
10/16/2009
$11.60
 
CA-0018
CA-0018-L22
City of Camden / Water Department
2
2
TaskOrder
7/23/2009
$10.62
Refer to RESDB
CA-0018
CA-0018-L01
Chicago Title Insurance Company
2
2
TaskOrder
6/9/2009
$365.00
Refer to RESDB
CA-0018
CA-0018-P01
Site Contractors Inc.
2
2
Change Order
2/13/2007
$125,552.00
This change reflects negotiated value for general conditions and general requirements items as agreed between Site Constractor Inc. (the Contractor) and New Jersey Schools Construction Authority (NJSCC) on Sept. 13, 2006. The Contractor shall receiv
CA-0018
CA-0018-L22
City of Camden / Water Department
9
9
TaskOrder
9/24/2009
$61.28
 
CA-0018
CA-0018-L01
Chicago Title Insurance Company
6
6
TaskOrder
10/20/2009
$492.00
 
CA-0018
CA-0018-L22
City of Camden / Water Department
23
23
TaskOrder
10/15/2009
$80.51
 
CA-0018
CA-0018-L22
City of Camden / Water Department
21
21
TaskOrder
10/16/2009
$34.48
 
CA-0018
CA-0018-L01
Chicago Title Insurance Company
1
1
TaskOrder
5/6/2009
$335.00
 
CA-0018
CA-0018-L23
Camden Redevelopment Agency
1
1
TaskOrder
11/20/2009
($510.00)
 
CA-0018
CA-0018-L22
City of Camden / Water Department
4
4
TaskOrder
9/24/2009
$341.02
 
CA-0018
CA-0018-L22
City of Camden / Water Department
3
3
TaskOrder
7/23/2009
$10.63
Refer to RESDB
CA-0018
CA-0018-L22
City of Camden / Water Department
18
18
TaskOrder
10/16/2009
$191.78
 
CA-0018
CA-0018-L22
City of Camden / Water Department
15
15
TaskOrder
9/24/2009
$160.48
 
CA-0018
CA-0018-L22
City of Camden / Water Department
14
14
TaskOrder
9/24/2009
$16.52
 
CA-0018
CA-0018-L22
City of Camden / Water Department
11
11
TaskOrder
9/24/2009
$17.16
 
CA-0018
CA-0018-L22
City of Camden / Water Department
7
7
TaskOrder
9/24/2009
$265.01
 
CA-0018
CA-0018-P01
Site Contractors Inc.
1
1
Change Order
12/12/2005
$120,234.12
CCR1: Removal and disposal of approx. 3000 s.f. of ACM floor materials in the gym area as identified by VNH/PH and as authorized by NJSCC in accordance with CCD #2, dated 2/15/05. This change reflects negotiated values for this work as agreed between
CA-0018
CA-0018-L01
Chicago Title Insurance Company
3
3
TaskOrder
7/13/2009
$384.00
Refer to RESDB
CA-0018
CA-0018-L22
City of Camden / Water Department
34
34
TaskOrder
1/8/2010
$50.90
Refer to RESDB
CA-0018
CA-0018-L22
City of Camden / Water Department
19
19
TaskOrder
10/16/2009
$255.60
 
CA-0018
CA-0018-L18
Velka Garcia d/b/a United Dollar Plus
1
1
TaskOrder
9/22/2009
$383.61
 
CA-0018
CA-0018-L22
City of Camden / Water Department
20
20
TaskOrder
10/16/2009
$25.87
 
CA-0018
CA-0018-L22
City of Camden / Water Department
8
8
TaskOrder
9/24/2009
$260.78
 
CA-0018
CA-0018-L17
City of Camden / Water Department
1
1
TaskOrder
12/3/2009
($10.00)
 
CA-0018
CA-0018-A01
Nadaskay Kopelson Architects
1
1
Change Order
2/20/2004
$17,797.25
Conceptual Site Feasibility Studies in respond to Camden Redevelopment Agency's proposed Master Plan for Lanning Square Renaissance zone, consistent with attached (NKA) leters dated 12/11/03 and 2/4/04 and fee scheduled documented attachment. Archi
CA-0018
CA-0018-L22
City of Camden / Water Department
13
13
TaskOrder
9/24/2009
$17.16
 
CA-0018
CA-0018-L01
Chicago Title Insurance Company
5
5
TaskOrder
8/4/2009
$669.00
Refer to RESDB
CA-0018
CA-0018-L22
City of Camden / Water Department
17
17
TaskOrder
10/16/2009
$15.46
 
CA-0018
CA-0018-L22
City of Camden / Water Department
32
32
TaskOrder
1/8/2010
$44.80
Refer to RESDB
CA-0018
CA-0018-A01
Nadaskay Kopelson Architects
2
2
Change Order
5/19/2004
$17,500.00
Architect-Nadaskay Kopelson Architects Evalutate and modify the building plans as necessary, including meetings with consultants: 100 hours at $130.00/Hour (avg) Total Labor $13,000 Landscape Consultant-Forrest Assosicates Ltd. Total Consultant 4
CA-0018
CA-0018-L22
City of Camden / Water Department
24
24
TaskOrder
1/4/2010
$31.29
 
CA-0018
CA-0018-L08
Justina Bodden
1
1
TaskOrder
7/23/2009
($1,510.00)
 
CA-0018
CA-0018-L06
Broadway Family Practice PC
1
1
TaskOrder
8/27/2009
($1,637.76)
 
CA-0018
CA-0018-L08
Justina Bodden
2
2
 
9/24/2009
$59.01
Refer to RESDB
CA-0018
CA-0018-L03
Nelly Ortiz
1
1
TaskOrder
8/20/2009
($1,510.00)
 
CA-0020
CA-0020-L16
Alexander Sterin DBA Camden Cleaning Center
1
1
 
8/6/2009
$1,000.00
An additional $1000 was authorized for search expenses.
EC-0001
EC-0001-A08
PMK Group
 
1
 
4/11/2002
$24,341.05
Additional services and reimbursables required to evaluate feasibility and site utilization of nine additional sites to accommodate 16 additional temporary classroom units as directed by Ed Clark of NJEDA on 6/1/01 per invoice 37104, 6/30/01 $23,911.
EC-0001
EC-0001-A17
Thomas Associates Architects + Engineers
 
1
 
3/22/2002
$7,398.00
Modifications of the portion of the already constructed trailers (by others) to include a complete fire alarm system including sequence of operations.
EC-0001
EC-0001-F03
Virco
 
1
Change Order
10/14/2005
($7,838.00)
Multi project FF&E - Price decrease due to quantity adjustment.
EC-0001
EC-0001-A20
Lan Associates, Engineering, Planning, A
 
1
 
7/2/2002
$3,165.53
Additional work has been executed by Lan Assoc. Revisions to the drawings to provide as-built conditions which have already been forwarded and submitted to NJ Dept. Community Affairs.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
16
Change Order
10/16/2002
$124,054.59
Modifications to twelve (12) TCU'S at ten sites in Newark per William Scotsman's proposal dated 7/9/02 and additional vandalism @ Oliver & Lafayette schools as reported Bovis Lend Lease.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
20
Change Order
11/13/2003
$2,728.55
Labor and materials to balance the distribution of phases on the MDP at PS #27, Paterson.
EC-0001
EC-0001-L09
French & Parrello Associates, P.A.
 
2
 
12/17/2001
$2,600.00
Note: This is actually CO#1 - It had been missing and not entered into PMIS. Additional services due to existing environmental conditions based on calls and a site meeting with NJEDA, NJDEP, and representatives of the Passaic School District.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
3
Change Order
1/30/2002
$1,266,105.00
Cost of site work to support TCU installations at Roberto Clemente, Hawkins, Lafayette, Oliver, Wilson, Abington, Rafael Hernandez, Elliot, McKinley, and Lincoln School sites in Newark and at PS #2 in West New York.
EC-0001
EC-0001-A03
MRM Architecture
 
1
 
10/24/2001
$22,600.00
Provide site placement and site utility design and construction documents for 18 TCU'S at the Foodtown Property, on Lanza Ave. in Garfield, NJ in accordance with the NJEDA Scope of services dated June 12, 01 and MRM proposal dated 10/5/01. MRM will
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
15
Change Order
10/16/2002
$2,850,058.00
Cost of site work to support TCU installation (total 35 units) at Dayton Ave. Passaic, NJ.
EC-0001
EC-0001-A06
Chapin Architectural Services, P.A.
1
1
 
3/28/2002
$33,345.00
Apply to NJDEP for two (2) variances to (1) locate TCU's in flood plain and (2) to not provide access from outside the flood plain. Redo Site feasibility for an additional (8) totaling (39) TCU'S at the Dayton Ave. site. Redo site feasibility for
EC-0001
EC-0001-A10
Regan Young England Butera, PC
 
1
 
2/4/2002
$7,397.61
Architect to provide additional services to submit documetns to the NJ Pinelands Commission and the Fort Dix Directorate of Public Works for their review.
EC-0001
EC-0001-A19
Musial Group (The)
 
2
 
3/15/2002
$6,994.00
Consultant Fee's purposed in the original contract did not allow for borings, which were later insisted upon by Bovis Lend Lease.
EC-0001
EC-0001-A09
El Taller Colaborativo, PC
 
1
Change Order
9/24/2001
$10,350.00
A/E CHARGES FOR SCHEMATIC DESIGN OF ONE ADD. SITE EVALUATION OF LINCOLN PARK SCHOOL LOCATED IN NEWARK PS DISTRICT.
EC-0001
EC-0001-F01
Childcraft
 
1
Change Order
3/1/2004
$8,935.48
An additional 26 temporary classroom units
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
17
Change Order
2/28/2003
$384,787.77
Misc. change orders at TCU sites in Elizabeth, N. Brunswick, Garfield, Newark and Passaic per recommendations of Bovis Lend Lease and Williams Scotsman CO's 62,65,66,96,98,124,125,127,129,131,135,136,144,156,158,159,160,161, and 163.
EC-0001
EC-0001-A14
Kellenyi Johnson Wagner
 
1
Change Order
2/14/2002
$54,000.00
The construction schedule at the time of the change order did not afford the option of putting the work out to bid. The Architect had already completed the site feasibility and therefore, already had the baseline information to incorporate the const
EC-0001
EC-0001-A11
Ronald J. Angelo, R.A.P.A.
 
1
 
10/17/2001
$4,400.00
DOE increased scope from 10 to 16 TCU'S. Include feasibility site planning for the 6 additional TCU'S. Authorized by EDA Project Officer Ed Clark in memo of 6/12/01.
EC-0001
EC-0001-A17
Thomas Associates Architects + Engineers
 
3
 
6/6/2002
$21,891.00
Revised drawings in accordance with actual field construction as req. by EDA, per email 1/11/02 and meeting minutes of 1/13/02. Documents were revised per DCA requests, following field investigation inspections of the modifications which now superc
EC-0001
EC-0001-L06
Langan Engineering & Environmental Services, Inc.
 
1
 
12/16/2001
$3,200.00
Additional subsurface investigation near Cameo Cleaners ( an existing dry cleaning establishment )
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
6
Change Order
4/24/2002
$819,976.00
Cost of site work and utility hookups for 15 redeployed TCU'S at Jefferson and Roosevelt sites in Passaic. See attached breakout by site, Williams Scotsman proposals, and Bovis Lend Lease check estimate.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
7
Change Order
4/17/2002
$1,259,072.00
Cost of site work and utility hookups for 18 redeployed TCU'S at Lanza Ave. in Garfield as per attached Williams Scotsman proposal and Bovis Lend Lease check estimate.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
19
Change Order
10/24/2003
$254,007.00
Reallocation of 4 TCU's from New Brunswick Roosevelt School to New Brunswick High school.
EC-0001
EC-0001-A15
Remington & Vernick Engineers
 
1
 
9/21/2001
$46,300.00
 
EC-0001
EC-0001-L07
T & M Associates
 
1
 
1/17/2002
$11,650.00
Additional services to perform phase 1 preliminary assessment, subsurface investigation (gpr), site investigation, (si) and sampling analysis and geotechnical evaluation for TCU site parking area block 174.01.
EC-0001
EC-0001-A17
Thomas Associates Architects + Engineers
 
2
 
3/27/2002
$8,976.00
Electrical change scope as req. by PSEG . Revise drawings in accordance with actual field construction as directed by the EDA.
EC-0001
EC-0001-L09
French & Parrello Associates, P.A.
 
1
 
5/2/2002
$5,195.00
Additional services to perform remedial action plan and specification development, soil disposal coordination and remedial activity oversight per French and Parrello proposal dated 4/1/02 for a total estimated fee of $5195.00. NOTE: THIS IS ACTUAL
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
21
Change Order
4/2/2004
$134,790.00
Labor and Material csts to install a manhole on Van Houted Avenue in Passaic, NJ. Labor and material costs for rock removal from sheet.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
18
Change Order
10/31/2003
$119,750.00
Labor and material for removal of concrete retaining wall found in the ground of dayton Avenue site.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
12
Change Order
9/25/2002
$206,360.66
Misc. revisions to installed TCU sites in Elizabeth, Passaic, and Garfield as per attached CO requests.
EC-0001
EC-0001-C01
Modular Space Corporation
 
1
Change Order
6/28/2002
$6,400,809.00
Schedule G work at 18 sites including but not limited to, site preparation, grading, paving and walkways, fencing, decking and ramps (that were not in base contract) electrical tie-ins, fire alarm, intercom, telephone and security systems, plumbing t
EC-0001
EC-0001-A14
Kellenyi Johnson Wagner
 
2
Change Order
4/7/2003
($21,770.00)
In the original scope, Design Consultant was limited to providing construction documents for plan review and permitting with no construction phase services. At owner's request, DC was asked to re-design and revise the electrical and plumbing plans t
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
11
Change Order
6/7/2002
$19,250.00
Misc. change orders to TCU sites in Garfield and Paterson as per attached recommendation by Bovis Lend Lease and attached Williams Scotsman change orders no's: 69,79 and 84.
EC-0001
EC-0001-L06
Langan Engineering & Environmental Services, Inc.
 
2
 
1/9/2002
$22,250.00
Additional boundary and topographic survey and mapping for TCU site are and adjoining property. Also, additional Phase II environmental investigation to delineate extent of TCE soil and froundwater impacts at borings B-6 and B-7.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
4
Change Order
3/27/2002
$2,493,403.80
Furnish and install 20 TCU'S in Neptune, NJ per RFP dated Oct. 11,01 and revised on Oct. 24, 01. Work is complete. Attached are the reconciled costs between PMF and Contractor for entire SOW. This change includes the total final cost for the 20 T
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
14
Change Order
10/16/2002
$260,631.51
Misc. change orders at TCU sites in Elizabeth, New Brunswick, Garfield, Passaic & Newark per attached.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
5
Change Order
4/25/2002
$4,384,927.00
Furnish and install 36 additional TCU'S as per competitive change order for Wilson and Livingston sites in New Brunswick and Holloran, Washington, and Scott sites in Elizabeth. See attached breakout by site, Williams Scotsman proposals, and Bovis Le
EC-0001
EC-0001-A19
Musial Group (The)
 
1
 
3/15/2002
$3,940.96
Elizabeth TCU'S - George Washington School $1697.94 William Halloran School - $2243.02
EC-0001
EC-0001-A16
Vitetta
 
1
Change Order
9/21/2001
$182,000.00
Furnish contract documents and other services as per attached EDA RFP dated 7/20/01 and Vitetta propose dated 8/3/01.
EC-0001
EC-0001-A19
Musial Group (The)
 
3
 
7/30/2002
($18,748.90)
Exhibit A: revisions to drawings after completion of construction documents - 2 schools @ 2500.00 ea. Schools 1 and 22. Exhibit B: Changes to as built drawings for school's #1 & #22 $7000.00. Exhibit C: Revisions to as built drawings for William
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
9
Change Order
6/6/2002
$210,139.00
Additional decking, rear doors, additional security system, latch guards,replacement of porch lights,replace handrails,gutter down spouts. CCR #'S - 2,3,5 thru 29,34,73,74,81,85, and 86.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
1
Change Order
1/30/2002
$1,766,258.00
Cost of site work to support TCU installations at Lord Sterling E.S. and Lincoln E.S. in New Brunswick and at Elmora School #12, Roosevelt School #17 and Lafayette School #6 in Elizabeth.
EC-0001
EC-0001-A14
Kellenyi Johnson Wagner
 
3
Change Order
1/25/2005
$7,500.00
For the design consultant to provide services for the relocation of temporary classroom units (TCU) no.13 & 16 and associated TCU utilities at the Neptune campus.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
13
Change Order
9/23/2002
$165,000.00
Labor and material to dismantle, relocate and reinstall (2) TCU'S at Butler School per released DCA drawings dated 7/5/02.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
10
Change Order
5/17/2002
$243,218.00
Misc. change orders at TCU sites in Elizabeth, New Brunswick and Jersey City per recommendations by Bovis Lend lease. Williams Scotsman Co #'s 31,33,40,42 thru 50, 70 thru 72, 76 thru 78, 80,82,83,88 thru 91 and 94.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
8
Change Order
7/2/2002
$43,708.00
Misc. Change Order not assigned to a particular district as per attached recommendation by Bovis Lend Lease and attached William Scotsman Change Orders #4,32 and 87.
EC-0001
EC-0001-C02
Williams Scotsman, Inc.
 
2
Change Order
2/23/2002
$2,106,664.00
Cost of site work to support TCU installations at Roosevelt ES and Redshaw ES in New Brunswick and at Butler School #23, Wilson School #19, Columbus School #15 and Hudson School #25 in Elizabeth.
#Rows On Page: 502
$48,284,598.78
 
#Rows On Report: 15934
$750,533,396.10
 
Report Was Generated on 3/10/2010 5:55:59 PM Version .Net 7.1.200001