Page: 1 Regular Operating Disrict Managed Projects | | | | | | |
0185-010-03-0589 | Barnegat Township | Lillian M. Dunfee E.S. | Addition to existing school. Also includes security upgrade including additional survelliance cameras and associated technology. | School Facility Project | Addition To Existing Facility | Construction |
0185-015-03-0591 | Barnegat Township | Cecil S. Collins E.S. | Addition to existing school Also includes security upgrade including additional survelliance cameras and associated technology. | School Facility Project | Addition To Existing Facility | Construction |
0185-050-03-0306 | Barnegat Township | Russell O. Brackman M.S. | Water infiltration remediation of existing structure. | School Facility Project | Rehab of Existing Facility | Construction Bid |
0185-050-03-0593 | Barnegat Township | Russell O. Brackman M.S. | Addition to Middle School | School Facility Project | Addition To Existing Facility | Construction |
0185-070-03-0592 | Barnegat Township | Horbelt ES | Addition to existing school. Also includes security upgrade including additional survelliance cameras and associated technology. | School Facility Project | Addition To Existing Facility | Construction |
0185-N01-02-0025 | Barnegat Township | New Barnegat High School | Proposed High School Pre referendum for new high school. If referendum passes progress to design, bid, and construction. | School Facility Project | New Construction | Completed |
0185-N01-03-0655 | Barnegat Township | New Barnegat High School | Addition to new high school | School Facility Project | Addition To Existing Facility | Construction |
0185-N02-03-0656 | Barnegat Township | Joseph T. Donahue E.S. | New Construction of an elementary school to house 591. Also includes security upgrade including additional survelliance cameras and associated technology. | School Facility Project | New Construction | Construction |
0590-030-02-1021 | Buena Regional | Cleary Middle | New three classroom addition | School Facility Project | Addition and Rehab of Existing Facility | Completed |
0590-045-03-0842 | Buena Regional | Collings Lake E.S. | Replacement of HVAC units in 1967 wing | School Facility Project | Rehab of Existing Facility | Design |
0590-N01-02-2219 | Buena Regional | New Middle School | pre-development work - construction of new middle school | School Facility Project | New Construction | Construction |
0850-005-04-000V | Clark Township | Arthur L. Johnson H.S. | Renovations to school in areas pertaining to code requirements, health & safety improvements, building improvements, energy conservation and handicapped accessibility | School Facility Project | Rehab of Existing Facility | Construction |
0850-030-04-000T | Clark Township | Frank K. Hehnly E.S. | Renovations to school in areas pertaining to code requirements, health & safety improvements, building improvements, energy conservation and handicapped accessibility | School Facility Project | Rehab of Existing Facility | Construction |
0850-035-04-000U | Clark Township | Carl H. Kumpf M.S. | Renovations to school in areas pertaining to code requirements, health & safety improvements, building improvements, energy conservation and handicapped accessibility | School Facility Project | Rehab of Existing Facility | Construction |
0850-040-04-000W | Clark Township | Valley Road E.S. | Renovations to school in areas pertaining to code requirements, health & safety improvements, building improvements, energy conservation and handicapped accessibility | School Facility Project | Rehab of Existing Facility | Construction |
0997-030-02-0926 | Cumberland Regional District | Cumberland Regional H.S. | Multiple renovations to existing HS. Pre-development request for A/E selection for Ed. Specs/ Schematics | School Facility Project | Rehab of Existing Facility | Construction |
1300-020-05-0ABT | Egg Harbor City | Charles L. Spragg E.S. | Rehabilitate existing fourth grade classroms into pre-kindergarten classroom by adding toilet rooms. | School Facility Project | Rehab of Existing Facility | Construction |
1300-X01-04-0ADY | Egg Harbor City | New Middle School | Request for design work to build a New Middle School. | School Facility Project | New Construction | Construction |
1310-005-04-0AEB | Egg Harbor Township | Egg Harbor Township H.S. | Additions to the Existing High School to meet impending enrollment. | School Facility Project | Addition and Rehab of Existing Facility | Construction |
1310-N02-05-0ADZ | Egg Harbor Township | New Davenport E.S. #2 | New Davenport E.S. #2 | School Facility Project | New Construction | Construction |
1310-N03-05-0AEA | Egg Harbor Township | New Slaybaugh E.S. #3 | New Slaybaugh E.S. #3 | School Facility Project | New Construction | Construction |
1460-x01-00-0366 | Fairfield Township - Cumberland | Fairfield Township ES (aka New ES -x01) | New ES | School Facility Project | New Construction | Construction |
1790-050-04-0ABP | Greater Egg Harbor Regional High School District | Oakcrest H.S. | Pre-Development Request for renovations to the High School auditorium that includes replacement seating, flooring, sound wall panels, lighting system, sound system and wooden stage floor. | School Facility Project | Rehab of Existing Facility | Construction |
1790-N01-04-0AWJ | Greater Egg Harbor Regional High School District | New High School | New High School. | School Facility Project | New Construction | Construction |
2060-X01-04-0ASL | Harrison | New Harrison High School (-x01) | Synthetic Turf Grass Project | School Facility Project | New Construction | Completed |
2940-040-02-0798 | Manchester Township | Manchester Township H.S. | Physical plant upgrades and 43372 sq. ft. addition | School Facility Project | Addition and Rehab of Existing Facility | Completed |
2940-045-02-0496 | Manchester Township | Manchester Township M.S. | addition and program space upgrades. H/A upgrades, air-conditioning throughout; electrical service/distribution upgrades; fire alarm, intercom and public adress system upgrades | School Facility Project | Addition and Rehab of Existing Facility | Completed |
2940-060-02-0497 | Manchester Township | Whiting E.S. | Addition and media center expansion. Covered walkway to modulars. | School Facility Project | Addition and Rehab of Existing Facility | Completed |
3970-100-08-0HAA | Passaic City | Number 6, Martin Luther King, Jr. | Roofing | School Facility Project | Rehab of Existing Facility | PreDevelopment |
5900-050-02-0560 | Woodlynne Borough | Woodlynne E.S. | A new two-story classroom addition and preconstruction rehab of 6,300 SF removal and re-surfacing of concrete in playground | School Facility Project | Addition To Existing Facility | Completed |
#Rows On Page: 30 | | | | | | |
#Rows On Report: 30 | | | | | | |
Report Was Generated on 7/3/2009 9:47:20 PM Version .Net 7.1.200001 |