Page: 1 2 3 4 5 6 Regular Operating District Grant Projects | | | | | | | | | | |
0010-050-02-0870 | Absecon City | Emma C. Attales E.S. | Replace classroom doors in the 1958 section and two pairs of egress doors in the gym | School Facility Project | Rehab of Existing Facility | Completed | $17,450.00 | $17,450.00 | $6,980.00 | $10,470.00 |
0010-050-02-1166 | Absecon City | Emma C. Attales E.S. | Rehab including: upgrades to access drive, curbs and sidewalks, new lockers, bleachers & divider curtain in gym, replace roof, new HVAC system, toilet room upgrades, new security, data-ports, telephone & fire alarm systems | School Facility Project | Rehab of Existing Facility | Completed | $2,050,766.46 | $1,852,559.00 | $741,024.00 | $1,309,742.46 |
0010-060-02-0869 | Absecon City | H. Ashton Marsh E.S. | Replace toilet partitions with phenolic compartments | School Facility Project | Rehab of Existing Facility | Completed | $12,600.00 | $12,600.00 | $5,040.00 | $7,560.00 |
0010-060-02-1167 | Absecon City | H. Ashton Marsh E.S. | Rehab including: Playground upgrades, new wood floor in gym, replace roof, new floor finishes in classrooms & corridor, new HVAC system, electrical upgrades, new security, data-ports, telephone & fire systems. | School Facility Project | Rehab of Existing Facility | Completed | $1,766,739.81 | $1,766,739.81 | $706,695.92 | $1,060,043.89 |
0010-060-09-0jal | Absecon City | H. Ashton Marsh E.S. | Replacement/upgrade of all heat pumps | School Facility Project | Rehab of Existing Facility | Offered | $1,246,925.00 | $1,246,925.00 | $498,770.00 | $748,155.00 |
0020-005-01-0532 | Alexandria Township | Alexandria M.S. | Addition of Classrooms, SGI, Tech lab, science lab; Renovation of office space and storage space into core spaces | School Facility Project | Addition and Rehab of Existing Facility | Completed | $6,541,000.00 | $3,964,971.00 | $1,585,988.00 | $4,955,012.00 |
0020-010-03-0825 | Alexandria Township | Lester D. Wilson E.S. | Asbestos abatement, ceiling replacement, and asbestos flooring replacement. | School Facility Project | Rehab of Existing Facility | Completed | $80,579.25 | $80,579.25 | $32,231.70 | $48,347.55 |
0020-010-03-0826 | Alexandria Township | Lester D. Wilson E.S. | Replacement of fire alarm for the entire building. | School Facility Project | Rehab of Existing Facility | Completed | $74,511.72 | $74,511.72 | $29,804.69 | $44,707.03 |
0020-010-09-0OAV | Alexandria Township | Lester D. Wilson E.S. | Relocate main office and entrance of school to allow for a more controlled and secure entry point. | School Facility Project | Rehab of Existing Facility | Offered | $295,443.00 | $295,443.00 | $118,177.20 | $177,265.80 |
0030-010-03-0780 | Allamuchy Township | Allamuchy Township E.S. | 1. 5120 SF Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $59,247.00 | $59,247.00 | $23,698.80 | $35,548.20 |
0030-010-05-0AEE | Allamuchy Township | Allamuchy Township E.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $196,700.00 | $196,700.00 | $78,680.00 | $118,020.00 |
0040-010-00-0014 | Allendale | Brookside E.S. | Addition(s) to Brookside School and conversion of media center, music/art/home ec room | Retro | Addition To Existing Facility | Completed | $4,541,056.64 | $4,215,048.00 | $1,686,019.20 | $2,855,037.44 |
0040-010-09-0JAU | Allendale | Brookside E.S. | Replacement of unit ventilators and associated equipment. | School Facility Project | Rehab of Existing Facility | Offered | $284,840.00 | $284,840.00 | $113,936.00 | $170,904.00 |
0040-020-00-0013 | Allendale | Hillside E.S. | New 14,400-s.f. Construction - multipurpose room & music room. Rehab/Convert - 2 classrooms & 2 kindergartens. | Retro | Addition and Rehab of Existing Facility | Completed | $5,163,041.36 | $2,339,700.00 | $935,880.00 | $4,227,161.36 |
0060-020-04-0AEW | Alloway Township | Alloway Twp. E.S. | State Share Grant Request for a new addition and rehabilitation. | School Facility Project | Rehab of Existing Facility | Completed | $6,084,047.48 | $5,235,679.00 | $2,667,720.00 | $3,416,327.48 |
0070-010-02-0707 | Alpha | Alpha E.S. | Re-roofing - 1917 building section | School Facility Project | Rehab of Existing Facility | Executed | $37,950.00 | $37,950.00 | $18,175.36 | $19,774.64 |
0070-010-03-0817 | Alpha | Alpha E.S. | Exterior door replacement | School Facility Project | Rehab of Existing Facility | Completed | $56,340.00 | $45,106.00 | $23,076.00 | $33,264.00 |
0080-010-02-1052 | Alpine | Alpine Public E.S. | HVAC System Upgrade | School Facility Project | Rehab of Existing Facility | Completed | $524,701.00 | $432,210.00 | $172,884.00 | $351,817.00 |
0080-010-02-1098 | Alpine | Alpine Public E.S. | Classroom floor tile abatement and replacement | School Facility Project | Rehab of Existing Facility | Completed | $50,760.00 | $50,760.00 | $20,304.00 | $30,456.00 |
0080-010-03-1092 | Alpine | Alpine Public E.S. | Classroom Floor Tile Abatement. Classroom Floor Tile Replacement. | School Facility Project | Rehab of Existing Facility | Executed | $64,500.00 | $64,500.00 | $25,800.00 | $38,700.00 |
0090-010-04-0AKR | Andover Regional | Florence M. Burd E.S. | Addition and Rehabilitation | School Facility Project | Addition and Rehab of Existing Facility | Executed | $7,575,082.28 | $6,405,663.00 | $2,562,265.00 | $5,012,817.28 |
0090-040-04-0AEX | Andover Regional | Long Pond M.S. | Rehabilitation | School Facility Project | Rehab of Existing Facility | Executed | $368,897.05 | $347,390.00 | $138,956.00 | $229,941.05 |
0110-010-04-0AAY | Atlantic City | Atlantic City H.S. | Pre-Development request for Chiller replacement, Boiler replacement and air conditioning projects for the existing High School. | School Facility Project | Rehab of Existing Facility | Completed | $0.00 | $0.00 | $0.00 | $0.00 |
0110-050-04-0AAZ | Atlantic City | Chelsea Heights E.S. | Pre-Development request for a Fire Alarm and Detection System. | School Facility Project | Rehab of Existing Facility | Completed | $103,978.00 | $103,978.00 | $41,591.20 | $62,386.80 |
0110-N01-00-0067 | Atlantic City | Sovereign Avenue School | New Sovereign Avenue School | School Facility Project | New Construction | Completed | $21,644,820.00 | $13,705,332.00 | $5,482,133.00 | $16,162,687.00 |
0125-N01-99-0489 | Atlantic Cty Spec Serv Sch Dist | New Special Services School | The 177,000 sf facility will replace existing special services facility and will include multi-purpose room, a gymnasium, time-out rooms, and changing rooms. It will also provide job-training opportunities in the restaurant. | Retro | Addition and Rehab of Existing Facility | Completed | $24,426,000.00 | $24,426,000.00 | $9,770,400.00 | $14,655,600.00 |
0130-020-02-1112 | Atlantic Highlands | Atlantic Highlands E.S. | Addition of computer and science classrooms, cafeteria/multi-purpose room, etc. Renovations to kindergarten classroom, pre-K classroom, Music/band classroom, OT/PT classroom, small group rooms and admin spaces | School Facility Project | Addition and Rehab of Existing Facility | Completed | $6,291,102.02 | $5,207,826.00 | $2,083,130.00 | $4,207,972.02 |
0150-010-02-1042 | Audubon | Audubon H.S. | Boiler and partial roof replacement | School Facility Project | Rehab of Existing Facility | Completed | $135,816.50 | $135,816.50 | $64,664.95 | $71,151.55 |
0150-010-04-00BS | Audubon | Audubon H.S. | Additions and renovations to existing facility | School Facility Project | Addition and Rehab of Existing Facility | Executed | $13,834,664.50 | $12,067,657.00 | $5,681,740.00 | $8,152,924.50 |
0150-010-04-00LD | Audubon | Audubon H.S. | The district is removing and replacing asbestos containing ceiling tiles in 25000sf of space in the jr./sr. high school. | School Facility Project | Rehab of Existing Facility | Completed | $278,987.50 | $278,987.50 | $131,354.01 | $147,633.49 |
0150-040-04-00BR | Audubon | Haviland Avenue E.S. | Additions and renovations to existing facility | School Facility Project | Addition and Rehab of Existing Facility | Executed | $1,765,530.00 | $1,575,132.00 | $741,610.00 | $1,023,920.00 |
0150-050-04-00BQ | Audubon | Mansion Avenue E.S. | Additions and renovations to existing facility | School Facility Project | Addition and Rehab of Existing Facility | Executed | $2,091,164.03 | $2,091,164.03 | $984,570.21 | $1,106,593.82 |
0170-010-02-0735 | Avalon | Avalon E.S. | Addition including art and music rooms, library media center, health suite, admin suite, science greenhouse, kitchen receiving/storage and gymnasium | School Facility Project | Addition and Rehab of Existing Facility | Completed | $7,308,796.73 | $4,030,178.00 | $1,612,071.00 | $5,696,725.73 |
0180-010-02-0473 | Avon Borough | Avon E.S. | fire alarm system upgrade | School Facility Project | Rehab of Existing Facility | Completed | $15,638.00 | $15,638.00 | $6,255.00 | $9,383.00 |
0185-010-02-0660 | Barnegat Township | Lillian M. Dunfee E.S. | Renovation of Field #1 | School Facility Project | Rehab of Existing Facility | Executed | $88,143.48 | $88,143.48 | $60,955.98 | $27,187.50 |
0185-010-02-0661 | Barnegat Township | Lillian M. Dunfee E.S. | Rehabilitation of Field #2 | School Facility Project | Rehab of Existing Facility | Executed | $68,128.62 | $68,128.62 | $47,114.62 | $21,014.00 |
0185-010-02-0662 | Barnegat Township | Lillian M. Dunfee E.S. | Heating and ventilation project | School Facility Project | Rehab of Existing Facility | Executed | $494,107.75 | $494,107.75 | $341,702.19 | $152,405.56 |
0185-010-02-0663 | Barnegat Township | Lillian M. Dunfee E.S. | Carpet replacement | School Facility Project | Rehab of Existing Facility | Executed | $27,852.99 | $27,852.99 | $19,261.85 | $8,591.14 |
0185-010-02-1092 | Barnegat Township | Lillian M. Dunfee E.S. | Replacement of existing exterior doors and frames | School Facility Project | Rehab of Existing Facility | Executed | $57,980.00 | $57,980.00 | $40,096.30 | $17,883.70 |
0185-015-02-0640 | Barnegat Township | Cecil S. Collins E.S. | Improvement tp Physical Education Facilities Field #2 | School Facility Project | Rehab of Existing Facility | Executed | $166,801.00 | $166,801.00 | $115,351.90 | $51,449.10 |
0185-015-02-0657 | Barnegat Township | Cecil S. Collins E.S. | Renovation of Phys Ed Field #1 | School Facility Project | Rehab of Existing Facility | Executed | $96,252.00 | $96,252.00 | $66,563.46 | $29,688.54 |
0185-015-02-0658 | Barnegat Township | Cecil S. Collins E.S. | Heating and ventilation | School Facility Project | Rehab of Existing Facility | Executed | $634,541.33 | $634,541.33 | $438,819.59 | $195,721.74 |
0185-015-02-0659 | Barnegat Township | Cecil S. Collins E.S. | Carpet replacment | School Facility Project | Rehab of Existing Facility | Executed | $38,100.94 | $38,100.94 | $26,348.86 | $11,752.08 |
0185-015-02-0956 | Barnegat Township | Cecil S. Collins E.S. | addition of new district board office to the Collins ES | School Facility Project | Rehab of Existing Facility | Executed | $568,244.99 | $568,244.99 | $392,972.10 | $175,272.89 |
0185-020-02-0664 | Barnegat Township | Elizabeth V. Edwards E.S. | Carpet replacement | School Facility Project | Rehab of Existing Facility | Executed | $8,080.25 | $8,080.25 | $5,587.93 | $2,492.32 |
0185-050-02-0641 | Barnegat Township | Russell O. Brackman M.S. | Improvments to Phys Ed facilities filed #1 | School Facility Project | Rehab of Existing Facility | Executed | $114,229.20 | $114,229.20 | $78,995.66 | $35,233.54 |
0185-050-02-0642 | Barnegat Township | Russell O. Brackman M.S. | Improvement to Phs Ed facilities Field #2 | School Facility Project | Rehab of Existing Facility | Executed | $135,644.58 | $135,644.58 | $93,805.55 | $41,839.03 |
0185-050-02-0652 | Barnegat Township | Russell O. Brackman M.S. | H&V core area heat pump replacment | School Facility Project | Rehab of Existing Facility | Executed | $526,857.90 | $526,857.90 | $364,350.70 | $162,507.21 |
0185-050-02-0653 | Barnegat Township | Russell O. Brackman M.S. | Fresh air system | School Facility Project | Rehab of Existing Facility | Executed | $548,606.00 | $548,606.00 | $379,390.67 | $169,215.33 |
0185-050-02-0654 | Barnegat Township | Russell O. Brackman M.S. | heat and vent pump replacement | School Facility Project | Rehab of Existing Facility | Executed | $543,780.00 | $543,780.00 | $376,053.24 | $167,726.76 |
0185-050-02-0655 | Barnegat Township | Russell O. Brackman M.S. | Partial roof replacement | School Facility Project | Rehab of Existing Facility | Executed | $140,300.01 | $140,300.01 | $97,025.03 | $43,274.98 |
0185-050-02-0656 | Barnegat Township | Russell O. Brackman M.S. | Carpet replacement | School Facility Project | Rehab of Existing Facility | Executed | $53,437.81 | $53,437.81 | $36,955.13 | $16,482.68 |
0185-050-02-1066 | Barnegat Township | Russell O. Brackman M.S. | conversion of woodshop to special education classrooms | School Facility Project | Rehab of Existing Facility | Executed | $376,215.84 | $376,215.84 | $260,173.57 | $116,042.27 |
0190-010-04-00AP | Barrington Borough | Avon E.S. | Addition of classrooms | School Facility Project | Addition and Rehab of Existing Facility | Executed | $6,357,339.00 | $4,983,894.00 | $1,993,558.00 | $4,363,781.00 |
0190-030-04-00AQ | Barrington Borough | Woodland E.S. | A 3,448 gsf Addition of 2 new classrooms and new Teacher's Workroom. Project includes renovation as well. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $2,865,947.66 | $2,597,408.36 | $1,038,963.35 | $1,826,984.31 |
0210-020-02-0549 | Bay Head | Bay Head E.S. | Renovation of Boys/Girls toilet rooms; New electric service throughout the school; New branch circuits throughout the school | School Facility Project | Rehab of Existing Facility | Executed | $226,237.00 | $226,237.00 | $90,495.00 | $135,742.00 |
0220-020-04-00IJ | Bayonne | Bayonne H.S. | General capital improvements including : electrical, architectural, mechanical, plumbing, building energy. | School Facility Project | Rehab of Existing Facility | Executed | $10,907,451.66 | $10,907,451.66 | $4,362,980.66 | $6,544,471.00 |
0220-020-09-0OAK | Bayonne | Bayonne H.S. | ADA restroom upgrades; asbestos abatement & montoring; HVAC upgrades; lintel replacement & masonry repair; replace fire doors; replace main steam line valves; install ADA compliant doors | School Facility Project | Rehab of Existing Facility | Offered | $2,226,035.00 | $2,226,035.00 | $1,251,815.23 | $974,219.77 |
0220-030-04-0AEY | Bayonne | Number 3, Walter F. Robinson E.S. | Addition and capital improvements to the existing facility including architectural, site, mechanical, electrical, plumbing, life safety, and building systems. | School Facility Project | Rehab of Existing Facility | Executed | $12,743,046.00 | $8,785,245.00 | $3,514,098.00 | $9,228,948.00 |
0220-030-09-0OAL | Bayonne | Number 3, Walter F. Robinson E.S. | Lintel replacment & masonry repair; ADA restroom upgrades | School Facility Project | Rehab of Existing Facility | Offered | $1,080,750.00 | $1,080,750.00 | $607,761.92 | $472,988.08 |
0220-040-04-00IK | Bayonne | Number 12, John M. Bailey E.S. | General capital improvements including : electrical, mechanical,plumbing, building energy. | School Facility Project | Rehab of Existing Facility | Executed | $920,474.00 | $920,474.00 | $368,190.00 | $552,284.00 |
0220-040-09-0OAM | Bayonne | Number 12, John M. Bailey E.S. | Lintel replacement & mansonry repair | School Facility Project | Rehab of Existing Facility | Offered | $597,000.00 | $597,000.00 | $335,724.14 | $261,275.86 |
0220-040-97-0328 | Bayonne | Number 12, John M. Bailey E.S. | | Retro | Addition and Rehab of Existing Facility | Executed | $2,239,471.00 | $1,595,556.00 | $638,222.40 | $1,601,248.60 |
0220-050-04-00IL | Bayonne | Henry E. Harris No. 1 E.S. | General capital improvement to school # 1 including masonry, site, finishes, architectural, mechanical, electrical, plumbing, building performance and energy. | School Facility Project | Rehab of Existing Facility | Executed | $1,775,702.00 | $1,775,702.00 | $710,281.00 | $1,065,421.00 |
0220-050-09-0OAN | Bayonne | Henry E. Harris No. 1 E.S. | Asbestos abatement and monitoring, lintel replacement and masonry repair | School Facility Project | Rehab of Existing Facility | Offered | $638,125.00 | $638,125.00 | $358,850.87 | $279,274.13 |
0220-050-97-0375 | Bayonne | Henry E. Harris No. 1 E.S. | | Retro | Addition and Rehab of Existing Facility | Executed | $1,934,088.00 | $1,780,200.00 | $712,080.00 | $1,222,008.00 |
0220-060-04-00IM | Bayonne | Horace Mann No. 6 E.S. | General capital improvements including: architectural, mechanical,electrical, plumbing, site work, building energy. | School Facility Project | Rehab of Existing Facility | Executed | $531,855.00 | $531,855.00 | $212,742.00 | $319,113.00 |
0220-060-09-0OAO | Bayonne | Horace Mann No. 6 E.S. | Asbestos abatement and monitioring, lintel replacement & masonry repair; replace boiler feed and vacuum. | School Facility Project | Rehab of Existing Facility | Offered | $811,250.00 | $811,250.00 | $456,208.06 | $355,041.94 |
0220-070-04-00IN | Bayonne | Lincoln No. 5 E.S. | General capital improvements including: architectural, mechanical, electrical, plumbing, site work, building enrgy | School Facility Project | Rehab of Existing Facility | Executed | $686,718.00 | $686,718.00 | $274,687.00 | $412,031.00 |
0220-070-09-0OAP | Bayonne | Lincoln No. 5 E.S. | Lintel replacement & masonry repair; window replacement, ext door replacement | School Facility Project | Rehab of Existing Facility | Offered | $831,250.00 | $831,250.00 | $467,455.10 | $363,794.90 |
0220-080-04-00IO | Bayonne | Mary J. Donohoe No. 4 E.S. | General capital improvements including: architectural, mechanical, electrical, plumbing, site work, building enrgy | School Facility Project | Rehab of Existing Facility | Executed | $626,700.00 | $626,700.00 | $250,680.00 | $376,020.00 |
0220-080-09-0OAQ | Bayonne | Mary J. Donohoe No. 4 E.S. | ADA restroom upgrades; asbestos abatement & monitoring ;lintel replacement and masonry repair | School Facility Project | Rehab of Existing Facility | Offered | $957,443.00 | $957,443.00 | $538,429.99 | $419,023.01 |
0220-080-97-0327 | Bayonne | Mary J. Donohoe No. 4 E.S. | | Retro | Addition and Rehab of Existing Facility | Executed | $2,544,853.00 | $2,102,430.00 | $840,972.00 | $1,703,881.00 |
0220-085-04-00IP | Bayonne | Midtown Community E.S. | General capital improvements including: architectural, mechanical, electrical, plumbing, site work, building enrgy | School Facility Project | Rehab of Existing Facility | Executed | $2,205,104.00 | $2,205,104.00 | $882,042.00 | $1,323,062.00 |
0220-090-04-00IQ | Bayonne | Phillip G. Vroom No. 2 E.S. | General capital improvements including: Architectural and building systems energy efficiency. | School Facility Project | Rehab of Existing Facility | Executed | $266,250.00 | $266,250.00 | $106,500.00 | $159,750.00 |
0220-090-09-0OAR | Bayonne | Phillip G. Vroom No. 2 E.S. | Asbestos abatement & monitoring, lintel replacement and masonry repair; boiler vacuum and feed system replacment | School Facility Project | Rehab of Existing Facility | Offered | $687,600.00 | $687,600.00 | $386,673.24 | $300,926.76 |
0220-120-04-00IR | Bayonne | Washington No. 9 E.S. | General capital improvements including: architectural, electrical, building enrgy | School Facility Project | Rehab of Existing Facility | Executed | $2,316,984.00 | $2,316,984.00 | $926,794.00 | $1,390,190.00 |
0220-120-09-0OAS | Bayonne | Washington No. 9 E.S. | ADA restroom upgrades; lintel replacement and masonry repair; window replacement | School Facility Project | Rehab of Existing Facility | Offered | $1,493,500.00 | $1,493,500.00 | $839,872.71 | $653,627.29 |
0220-120-97-0373 | Bayonne | Washington No. 9 E.S. | | Retro | Addition and Rehab of Existing Facility | Executed | $3,461,000.00 | $3,091,200.00 | $1,236,480.00 | $2,224,520.00 |
0220-130-04-0AEZ | Bayonne | Woodrow Wilson No. 10 E.S. | Addition and capital improvements to the existing facility including architectural, mechanical,site, electrical, plumbing, life safety, and building systems. | School Facility Project | Rehab of Existing Facility | Executed | $10,843,544.00 | $7,550,803.00 | $3,020,321.00 | $7,823,223.00 |
0220-130-09-0OAT | Bayonne | Woodrow Wilson No. 10 E.S. | ADA restroom upgrades; lintel replacement and masonry repair. | School Facility Project | Rehab of Existing Facility | Offered | $1,258,250.00 | $1,258,250.00 | $707,579.40 | $550,670.60 |
0220-x02-04-0AFA | Bayonne | New School No.14 | Demolition of the existing school No. 14 and replacement with a new facility | School Facility Project | Rehab of Existing Facility | Completed | $17,998,205.00 | $10,010,000.00 | $4,004,000.00 | $13,994,205.00 |
0230-020-02-0977 | Beach Haven Borough | Beach Haven E.S. | Closure of underground oil tank | School Facility Project | Rehab of Existing Facility | Executed | $5,660.00 | $5,660.00 | $2,264.00 | $3,396.00 |
0230-020-02-1038 | Beach Haven Borough | Beach Haven E.S. | Conversion of oil burner to gas | School Facility Project | Rehab of Existing Facility | Executed | $8,500.00 | $8,500.00 | $3,400.00 | $5,100.00 |
0250-020-03-1123 | Belleville | Belleville Senior H.S. | Doors & hardware replacement | School Facility Project | Rehab of Existing Facility | Completed | $78,378.68 | $78,378.68 | $31,743.21 | $46,635.47 |
0250-020-04-0ASU | Belleville | Belleville Senior H.S. | Installation of Fiber Optic Communications System | School Facility Project | Rehab of Existing Facility | Executed | $177,502.00 | $177,502.00 | $71,888.00 | $105,614.00 |
0250-020-05-0AIL | Belleville | Belleville Senior H.S. | This project consists of the replacement of the existing roof. | School Facility Project | Rehab of Existing Facility | Completed | $734,077.39 | $734,077.39 | $297,299.87 | $436,777.52 |
0250-020-09-0MAW | Belleville | Belleville Senior H.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Offered | $1,049,540.00 | $1,049,540.00 | $468,782.00 | $580,758.00 |
0250-025-01-0805 | Belleville | Belleville M.S. | installation of an elevator | School Facility Project | Rehab of Existing Facility | Executed | $329,777.30 | $329,777.30 | $132,417.13 | $197,360.17 |
0250-025-03-1124 | Belleville | Belleville M.S. | doors & hardware replacement | School Facility Project | Rehab of Existing Facility | Completed | $53,490.38 | $53,490.38 | $21,663.50 | $31,826.88 |
0250-025-04-0ASV | Belleville | Belleville M.S. | Installation of Fiber Optic Communication System | School Facility Project | Rehab of Existing Facility | Executed | $75,908.00 | $75,908.00 | $30,743.00 | $45,165.00 |
0250-025-09-0MAX | Belleville | Belleville M.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Offered | $755,600.00 | $755,600.00 | $337,493.00 | $418,107.00 |
0250-050-03-0738 | Belleville | Number 3 E.S. | Window Replacement. | School Facility Project | Rehab of Existing Facility | Completed | $128,808.00 | $128,808.00 | $52,167.00 | $76,641.00 |
0250-050-03-1125 | Belleville | Number 3 E.S. | Doors and Hardware Replacement. | School Facility Project | Rehab of Existing Facility | Completed | $43,456.37 | $43,456.37 | $17,599.82 | $25,856.55 |
0250-050-04-0ASW | Belleville | Number 3 E.S. | Installation of Fiber Optic Communication System | School Facility Project | Rehab of Existing Facility | Executed | $75,908.00 | $75,908.00 | $30,743.00 | $45,165.00 |
0250-055-04-0ASX | Belleville | Number 4 E.S. | Installation of Fiber Optic Communication System | School Facility Project | Rehab of Existing Facility | Executed | $75,908.00 | $75,908.00 | $30,743.00 | $45,165.00 |
0250-060-03-0739 | Belleville | Number 5 E.S. | Replacement of Windows and Lintels. | School Facility Project | Rehab of Existing Facility | Executed | $516,709.45 | $516,709.45 | $209,266.00 | $307,443.45 |
0250-060-03-1126 | Belleville | Number 5 E.S. | Replacement of Exterior Doors & Hardware. | School Facility Project | Rehab of Existing Facility | Completed | $48,445.86 | $48,445.86 | $19,620.48 | $28,825.38 |
0250-060-04-0ASY | Belleville | Number 5 E.S. | Installation of Fiber Optic Communications System | School Facility Project | Rehab of Existing Facility | Executed | $75,908.00 | $75,908.00 | $30,743.00 | $45,165.00 |
0250-060-05-0AUX | Belleville | Number 5 E.S. | Asbestos Removal | School Facility Project | Rehab of Existing Facility | Completed | $75,670.00 | $75,670.00 | $30,646.20 | $45,023.80 |
0250-060-09-0MAY | Belleville | Number 5 E.S. | Electrical service upgrade | School Facility Project | Rehab of Existing Facility | Offered | $93,500.00 | $93,500.00 | $41,762.00 | $51,738.00 |
0250-070-03-1134 | Belleville | Number 7 E.S. | Window Replacement. | School Facility Project | Rehab of Existing Facility | Completed | $42,638.97 | $42,638.97 | $17,268.70 | $25,370.27 |
0250-070-04-0ASZ | Belleville | Number 7 E.S. | Installation of Fiber Optic Communications System | School Facility Project | Rehab of Existing Facility | Executed | $78,831.00 | $78,831.00 | $31,926.00 | $46,905.00 |
0250-080-03-0748 | Belleville | Number 8 E.S. | Roof Replacement. | School Facility Project | Rehab of Existing Facility | Completed | $171,349.65 | $171,349.65 | $69,396.27 | $101,953.38 |
0250-080-03-1135 | Belleville | Number 8 E.S. | Window, Doors and Hardware Replacement. | School Facility Project | Rehab of Existing Facility | Completed | $47,237.94 | $47,237.94 | $19,131.27 | $28,106.67 |
0250-080-04-0ATA | Belleville | Number 8 E.S. | Installation of Fiber Optic Communications System | School Facility Project | Rehab of Existing Facility | Executed | $75,908.00 | $75,908.00 | $30,743.00 | $45,165.00 |
0250-090-03-1200 | Belleville | Number 9 E.S. | Parapet Wall Repair | School Facility Project | Rehab of Existing Facility | Completed | $226,472.64 | $226,472.64 | $91,720.97 | $134,751.67 |
0250-090-04-0ATB | Belleville | Number 9 E.S. | Installation of Fiber Optic Communications System | School Facility Project | Rehab of Existing Facility | Executed | $75,908.00 | $75,908.00 | $30,743.00 | $45,165.00 |
0250-100-03-1127 | Belleville | Number 10 E.S. | Doors and Hardware Replacement. | School Facility Project | Rehab of Existing Facility | Completed | $6,288.42 | $6,288.42 | $2,546.80 | $3,741.62 |
0250-100-04-00LW | Belleville | Number 10 E.S. | Boiler replacement | School Facility Project | Rehab of Existing Facility | Completed | $441,874.59 | $441,874.59 | $178,958.33 | $262,916.26 |
0260-015-02-0871 | Bellmawr Borough | Bell Oaks E.S. | Emergent replacement of boilers | School Facility Project | Rehab of Existing Facility | Completed | $189,577.43 | $189,577.43 | $75,830.97 | $113,746.45 |
0260-015-04-0APD | Bellmawr Borough | Bell Oaks E.S. | Renovations of storm drainage and walkway. | School Facility Project | Rehab of Existing Facility | Executed | $29,083.81 | $29,083.81 | $11,633.52 | $17,450.29 |
0260-015-09-0MAF | Bellmawr Borough | Bell Oaks E.S. | Security system upgrades | School Facility Project | Rehab of Existing Facility | Offered | $60,000.00 | $60,000.00 | $31,371.00 | $28,629.00 |
0260-020-05-0APE | Bellmawr Borough | Bellmawr Park E.S. | Renovations of storm drainage and walkway | School Facility Project | Rehab of Existing Facility | Completed | $131,504.30 | $131,504.30 | $52,601.72 | $78,902.58 |
0260-020-09-0MAG | Bellmawr Borough | Bellmawr Park E.S. | Security system upgrades | School Facility Project | Rehab of Existing Facility | Offered | $50,000.00 | $50,000.00 | $26,143.00 | $23,857.00 |
0260-030-04-0APF | Bellmawr Borough | Ethel M. Burke E.S. | Renovations of classrooms and nurses area | School Facility Project | Rehab of Existing Facility | Completed | $204,237.45 | $204,237.45 | $81,694.98 | $122,542.47 |
0260-030-05-0APG | Bellmawr Borough | Ethel M. Burke E.S. | Renovations of storm drainage and walkway | School Facility Project | Rehab of Existing Facility | Completed | $338,189.41 | $338,189.41 | $135,275.76 | $202,913.65 |
0260-030-09-0MAH | Bellmawr Borough | Ethel M. Burke E.S. | Security system upgrades | School Facility Project | Rehab of Existing Facility | Offered | $60,000.00 | $60,000.00 | $31,371.00 | $28,629.00 |
0270-020-03-0419 | Belmar | Belmar E.S. | Roof replacement, emergency egress & exit lighting repairs, floor and ceiling replacement at classrooms & corridors, and asbestos abatement (roof) | School Facility Project | Rehab of Existing Facility | Completed | $2,465,636.00 | $2,465,636.00 | $986,254.40 | $1,479,381.60 |
0270-020-03-0480 | Belmar | Belmar E.S. | Upgrades to HVAC system | School Facility Project | Rehab of Existing Facility | Completed | $3,151,336.20 | $3,151,336.00 | $1,260,534.00 | $1,890,802.20 |
0280-020-02-0863 | Belvidere | Belvidere H.S. | Re-roofing | School Facility Project | Rehab of Existing Facility | Completed | $88,515.00 | $88,515.00 | $47,016.00 | $41,499.00 |
0280-030-03-0023 | Belvidere | Oxford Street E.S. | Rehabilitation - Capital Maintenance Replacement of approximately 14,500 sq ft. of roofing. Project affects health and safety by maintaining building envelope. | School Facility Project | Rehab of Existing Facility | Executed | $163,050.00 | $163,050.00 | $89,241.99 | $73,808.01 |
0280-050-05-0DAH | Belvidere | Third Street E.S. | Reroof existing shingle roof. | School Facility Project | Rehab of Existing Facility | Completed | $62,153.00 | $56,903.00 | $31,144.66 | $31,008.34 |
0285-030-03-0258 | Bergen County Special Services District | Program 1-Hearing Impaired | Total HVAC Mechanical System Replacement | School Facility Project | Rehab of Existing Facility | Completed | $219,933.90 | $194,247.00 | $77,699.00 | $142,234.90 |
0285-050-03-0259 | Bergen County Special Services District | Program 3-Emotionally Disturb. | Renovations to the HVAC equipment | School Facility Project | Rehab of Existing Facility | Completed | $1,254,724.48 | $1,254,724.48 | $501,889.79 | $752,834.69 |
0285-070-03-0375 | Bergen County Special Services District | Program 5-Life Skills | Alteration/renovation of 2-story masonry bldg, upgrade existing outdated MEP & fire protection systems & replace roofing sys. | School Facility Project | Rehab of Existing Facility | Completed | $2,996,967.89 | $2,994,359.00 | $1,197,744.00 | $1,925,824.02 |
0290-020-02-0220 | Bergen County Vocational School District | Academies Voc. & Tech. High, Hackensack | Academies Auto Trades - Rehab roof. | School Facility Project | Rehab of Existing Facility | Completed | $231,754.36 | $231,754.36 | $92,701.74 | $139,052.62 |
0290-020-02-0447 | Bergen County Vocational School District | Academies Voc. & Tech. High, Hackensack | Academies H.S. - Physics lab renovations. | School Facility Project | Rehab of Existing Facility | Completed | $1,792,000.00 | $1,792,000.00 | $716,800.00 | $1,075,200.00 |
0290-020-03-0633 | Bergen County Vocational School District | Academies Voc. & Tech. High, Hackensack | Renovations to existing facility | School Facility Project | Rehab of Existing Facility | Executed | $536,586.28 | $380,159.00 | $152,064.00 | $384,522.28 |
0290-020-03-0715 | Bergen County Vocational School District | Academies Voc. & Tech. High, Hackensack | Renovations to existing facility | School Facility Project | Rehab of Existing Facility | Completed | $956,285.74 | $956,285.74 | $382,514.30 | $573,771.44 |
0290-030-04-0AEF | Bergen County Vocational School District | Vocational, Paramus (Spec. Need) | One story addition to existing building linking two buildings that include 4 classrooms, one computer lab, and one Physics Lab. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $2,678,673.00 | $2,678,673.00 | $1,067,198.79 | $1,600,798.19 |
0290-070-01-0823 | Bergen County Vocational School District | Vocational, Teterboro | Addition of gymnasium, general classrooms, locker room, etc. | School Facility Project | Addition To Existing Facility | Completed | $5,307,159.00 | $5,307,159.00 | $2,122,864.00 | $3,184,295.00 |
0290-070-02-0095 | Bergen County Vocational School District | Vocational, Teterboro | Technical H.S - interior renovations/change of use of auditorium to SGI classrooms | School Facility Project | Rehab of Existing Facility | Completed | $85,000.00 | $85,000.00 | $34,000.00 | $51,000.00 |
0290-070-02-0445 | Bergen County Vocational School District | Vocational, Teterboro | Technical H.S. - Renovations to 3 Classrooms and a lab | School Facility Project | Rehab of Existing Facility | Completed | $305,000.00 | $305,000.00 | $122,000.00 | $183,000.00 |
0290-070-03-0543 | Bergen County Vocational School District | Vocational, Teterboro | Renovation to 3,300-gsf: 3 Academic classrooms & electronics lab (formerly masonry shop/storage). Related furniture & equipment. | School Facility Project | Rehab of Existing Facility | Completed | $1,099,491.07 | $912,269.00 | $364,908.00 | $734,583.07 |
0290-070-04-0AEG | Bergen County Vocational School District | Vocational, Teterboro | Change-of-use: Covert obsolete gym to auditorium. | School Facility Project | Rehab of Existing Facility | Executed | $721,362.00 | $721,362.00 | $288,545.00 | $432,817.00 |
0290-070-04-0AEH | Bergen County Vocational School District | Vocational, Teterboro | Change-of-use: Convert obsolete locker rooms to music instruction room. | School Facility Project | Rehab of Existing Facility | Executed | $273,400.00 | $273,400.00 | $109,360.00 | $164,040.00 |
0290-075-02-0446 | Bergen County Vocational School District | Vocational, Paramus | Technical Education Center - Renovations to science labs, vestibule, related furniture & equipment | School Facility Project | Rehab of Existing Facility | Completed | $205,308.46 | $205,308.46 | $82,123.38 | $123,185.08 |
0300-020-02-0901 | Bergenfield | Bergenfield H.S. | Refurbish 826 existing auditorium chairs | School Facility Project | Rehab of Existing Facility | Completed | $117,490.74 | $117,490.74 | $46,996.30 | $70,494.44 |
0300-020-02-1091 | Bergenfield | Bergenfield H.S. | ADA upgrades to Girl's and Boy's toilet rooms | School Facility Project | Rehab of Existing Facility | Completed | $159,469.55 | $159,469.55 | $63,787.82 | $95,681.73 |
0300-020-04-00LE | Bergenfield | Bergenfield H.S. | roof replacement | School Facility Project | Rehab of Existing Facility | Completed | $265,542.35 | $265,542.35 | $106,216.94 | $159,325.41 |
0300-040-04-00LF | Bergenfield | Franklin E.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Completed | $68,554.08 | $68,554.08 | $27,421.63 | $41,132.45 |
0300-050-00-0220 | Bergenfield | Hoover E.S. | Addition and renovations to school | Retro | Addition and Rehab of Existing Facility | Completed | $454,020.00 | $454,020.00 | $181,608.00 | $272,412.00 |
0300-050-02-0902 | Bergenfield | Hoover E.S. | Electrical upgrades including Technology wiring and associated split-system air conditioning unit | School Facility Project | Rehab of Existing Facility | Completed | $81,696.38 | $81,696.38 | $32,678.55 | $49,017.83 |
0300-050-04-00LG | Bergenfield | Hoover E.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Completed | $187,019.43 | $187,019.43 | $74,807.77 | $112,211.66 |
0300-060-02-0903 | Bergenfield | Jefferson E.S. | Electrical upgrades including technology and associated split-system air conditioning unit | School Facility Project | Rehab of Existing Facility | Completed | $101,027.83 | $101,027.83 | $40,411.13 | $60,616.70 |
0300-075-02-0904 | Bergenfield | Roy W. Brown M.S. | electrical upgrades including Technology wiring and associated split-sytem air conditioning unit | School Facility Project | Rehab of Existing Facility | Completed | $500,000.00 | $500,000.00 | $200,000.00 | $300,000.00 |
0300-075-04-00LH | Bergenfield | Roy W. Brown M.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $59,102.68 | $58,500.00 | $23,400.00 | $35,702.68 |
0300-080-04-00LI | Bergenfield | Washington E.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $92,459.39 | $92,459.39 | $36,983.76 | $55,475.63 |
0310-005-01-0236 | Berkeley Heights | Governor Livingston H.S. | Rehab - toilet rooms, repair roof, electrical system, upgrade science labs | Waiver | Addition and Rehab of Existing Facility | Completed | $1,489,732.16 | $1,489,732.16 | $595,892.86 | $893,839.30 |
0310-005-09-0XAZ | Berkeley Heights | Governor Livingston H.S. | ADA upgrades to exisiting toilet rooms. | School Facility Project | Rehab of Existing Facility | Offered | $545,550.00 | $545,550.00 | $218,220.00 | $327,330.00 |
0310-020-01-0233 | Berkeley Heights | Thomas P. Hughes E.S. | Rehab - toilet rooms/exhaust systems, ventilation system, electrical equipment, technology panels | Waiver | Addition and Rehab of Existing Facility | Completed | $328,091.95 | $325,255.65 | $130,102.26 | $197,989.69 |
0310-030-00-0355 | Berkeley Heights | Columbia M.S. | Rehab - Alt. to music area, install ramp/electrical equipment/intercom systems and replace doors/ent | Waiver | Addition and Rehab of Existing Facility | Completed | $5,365,025.00 | $3,786,892.00 | $1,514,756.80 | $3,850,268.20 |
0310-030-03-0838 | Berkeley Heights | Columbia M.S. | Removal of existing wheelchair lifts and replacement. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $69,682.26 | $63,941.00 | $25,576.00 | $44,105.86 |
0310-030-03-0938 | Berkeley Heights | Columbia M.S. | Removal and replacement of existing boilers. | School Facility Project | Rehab of Existing Facility | Completed | $625,301.16 | $625,301.16 | $250,120.46 | $375,180.70 |
0310-035-00-0356 | Berkeley Heights | Early Childhood Cnt.-Hamil Terr E.S | Rehab - elevator/restrooms, toilets, electrical equipment, replace exterior entrances, tech panels | Waiver | Addition and Rehab of Existing Facility | Completed | $715,993.47 | $715,993.47 | $286,397.39 | $429,596.08 |
0310-040-01-0234 | Berkeley Heights | Mountain Park E.S. | Rehab - toilet rooms/exhaust systems, electrical equipment, technology panels | Waiver | Addition and Rehab of Existing Facility | Completed | $339,428.00 | $339,428.00 | $135,771.20 | $203,656.80 |
0310-040-03-1323 | Berkeley Heights | Mountain Park E.S. | Remove and replace existing roof system and soffits. | School Facility Project | Rehab of Existing Facility | Completed | $661,127.00 | $661,127.00 | $264,451.00 | $396,676.00 |
0310-050-01-0235 | Berkeley Heights | William Woodruff E.S. | Rehab - Toilet rooms/exhaust systems, electrical equipment, technology panels | Waiver | Addition and Rehab of Existing Facility | Completed | $327,914.84 | $327,702.28 | $131,080.91 | $196,833.93 |
0320-020-02-0414 | Berkeley Township | Bayville E.S. | Addition of 5 classrooms, media center, 7 small group instruction spaces, 1 science lab, 2 vocal music/instrumental music romms, 2 speech rooms, 1 computer lab, 1 art room and a gym | School Facility Project | Addition and Rehab of Existing Facility | Executed | $5,491,372.73 | $4,294,522.00 | $1,717,809.00 | $3,773,563.73 |
0320-030-02-0415 | Berkeley Township | Clara B. Worth E.S. | Addition of 12 classrooms, 2 small group instruction spaces, science lab, media center, special education classroom and 2 vocal/instrumental music rooms. Various renovations. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $5,626,000.00 | $3,826,815.00 | $1,530,726.00 | $4,095,274.00 |
0320-030-09-0VAS | Berkeley Township | Clara B. Worth E.S. | Bolier replacement | School Facility Project | Rehab of Existing Facility | Executed | $334,800.00 | $334,800.00 | $133,920.00 | $200,880.00 |
0320-040-02-0416 | Berkeley Township | H & M Potter E.S. | Addition of new pre-K, K and general classrooms, science lab, vocal music, instrumental music, small group instruction, gymnasium and small kitchen. Various renovations. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $5,296,300.00 | $3,784,599.00 | $1,513,840.00 | $3,782,460.00 |
0320-N01-02-0417 | Berkeley Township | New Elementary School | New Elementary School facility | School Facility Project | New Construction | Executed | $16,661,101.48 | $11,871,312.00 | $4,748,525.00 | $11,912,576.46 |
0330-020-02-0993 | Berlin Borough | Berlin Community E.S. | New addition including classrooms, offices, expansion of multipurpose room, etc. Rehab for computer lab and SGI pulus toilet renovations and site work. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $7,592,995.00 | $6,596,349.00 | $2,681,050.00 | $4,911,945.00 |
0350-050-01-0527 | Bernards Township | Ridge H.S. | replace existing roof with a new roof - project includes a double tear off and a full replacement | School Facility Project | Rehab of Existing Facility | Completed | $1,120,262.00 | $1,120,262.00 | $448,104.80 | $672,157.20 |
0350-055-04-00CL | Bernards Township | William Annin M.S. | Replace boilers | School Facility Project | Rehab of Existing Facility | Executed | $397,000.00 | $397,000.00 | $158,800.00 | $238,200.00 |
0350-060-03-0947 | Bernards Township | Oak Street E.S. | Roof replacement and Exterior Brick re-pointing. | School Facility Project | Rehab of Existing Facility | Completed | $632,790.00 | $632,790.00 | $253,116.00 | $379,674.00 |
0350-060-05-0AQU | Bernards Township | Oak Street E.S. | Replace windows | School Facility Project | Rehab of Existing Facility | Executed | $174,930.00 | $174,930.00 | $69,972.00 | $104,958.00 |
0350-070-02-1005 | Bernards Township | Cedar Hill E.S. | replacement of heating pipes | School Facility Project | Rehab of Existing Facility | Completed | $191,248.47 | $191,248.47 | $76,499.38 | $114,749.09 |
0350-070-05-0AQV | Bernards Township | Cedar Hill E.S. | Replace windows | School Facility Project | Rehab of Existing Facility | Executed | $167,195.00 | $167,195.00 | $66,878.00 | $100,317.00 |
0350-080-02-0816 | Bernards Township | Liberty Corner E.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $292,720.00 | $292,720.00 | $117,088.00 | $175,632.00 |
0350-080-04-00CK | Bernards Township | Liberty Corner E.S. | Replace hot water boilers. | School Facility Project | Rehab of Existing Facility | Executed | $364,044.60 | $364,044.60 | $145,618.00 | $218,426.60 |
0350-080-05-0AQW | Bernards Township | Liberty Corner E.S. | Replace windows | School Facility Project | Rehab of Existing Facility | Executed | $195,064.00 | $195,064.00 | $78,026.00 | $117,038.00 |
0350-080-05-0CAO | Bernards Township | Liberty Corner E.S. | Replace windows and new classroom ceiling fans. | School Facility Project | Rehab of Existing Facility | Executed | $409,940.00 | $364,847.00 | $145,939.00 | $264,001.00 |
0370-020-00-0242 | Bethlehem Township | Ethel Hoppock Elementary | Renovation of existing interior spaces and exisiting systems | Waiver | Addition and Rehab of Existing Facility | Completed | $2,328,474.00 | $2,328,474.00 | $931,389.60 | $1,397,084.40 |
0370-020-05-0CAZ | Bethlehem Township | Ethel Hoppock Elementary | Roof Replacement, Ramp Repair & Regrading. | School Facility Project | Rehab of Existing Facility | Executed | $1,114,051.00 | $1,114,051.00 | $445,620.00 | $668,431.00 |
0370-070-00-0243 | Bethlehem Township | Thomas B. Conley E.S. | Renovation of existing spaces and existing systems | Waiver | Addition and Rehab of Existing Facility | Completed | $4,278,000.00 | $4,278,000.00 | $1,711,200.00 | $2,566,800.00 |
0370-070-05-0DAA | Bethlehem Township | Thomas B. Conley E.S. | Repave & stripe existing parking lot. Repair damaged curbs, crosswalks, & islands that are safety issues. | School Facility Project | Rehab of Existing Facility | Executed | $149,460.00 | $149,460.00 | $59,784.00 | $89,676.00 |
0380-025-09-0LAU | Beverly City | Beverly E.S. | Two PK classroom 6,070 SF addition with special education classroom, storage, two barrier-free-restrooms, roof replacement, window replacement, HVAC replacement, flooring replacement, bleacher replacement, etc. | School Facility Project | Rehab of Existing Facility | Offered | $7,216,988.00 | $5,937,437.00 | $2,970,606.00 | $4,246,382.00 |
0390-020-04-0AEI | Black Horse Pike Regional | Highland H.S. | Replacing entire flat roof due to extreme damage and leaking throughout the school. | School Facility Project | Rehab of Existing Facility | Completed | $1,594,321.24 | $1,594,321.24 | $921,232.29 | $673,088.95 |
0390-050-09-0MAI | Black Horse Pike Regional | Triton H.S. | HVAC and lighting system replacement in auditorium. | School Facility Project | Rehab of Existing Facility | Executed | $660,000.00 | $660,000.00 | $396,476.00 | $263,254.00 |
0400-030-02-0885 | Blairstown Township | Blairstown E.S. | boiler replacement | School Facility Project | Rehab of Existing Facility | Completed | $39,150.00 | $39,150.00 | $15,660.00 | $23,490.00 |
0400-030-04-0AZR | Blairstown Township | Blairstown E.S. | Upgrade/replacement of existing on-site sanitary sewerage system. | School Facility Project | Rehab of Existing Facility | Completed | $286,584.60 | $286,584.60 | $114,633.84 | $171,950.76 |
0410-020-02-0451 | Bloomfield Township | Bloomfield H.S. | Addition of 5 general and 7 science classrooms, auxillary gymnaium and storage, locker and fitness training rooms, kitchen area and support services facility, faculty diningand main office suite and rehabilitation of existing rooms | School Facility Project | Addition and Rehab of Existing Facility | Executed | $58,065,079.00 | $45,298,295.00 | $18,119,318.00 | $39,945,761.00 |
0410-030-02-0850 | Bloomfield Township | Bloomfield Middle | Installation of connections for computer equipment | School Facility Project | Rehab of Existing Facility | Completed | $357,874.00 | $357,874.00 | $143,149.60 | $214,724.40 |
0410-030-04-00MU | Bloomfield Township | Bloomfield Middle | Telecommunications upgrade | School Facility Project | Rehab of Existing Facility | Completed | $46,050.00 | $46,050.00 | $18,420.00 | $27,630.00 |
0410-050-02-0847 | Bloomfield Township | Berkeley E.S. | Stair tower repair and computer connections | School Facility Project | Rehab of Existing Facility | Completed | $14,769.00 | $14,769.00 | $5,907.00 | $8,862.00 |
0410-050-04-00MW | Bloomfield Township | Berkeley E.S. | Telecommunications upgrade. | School Facility Project | Rehab of Existing Facility | Completed | $30,978.00 | $30,978.00 | $12,391.00 | $18,587.00 |
0410-060-02-0851 | Bloomfield Township | Brookdale E.S. | Installation of connections for computer equipment and repair built-in gutter system | School Facility Project | Rehab of Existing Facility | Completed | $16,944.00 | $16,944.00 | $6,778.00 | $10,166.00 |
0410-060-04-00CV | Bloomfield Township | Brookdale E.S. | Interior Rehabilitation-replacement of asbestos floor tile and repair of stair tower. | School Facility Project | Rehab of Existing Facility | Completed | $52,217.00 | $52,217.00 | $20,887.00 | $31,330.00 |
0410-060-04-00MV | Bloomfield Township | Brookdale E.S. | Telecommunications upgrade. | School Facility Project | Rehab of Existing Facility | Completed | $21,512.00 | $21,512.00 | $8,605.00 | $12,907.00 |
0410-080-02-0852 | Bloomfield Township | Carteret E.S. | Window replacement and computer connections | School Facility Project | Rehab of Existing Facility | Completed | $161,694.00 | $161,694.00 | $64,677.60 | $97,016.40 |
0410-080-04-00MX | Bloomfield Township | Carteret E.S. | Telecommunications upgrade | School Facility Project | Rehab of Existing Facility | Completed | $27,498.00 | $27,498.00 | $10,999.00 | $16,499.00 |
0410-100-02-0854 | Bloomfield Township | Demarest E.S. | Installation of connections for computer equipment and replacement of PA system | School Facility Project | Rehab of Existing Facility | Completed | $14,847.00 | $14,847.00 | $5,939.00 | $8,908.00 |
0410-100-04-00MY | Bloomfield Township | Demarest E.S. | Telecommunications upgrade | School Facility Project | Rehab of Existing Facility | Completed | $28,033.00 | $28,033.00 | $11,213.00 | $16,820.00 |
0410-110-02-0856 | Bloomfield Township | Fairview E.S. | Computer connections and removal of ext. fire excape | School Facility Project | Rehab of Existing Facility | Completed | $47,843.00 | $47,843.00 | $19,137.20 | $28,705.80 |
0410-110-04-00MZ | Bloomfield Township | Fairview E.S. | Telecommunications upgrade | School Facility Project | Rehab of Existing Facility | Completed | $30,415.00 | $30,415.00 | $12,166.00 | $18,249.00 |
0410-120-04-00NA | Bloomfield Township | Forest Glen | Telecommunications upgrade | School Facility Project | Rehab of Existing Facility | Completed | $18,373.00 | $18,373.00 | $7,349.00 | $11,024.00 |
0410-130-02-0859 | Bloomfield Township | Franklin E.S. | Installation of connections for computer equipment | School Facility Project | Rehab of Existing Facility | Completed | $6,747.00 | $6,747.00 | $2,699.00 | $4,048.00 |
0410-130-04-00CU | Bloomfield Township | Franklin E.S. | Asbestos Floor tile replacement. | School Facility Project | Rehab of Existing Facility | Completed | $37,591.00 | $37,591.00 | $15,036.00 | $22,555.00 |
0410-130-04-00NB | Bloomfield Township | Franklin E.S. | Telecommunications upgrade | School Facility Project | Rehab of Existing Facility | Completed | $23,939.00 | $23,939.00 | $9,576.00 | $14,363.00 |
0410-140-02-0860 | Bloomfield Township | Oak View E.S. | Installation of connections for computer equipment | School Facility Project | Rehab of Existing Facility | Completed | $10,429.00 | $10,429.00 | $4,172.00 | $6,257.00 |
0410-140-03-1392 | Bloomfield Township | Oak View E.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $408,563.54 | $408,563.54 | $163,425.42 | $245,138.12 |
0410-140-04-00NC | Bloomfield Township | Oak View E.S. | Telecommunications upgrade | School Facility Project | Rehab of Existing Facility | Completed | $23,433.00 | $23,433.00 | $9,373.00 | $14,060.00 |
0410-140-09-0MAZ | Bloomfield Township | Oak View E.S. | Replacement of existing main boiler with new unit | School Facility Project | Rehab of Existing Facility | Offered | $222,747.00 | $222,747.00 | $89,099.00 | $133,648.00 |
0410-150-02-0861 | Bloomfield Township | Watsessing E.S. | Installation of connections for computer equipment | School Facility Project | Rehab of Existing Facility | Completed | $6,459.00 | $6,459.00 | $2,584.00 | $3,875.00 |
0410-150-04-00ND | Bloomfield Township | Watsessing E.S. | Telecommunications upgrade | School Facility Project | Rehab of Existing Facility | Completed | $26,521.00 | $26,521.00 | $10,608.00 | $15,913.00 |
0420-020-09-0WAT | Bloomingdale | Martha B. Day E.S. | Corridor, office and toilet room lighting upgrade. | School Facility Project | Rehab of Existing Facility | Offered | $87,702.00 | $87,702.00 | $35,081.00 | $52,621.00 |
0420-030-02-0612 | Bloomingdale | Samuel R. Donald E.S. | Replace the exisiting oil fired boilers with gas fired boilers and install new heating and ventilating system in the all purpose room | School Facility Project | Rehab of Existing Facility | Completed | $272,686.80 | $272,686.80 | $109,074.72 | $163,612.08 |
0420-050-04-00CF | Bloomingdale | Walter T. Bergen M.S. | replacement of deteriorated corrugated metal stormwatre pipe under parkign lot. Stormwater is running under the existing pipe. | School Facility Project | Rehab of Existing Facility | Completed | $93,354.00 | $93,354.00 | $37,342.00 | $56,012.00 |
0430-020-05-0AZH | Bloomsbury | Bloomsbury E.S. | Additions and alteration to existing building. | School Facility Project | Rehab of Existing Facility | Completed | $155,315.07 | $155,315.07 | $62,126.03 | $93,189.04 |
0440-020-02-0992 | Bogota | Bogota H.S. | Removal & replacment of stair tower doors | School Facility Project | Rehab of Existing Facility | Executed | $170,271.00 | $170,271.00 | $68,108.00 | $102,163.00 |
0440-020-09-0JAV | Bogota | Bogota H.S. | Repair and replace existing roofing | School Facility Project | Rehab of Existing Facility | Offered | $1,126,778.00 | $1,126,778.00 | $592,966.00 | $533,812.00 |
0440-030-02-0217 | Bogota | E. Roy Bixby E.S. | Additions and Renovations | School Facility Project | Addition and Rehab of Existing Facility | Completed | $5,056,518.00 | $4,082,805.00 | $1,369,435.00 | $3,687,083.00 |
0440-050-02-0218 | Bogota | Lillian M. Steen E.S. | Addition and Renovations | School Facility Project | Addition and Rehab of Existing Facility | Completed | $7,921,107.00 | $5,631,066.00 | $2,252,426.00 | $5,668,681.00 |
0450-020-02-1069 | Boonton Town | Boonton H.S. | auditorium upgrade | School Facility Project | Rehab of Existing Facility | Completed | $389,114.72 | $389,064.72 | $155,625.88 | $233,488.84 |
0450-020-03-1429 | Boonton Town | Boonton H.S. | The District has requested a state share grant to offset the cost of replacing the Intercom system at the high school. This is a non-educational project. | School Facility Project | Rehab of Existing Facility | Completed | $88,703.84 | $88,703.84 | $35,481.54 | $53,222.30 |
0450-020-03-1430 | Boonton Town | Boonton H.S. | The District has requested a State Share Grant to offset the costs of replacing two HC lifts. This is considered an Educational Project. | School Facility Project | Rehab of Existing Facility | Completed | $62,676.90 | $62,676.90 | $25,070.76 | $37,606.14 |
0450-020-04-00ZB | Boonton Town | Boonton H.S. | This district has requested a state share grant to offset the costs of replacing sections of the roof. This is considered a non-educational project. | School Facility Project | Rehab of Existing Facility | Completed | $230,850.00 | $230,850.00 | $92,340.00 | $138,510.00 |
0450-030-05-0ALC | Boonton Town | John Hill E.S. | The district has requested a state share gran to offset the osts of replacing the Multipurpose Room/Gym Flr. This is considered a non-educational project. | School Facility Project | Rehab of Existing Facility | Completed | $128,325.00 | $115,454.00 | $46,181.60 | $82,143.40 |
0450-040-03-0016 | Boonton Town | School Street E.S. | repairs to school's façade | School Facility Project | Rehab of Existing Facility | Completed | $148,305.00 | $148,305.00 | $59,322.00 | $88,983.00 |
0450-040-05-0AZT | Boonton Town | School Street E.S. | The project will be to replace the current equipment. | School Facility Project | Rehab of Existing Facility | Completed | $41,167.00 | $39,202.00 | $15,681.00 | $25,486.00 |
0460-060-02-1113 | Boonton Township | Rockaway Valley E.S. | New lighting | School Facility Project | Rehab of Existing Facility | Completed | $92,500.00 | $92,500.00 | $37,000.00 | $55,500.00 |
0460-060-05-0AUY | Boonton Township | Rockaway Valley E.S. | Playground Equipment Replacement | School Facility Project | Rehab of Existing Facility | Completed | $158,313.00 | $158,313.00 | $63,325.00 | $94,988.00 |
0475-060-02-0335 | Bordentown Regional School District | Clara Barton E.S. | renovations | School Facility Project | Rehab of Existing Facility | Completed | $1,831,755.00 | $1,132,109.00 | $452,844.00 | $1,378,911.00 |
0475-090-02-0336 | Bordentown Regional School District | MacFarland Elementary School | renovations | School Facility Project | Rehab of Existing Facility | Completed | $1,118,875.01 | $1,118,664.00 | $447,466.00 | $671,409.01 |
0475-090-02-1097 | Bordentown Regional School District | MacFarland Elementary School | replacement of hot water heaters | School Facility Project | Rehab of Existing Facility | Completed | $17,200.00 | $17,200.00 | $6,880.00 | $10,320.00 |
0475-100-02-0337 | Bordentown Regional School District | Peter Muschal School | corridor link and renovations | School Facility Project | Addition and Rehab of Existing Facility | Completed | $923,063.00 | $301,514.00 | $120,606.00 | $802,457.00 |
0475-N01-02-0338 | Bordentown Regional School District | Middle School (Existing High School) | conversion of existing high school to middle school/renovations | School Facility Project | Rehab of Existing Facility | Completed | $1,674,235.00 | $1,674,235.00 | $669,694.00 | $1,004,541.00 |
0475-N02-02-0339 | Bordentown Regional School District | New High School | new contruction - Block 58, Lots 6 & 5.01 | School Facility Project | New Construction | Executed | $37,420,503.00 | $19,938,792.00 | $7,975,517.00 | $29,444,986.00 |
0490-020-04-00EA | Bound Brook Borough | Bound Brook H.S. | Remove and replace existing wood gym floor. | School Facility Project | Rehab of Existing Facility | Completed | $136,201.00 | $136,201.00 | $54,480.40 | $81,720.60 |
0490-020-04-00XS | Bound Brook Borough | Bound Brook H.S. | Remove and replace existing wood gym bleachers. | School Facility Project | Rehab of Existing Facility | Completed | $86,595.00 | $86,595.00 | $34,638.00 | $51,957.00 |
0490-020-05-0ALA | Bound Brook Borough | Bound Brook H.S. | Renovations to Guidance Suite and Art room, | School Facility Project | Rehab of Existing Facility | Completed | $221,794.00 | $221,794.00 | $88,718.00 | $133,076.00 |
0490-020-05-0AUZ | Bound Brook Borough | Bound Brook H.S. | Renovations to 4 sub-standard classrooms. | School Facility Project | Rehab of Existing Facility | Completed | $206,485.00 | $206,485.00 | $82,594.00 | $123,891.00 |
0490-020-09-0ZBD | Bound Brook Borough | Bound Brook H.S. | Install new water feed distribution system into boiler room. | School Facility Project | Rehab of Existing Facility | Offered | $102,038.00 | $102,038.00 | $60,285.48 | $41,752.52 |
0490-030-09-0ZBE | Bound Brook Borough | Lafayette E.S. | Electrical service upgrade withnew sub main distribution board. | School Facility Project | Rehab of Existing Facility | Offered | $88,750.00 | $88,750.00 | $52,434.74 | $36,315.26 |
0490-030-09-0ZBF | Bound Brook Borough | Lafayette E.S. | Power and data modification and wiring for electrical equipment. | School Facility Project | Rehab of Existing Facility | Offered | $109,751.00 | $109,751.00 | $64,842.43 | $44,908.57 |
0490-035-09-0ZBG | Bound Brook Borough | LaMonte E.S. | Roof structure repair and ceiling design. | School Facility Project | Rehab of Existing Facility | Offered | $222,256.00 | $222,256.00 | $131,311.96 | $90,944.04 |
0490-040-04-000X | Bound Brook Borough | LaMonte Building | Remove existing doors and Replace with Fire Doors. | School Facility Project | Rehab of Existing Facility | Completed | $60,874.00 | $60,874.00 | $24,350.00 | $36,524.00 |
0490-050-09-0ZBH | Bound Brook Borough | Smalley E.S. | Power and data modification and wiring for electrical equipment. | School Facility Project | Rehab of Existing Facility | Offered | $109,750.00 | $109,750.00 | $64,841.84 | $44,908.16 |
0500-020-03-0358 | Bradley Beach | Bradley Beach E.S. | Building addition to house a 4-stop hydraulic elevator and entry vestibule. | School Facility Project | Rehab of Existing Facility | Completed | $450,088.47 | $450,088.47 | $180,035.39 | $270,053.08 |
0500-020-03-0414 | Bradley Beach | Bradley Beach E.S. | a) Renovation of toilet rooms, exterior doors, stairs and sidewalks, replace windows, provide windows. Provide ADA hardware, repair roof caves, gutters and soffits. | School Facility Project | Rehab of Existing Facility | Executed | $3,608,846.38 | $3,608,846.38 | $1,443,538.55 | $2,165,307.83 |
0510-020-00-0332 | Branchburg Township | Central M.S. | | Retro | Addition and Rehab of Existing Facility | Executed | $16,991,000.00 | $8,317,198.78 | $3,326,879.60 | $13,664,120.40 |
0510-020-04-00NG | Branchburg Township | Central M.S. | Replace roof, siding, HVAC controls and windows. | School Facility Project | Rehab of Existing Facility | Executed | $1,152,657.92 | $1,152,657.92 | $461,063.00 | $691,594.92 |
0510-020-04-00XT | Branchburg Township | Central M.S. | Interior security systems and roof finishes. | School Facility Project | Rehab of Existing Facility | Completed | $29,360.00 | $4,390.00 | $1,756.00 | $27,604.00 |
0510-020-04-0AED | Branchburg Township | Central M.S. | Install rails on the bleachers & install sound panels on the Cafeteria walls. | School Facility Project | Rehab of Existing Facility | Completed | $10,745.00 | $10,745.00 | $4,298.00 | $6,447.00 |
0510-050-00-0331 | Branchburg Township | Old York E.S. | | Retro | Addition and Rehab of Existing Facility | Completed | $376,935.00 | $290,000.00 | $116,000.00 | $260,935.00 |
0510-050-04-00NH | Branchburg Township | Old York E.S. | Replace boiler, HVAC controls, door and window replacement. | School Facility Project | Rehab of Existing Facility | Completed | $1,181,715.80 | $1,181,715.80 | $472,686.32 | $709,029.48 |
0510-050-04-00XU | Branchburg Township | Old York E.S. | Minor replacement of interior finishes, security equipment, and site work. | School Facility Project | Rehab of Existing Facility | Completed | $28,450.00 | $15,050.00 | $6,020.00 | $22,430.00 |
0510-050-04-00XV | Branchburg Township | Old York E.S. | Exterior lights and basketball backstops in the playground. | School Facility Project | Rehab of Existing Facility | Completed | $3,415.00 | $1,415.00 | $566.00 | $2,849.00 |
0510-060-00-0333 | Branchburg Township | Stony Brook E.S. | | Retro | Addition and Rehab of Existing Facility | Completed | $337,886.00 | $320,700.00 | $128,280.00 | $209,606.00 |
0510-060-04-00NF | Branchburg Township | Stony Brook E.S. | Replace HVAC controls and exterior door replacement | School Facility Project | Rehab of Existing Facility | Completed | $95,016.28 | $95,016.28 | $38,006.51 | $57,009.77 |
0510-060-04-0AEC | Branchburg Township | Stony Brook E.S. | Replace exterior building light fixtures, new exterior storage building addition, and ADA signage. | School Facility Project | Rehab of Existing Facility | Completed | $21,108.00 | $4,688.00 | $1,875.00 | $19,233.00 |
0510-090-00-0330 | Branchburg Township | Whiton E.S. | | Retro | Addition and Rehab of Existing Facility | Completed | $4,179,678.00 | $862,500.00 | $345,000.00 | $3,834,678.00 |
0510-090-03-1499 | Branchburg Township | Whiton E.S. | The project is the replacement of the HVAC energy control system. | School Facility Project | Rehab of Existing Facility | Completed | $8,100.00 | $8,100.00 | $3,240.00 | $4,860.00 |
0510-090-04-00NE | Branchburg Township | Whiton E.S. | The project is a replacement of the HVAC energy control sytem. | School Facility Project | Rehab of Existing Facility | Executed | $124,208.00 | $124,208.00 | $49,683.00 | $74,525.00 |
0530-020-02-0058 | Brick Township | Brick Township H.S. | Auxillary Gym added | School Facility Project | Addition To Existing Facility | Executed | $859,430.20 | $456,642.00 | $182,656.80 | $676,773.40 |
0530-020-03-0110 | Brick Township | Brick Township H.S. | Replace four deficient roof sections | School Facility Project | Rehab of Existing Facility | Completed | $574,767.96 | $574,767.96 | $229,907.18 | $344,860.18 |
0530-020-04-00SF | Brick Township | Brick Township H.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $233,575.54 | $233,575.54 | $93,430.22 | $140,145.32 |
0530-020-09-0VAU | Brick Township | Brick Township H.S. | Installation of new ADA chairlift at exiting stairs on corridors at two locations | School Facility Project | Rehab of Existing Facility | Offered | $84,950.00 | $84,950.00 | $33,980.00 | $50,970.00 |
0530-025-02-0057 | Brick Township | Brick Township Memorial H.S. | Addition of classrooms, groop instruction spaces, science labs, cafeteria, offices; rehab to cafeteria, kitchen an shop areas. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $7,853,993.96 | $6,689,992.00 | $2,675,997.00 | $5,177,996.96 |
0530-027-03-0111 | Brick Township | Brick Comm. Prim. Learn.Ctr. | Parapet repair. | School Facility Project | Rehab of Existing Facility | Completed | $119,409.32 | $71,170.00 | $28,468.00 | $90,941.32 |
0530-035-02-0066 | Brick Township | Emma Havens Young E.S. | Addition of elevator | School Facility Project | Rehab of Existing Facility | Completed | $203,420.45 | $184,100.00 | $73,640.00 | $129,780.45 |
0530-040-02-0064 | Brick Township | Hebertsville E.S. | Additions: Classrooms, New media/Library | School Facility Project | Addition and Rehab of Existing Facility | Completed | $683,600.00 | $451,260.00 | $180,504.00 | $503,096.00 |
0530-043-02-0060 | Brick Township | Lake Riviera M.S. | Additions: Classrooms, science labs, small group instruction rooms, expanded cafeteria/all purpose room, elevator | School Facility Project | Addition To Existing Facility | Completed | $3,489,713.33 | $3,463,800.00 | $1,385,520.00 | $2,104,193.33 |
0530-060-02-0063 | Brick Township | Midstreams E.S. | Additions: Classrooms, Library, Office complex. Existing library to be renovated into classrom | School Facility Project | Addition and Rehab of Existing Facility | Completed | $1,371,942.02 | $1,186,800.00 | $474,720.00 | $897,222.02 |
0530-070-02-0065 | Brick Township | Osbornville E.S. | Additions: Classrooms, New media/Library, Small group instruction room. Existing library into Storage. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $1,453,098.20 | $1,138,500.00 | $455,400.00 | $997,698.20 |
0530-070-09-0WAK | Brick Township | Osbornville E.S. | Partial roof replacement | School Facility Project | Rehab of Existing Facility | Offered | $85,600.00 | $85,600.00 | $34,240.00 | $51,360.00 |
0530-080-02-0062 | Brick Township | Veteran's Memorial E.S. | Additions: Classrooms, Kitchen - Rehab exisiting kitchen into storage space | School Facility Project | Addition and Rehab of Existing Facility | Completed | $1,928,280.92 | $1,435,200.00 | $574,080.00 | $861,120.00 |
0530-080-04-0ANW | Brick Township | Veteran's Memorial E.S. | replace the entire roof of this building | School Facility Project | Rehab of Existing Facility | Completed | $893,206.20 | $725,863.00 | $290,345.20 | $602,861.00 |
0530-090-02-0061 | Brick Township | Veteran's Memorial M.S. | Additions: Classroms, Science Labs, Small Group Instruction, Support and storage spaces | School Facility Project | Addition To Existing Facility | Completed | $2,207,316.75 | $2,207,316.75 | $882,926.70 | $1,324,390.05 |
0530-090-03-0112 | Brick Township | Veteran's Memorial M.S. | Remove and replace two deficient roof sections. | School Facility Project | Rehab of Existing Facility | Executed | $356,991.89 | $350,987.00 | $140,395.00 | $216,596.89 |
0530-N01-02-0059 | Brick Township | Educational Enrichment Complex | new construction including 8 classrooms, group instuction spaces, cafeteria, conference room, etc. | School Facility Project | New Construction | Completed | $3,985,908.92 | $2,815,200.00 | $1,126,080.00 | $2,859,828.92 |
0555-005-00-0185 | Bridgewater-Raritan Regional | Bridgewater-Raritan H.S. | | Retro | Addition and Rehab of Existing Facility | Completed | $19,660,000.00 | $15,412,043.00 | $6,164,817.20 | $13,495,182.80 |
0555-010-04-0ACG | Bridgewater-Raritan Regional | Bridgewater-Raritan M.S. | Partial re-roofing | School Facility Project | Rehab of Existing Facility | Completed | $1,400,567.18 | $1,400,567.18 | $560,226.87 | $840,340.31 |
0555-010-09-0XAF | Bridgewater-Raritan Regional | Bridgewater-Raritan M.S. | Partial unit ventilator replacement | School Facility Project | Rehab of Existing Facility | Executed | $1,097,861.00 | $1,097,861.00 | $439,144.00 | $658,717.00 |
0555-030-02-0665 | Bridgewater-Raritan Regional | Adamsville E.S. | renovatons to nurses office and pre-k classroom | School Facility Project | Rehab of Existing Facility | Completed | $276,672.00 | $276,672.00 | $110,668.80 | $166,003.20 |
0555-030-03-0263 | Bridgewater-Raritan Regional | Adamsville E.S. | New construction includes two classrooms, three kindergarten classrooms, one multi-purpose classroom, five SGI's, faculty and student toilets. Rehab includes electrical and communications upgrades. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $2,607,434.69 | $1,872,503.00 | $749,001.00 | $1,858,433.69 |
0555-030-04-00UP | Bridgewater-Raritan Regional | Adamsville E.S. | Alterations to Existing Building | School Facility Project | Rehab of Existing Facility | Completed | $11,796.63 | $11,796.63 | $4,718.65 | $7,077.98 |
0555-040-02-0961 | Bridgewater-Raritan Regional | Bradley Gardens E.S. | Partial reroofing project of 29,200 sf | School Facility Project | Rehab of Existing Facility | Completed | $250,005.00 | $250,005.00 | $100,002.00 | $150,003.00 |
0555-040-03-0270 | Bridgewater-Raritan Regional | Bradley Gardens E.S. | Rehabilitation includes electrical and communications upgrades. | School Facility Project | Rehab of Existing Facility | Completed | $99,560.00 | $99,560.00 | $39,824.00 | $59,736.00 |
0555-045-03-0268 | Bridgewater-Raritan Regional | Crim E.S. | Addition and alterations to existing building; new construction includes a new gymnasium, storage room and physical education instructors office. Rehab includes electrical and communications upgrades. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $1,094,355.84 | $773,454.00 | $309,382.00 | $784,973.84 |
0555-048-03-0267 | Bridgewater-Raritan Regional | Eisenhower E.S. | New construction includes twelve classrooms, two multi-purpose classrooms, five SGI's, one Music Room, two music practice rooms, storage rooms, an auxiliary gymnasium w/stage, boys and girls gang toilet rooms, etc. | School Facility Project | New Construction | Executed | $7,357,751.19 | $5,231,155.00 | $2,092,462.00 | $5,265,289.19 |
0555-048-04-00UU | Bridgewater-Raritan Regional | Eisenhower E.S. | Alterations to Existing Building | School Facility Project | Rehab of Existing Facility | Completed | $16,428.31 | $16,428.31 | $6,571.22 | $9,857.09 |
0555-063-03-0266 | Bridgewater-Raritan Regional | Hamilton E.S. | New Construction includes one Multi-Purpose classroom, three SGI's, one pre-school disabled classroom, five general classrooms, gymnasium w/storage room and boys and girls gang toilet rooms, etc. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $3,410,545.29 | $2,522,270.00 | $1,008,908.00 | $2,401,637.29 |
0555-065-03-0265 | Bridgewater-Raritan Regional | Hillside E.S. | Addition of music rooms, all-purpose room, general classroom, SGIs, computer room, auxiliary gym with storage, etc. Renovations include conversion of locker rooms to music practice room and two SGIs, etc. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $5,336,335.93 | $1,580,574.00 | $632,230.00 | $4,704,105.93 |
0555-065-04-00UQ | Bridgewater-Raritan Regional | Hillside E.S. | Alterations to Existing Building | School Facility Project | Rehab of Existing Facility | Completed | $17,490.13 | $17,490.13 | $6,996.05 | $10,494.08 |
0555-067-03-0264 | Bridgewater-Raritan Regional | John F. Kennedy E.S. | Addition and alterations to existing building; new construction includes gymnasium with stage and storage room, boys and girls gang toilets and Physical Education Office. Renovations include converting two classrooms to a kindergarten, etc | School Facility Project | Addition and Rehab of Existing Facility | Executed | $1,359,514.59 | $960,180.00 | $384,072.00 | $975,442.59 |
0555-105-03-0271 | Bridgewater-Raritan Regional | Van Holten E.S. | Addition and alterations to existing building; new construction includes gymnasium with stage and storage room, boys and girls gang toilets and Physical Education Office. Rehab includes electrical and communications upgrades. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $1,420,241.72 | $1,004,710.00 | $401,884.00 | $1,018,357.72 |
0555-N01-03-0574 | Bridgewater-Raritan Regional | Milltown Road E.S. | Land acquisition of 6+/-Acres from a partial of 17+/-Acress and construction of a New E.S. that is two stories high and is to house Pre-K to 4th grade. The facility has twenty-two general classrooms, three Kindergarten Classrooms, etc. | School Facility Project | New Construction | Executed | $13,947,499.41 | $9,384,000.00 | $3,753,600.00 | $10,193,899.41 |
0560-020-01-0392 | Brielle Borough | Brielle E.S. | Administration area classroom expansion/upgrade. Replace HVAC, mechanical, electrical and plumbing. | Waiver | Addition and Rehab of Existing Facility | Completed | $10,400,000.00 | $8,710,730.00 | $3,484,292.00 | $6,915,708.00 |
0560-020-04-0ADG | Brielle Borough | Brielle E.S. | Existing mechanical system replacement in existing gymnasium | School Facility Project | Rehab of Existing Facility | Completed | $98,991.00 | $98,991.00 | $39,596.00 | $59,395.00 |
0570-030-04-00KV | Brigantine City | Brigantine North School | Replace approximately 72,753 s.f. of existing roof system | School Facility Project | Rehab of Existing Facility | Completed | $459,368.88 | $459,368.88 | $183,747.55 | $275,621.33 |
0580-010-01-0397 | Brooklawn | Alice Costello E.S. | addition of gym and multipurpose room; rehab of windows, lighting, etc. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $3,256,950.00 | $2,900,850.00 | $1,697,679.00 | $1,559,271.00 |
0580-010-05-0AQQ | Brooklawn | Alice Costello E.S. | Replacement of doors, windows and boiler. (portion of approved project ) | School Facility Project | Rehab of Existing Facility | Completed | $495,585.00 | $495,585.00 | $308,959.73 | $186,625.51 |
0590-025-02-1205 | Buena Regional | Buena Regional H.S. | auditorium/ stage lighting and sound system replacement | School Facility Project | Rehab of Existing Facility | Completed | $188,595.00 | $188,595.00 | $122,187.00 | $66,408.00 |
0590-025-03-0840 | Buena Regional | Buena Regional H.S. | Replacement of HVAC unit ventilators in "B" wing of HS. | School Facility Project | Rehab of Existing Facility | Completed | $467,794.45 | $467,794.45 | $303,075.14 | $164,719.31 |
0590-025-03-0841 | Buena Regional | Buena Regional H.S. | Replacement of approximately 1,100 student lockers. | School Facility Project | Rehab of Existing Facility | Completed | $165,141.21 | $165,141.21 | $106,991.85 | $58,149.36 |
0590-045-99-0189 | Buena Regional | Collings Lake E.S. | Addition to school | Retro | Addition To Existing Facility | Completed | $717,324.00 | $717,324.00 | $466,427.00 | $250,897.00 |
0590-055-00-0258 | Buena Regional | John C. Milanesi E.S. | Addition and Renovation of existing facility. | Retro | Addition and Rehab of Existing Facility | Completed | $1,739,699.00 | $1,739,699.00 | $1,131,207.96 | $608,491.04 |
0590-055-02-0726 | Buena Regional | John C. Milanesi E.S. | New 28,000 sf wood truss roof over existing built-up roof and window replacement in cafeteria. | School Facility Project | Rehab of Existing Facility | Executed | $526,019.58 | $526,019.58 | $353,467.80 | $172,551.78 |
0590-N02-09-0JAM | Buena Regional | Buena Regional ECC | New early childhood center for 274 students - 19 new classrooms and 2 special education classrooms, admin offices, multipurpose room and various ancillary spaces. | School Facility Project | New Construction | Offered | $9,521,039.00 | $5,523,375.00 | $3,719,643.00 | $5,801,396.00 |
0610-030-02-0499 | Burlington County Vocational School District | Inst of Tech-Westampton | Fire alarm upgrade, auditorium asbestos removal, auditorium renovation. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $24,981,028.00 | $24,981,028.00 | $9,992,411.00 | $14,988,617.00 |
0610-040-02-0500 | Burlington County Vocational School District | Inst of Tech-Medford Campus | Fire alarm system and partial renovation of 2 special ed. Classrooms | School Facility Project | Addition and Rehab of Existing Facility | Completed | $19,242,967.00 | $19,242,967.00 | $7,697,187.00 | $11,545,780.00 |
0620-025-03-1071 | Burlington Township | Thomas O. Hopkins M.S. | Addition and Renovation to accommodate Central Admin & classroom space. Other systems improvements | School Facility Project | Addition and Rehab of Existing Facility | Executed | $2,892,500.00 | $2,892,500.00 | $1,425,471.00 | $1,467,029.00 |
0620-030-03-1072 | Burlington Township | B. Bernice Young E.S. | District is adding 6 kindergarten and 12 first grade rooms to accommodate increased projected enrollment. | School Facility Project | Addition To Existing Facility | Completed | $3,890,741.84 | $3,718,000.00 | $1,832,291.00 | $2,089,182.64 |
0620-030-04-0ANN | Burlington Township | B. Bernice Young E.S. | Replacement of existing boiler | School Facility Project | Rehab of Existing Facility | Executed | $276,574.49 | $276,574.49 | $136,300.33 | $140,274.16 |
0620-030-05-0ANP | Burlington Township | B. Bernice Young E.S. | Expansion of the existing cafeteria | School Facility Project | Addition and Rehab of Existing Facility | Executed | $1,127,211.00 | $738,285.00 | $363,839.00 | $763,372.00 |
0620-N01-03-1073 | Burlington Township | New Middle School | Construction of a new middle school | School Facility Project | New Construction | Executed | $30,372,867.55 | $25,121,382.00 | $12,380,229.00 | $17,992,638.55 |
0630-020-02-0069 | Butler | Butler H.S. | replacement of intercom/phone system for the Butler High School | School Facility Project | Rehab of Existing Facility | Completed | $50,150.00 | $50,150.00 | $20,060.00 | $30,090.00 |
0630-020-02-0951 | Butler | Butler H.S. | re-roofing | School Facility Project | Rehab of Existing Facility | Executed | $291,160.90 | $291,160.90 | $116,464.36 | $174,696.54 |
0630-020-03-0942 | Butler | Butler H.S. | Project consists of facility upgrades to the existing school building including replacement of interior and exterior doors; windoew replacement; removal of asbestos tile flooring; replacement of stair treads; ADA compliance, etc. | School Facility Project | Rehab of Existing Facility | Completed | $3,077,298.35 | $3,077,298.35 | $1,230,919.34 | $1,846,379.01 |
0630-020-03-1437 | Butler | Butler H.S. | The project consists of athletic field and faclity upgrades. | School Facility Project | Rehab of Existing Facility | Completed | $435,000.00 | $428,000.00 | $171,200.00 | $263,800.00 |
0630-025-02-0070 | Butler | Aaron Decker E.S. | intercom/phone system | School Facility Project | Rehab of Existing Facility | Completed | $24,675.00 | $24,675.00 | $9,870.00 | $14,805.00 |
0630-025-02-0952 | Butler | Aaron Decker E.S. | re-roofing | School Facility Project | Rehab of Existing Facility | Completed | $148,604.40 | $148,604.40 | $59,441.76 | $89,162.64 |
0630-025-03-0943 | Butler | Aaron Decker E.S. | The project consists of facility upgrades to the existing school building including: fire alarm replacement, exterior lighting, asbestos tile, floor removal, window replacement; ADA signage; ADA toilet. | School Facility Project | Rehab of Existing Facility | Completed | $1,709,152.79 | $1,709,152.79 | $683,661.12 | $1,025,491.67 |
0630-030-02-0071 | Butler | Richard Butler E.S. | intercom/phone system | School Facility Project | Rehab of Existing Facility | Completed | $24,950.00 | $24,950.00 | $9,980.00 | $14,970.00 |
0630-030-03-0799 | Butler | Richard Butler E.S. | Provide an ADA-Compliant Egress Doorway and Walkway at the Richard Butler Elementary School. | School Facility Project | Rehab of Existing Facility | Completed | $32,300.00 | $32,300.00 | $12,920.00 | $19,380.00 |
0630-030-03-0941 | Butler | Richard Butler E.S. | This project consists of facility upgrades to the existing school building including replacement of fire alarm, removal of asbestos tile flooring, roof replacement; window replacement; ADA compliance including signage: toilet; hardware | School Facility Project | Rehab of Existing Facility | Completed | $2,555,049.76 | $2,536,630.00 | $1,014,652.00 | $1,540,397.76 |
0640-x01-01-0303 | Byram Township | New K-5 E.S. (-x01) | | Waiver | New Construction | Completed | $16,775,000.00 | $11,523,000.00 | $4,609,200.00 | $12,165,800.00 |
0660-060-05-0ARX | Caldwell-West Caldwell | Grover Cleveland J.H.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $99,900.00 | $99,900.00 | $39,960.00 | $59,940.00 |
0660-070-02-0437 | Caldwell-West Caldwell | Jefferson E.S. | Window replacement | School Facility Project | Rehab of Existing Facility | Completed | $95,700.00 | $95,700.00 | $38,280.00 | $57,420.00 |
0660-070-03-0885 | Caldwell-West Caldwell | Jefferson E.S. | Replacement of Roof Section. | School Facility Project | Rehab of Existing Facility | Completed | $49,460.45 | $49,460.45 | $19,784.18 | $29,676.27 |
0660-070-04-00IS | Caldwell-West Caldwell | Jefferson E.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Completed | $421,162.50 | $421,162.50 | $168,465.00 | $252,697.50 |
0660-120-02-0438 | Caldwell-West Caldwell | Wilson E.S. | Window Replacement | School Facility Project | Rehab of Existing Facility | Completed | $310,750.00 | $310,750.00 | $124,300.00 | $186,450.00 |
0660-120-04-00GB | Caldwell-West Caldwell | Wilson E.S. | Mold Remediation | School Facility Project | Rehab of Existing Facility | Completed | $148,744.42 | $148,744.42 | $59,497.77 | $89,246.65 |
0660-120-04-00IT | Caldwell-West Caldwell | Wilson E.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Completed | $323,137.50 | $323,137.50 | $129,255.00 | $193,882.50 |
0700-030-04-00PT | Camden County Vocational School District | Camden Co. Technical V.S. (Pennsauken) | Roof replacement of the 1926 Section(Academic Wing) totaling 32,750 sf. | School Facility Project | Rehab of Existing Facility | Executed | $432,300.00 | $432,300.00 | $229,780.00 | $202,520.00 |
0710-050-02-1037 | Cape May City | Cape May City E.S. | roof replacement | School Facility Project | Rehab of Existing Facility | Completed | $380,200.00 | $380,200.00 | $152,080.00 | $228,120.00 |
0710-050-03-0061 | Cape May City | Cape May City E.S. | replacement of acoustical wall treatment in pool and ceramic tile replacement in pool | School Facility Project | Rehab of Existing Facility | Completed | $77,969.00 | $74,500.00 | $29,800.00 | $48,169.00 |
0710-050-03-0154 | Cape May City | Cape May City E.S. | State Share Grant Request for non-educational rehabilitation project for boiler replacement with piping. | School Facility Project | Rehab of Existing Facility | Executed | $137,629.30 | $137,629.30 | $55,052.00 | $82,577.30 |
0715-020-04-00YU | Cape May County Special Services District | Alternative School H.S. | Replacement of the following systems totaling 33,027; 1981 roof, main electric service-underground conduit substation and switchgear, and HVAC mechanical system. | School Facility Project | Rehab of Existing Facility | Completed | $1,093,579.00 | $1,093,579.00 | $437,432.00 | $656,147.00 |
0715-020-04-00YV | Cape May County Special Services District | Alternative School H.S. | Addition of basketball court, rehabilitation of faculty office and area into a Driver Ed classroom. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $86,954.00 | $86,954.00 | $34,782.00 | $52,172.00 |
0715-075-04-00YW | Cape May County Special Services District | George E. Bailey M.S. | Replacement of main electrical service(91,846 sf) | School Facility Project | Rehab of Existing Facility | Completed | $86,560.64 | $86,560.64 | $33,733.00 | $50,600.00 |
0715-095-04-00YX | Cape May County Special Services District | Ocean Academy | Replacemnt of roof, main electric service, and HVAC mechanical system. | School Facility Project | Rehab of Existing Facility | Completed | $1,087,919.00 | $1,087,919.00 | $435,168.00 | $652,751.00 |
0715-095-05-00YY | Cape May County Special Services District | Ocean Academy | Educational rehabilitation project to replace existing playground with new surface and equipment | School Facility Project | Rehab of Existing Facility | Completed | $151,178.00 | $151,178.00 | $60,471.00 | $90,707.00 |
0720-030-03-0412 | Cape May County Vocational School District | Cape May Co. Tech. H.S. | Rehab of 157,665 s.f. involving electrical distribution, HVAC, exterior closure and site improvements | School Facility Project | Rehab of Existing Facility | Completed | $2,819,672.28 | $2,819,672.28 | $1,127,868.91 | $1,691,803.37 |
0740-n01-04-00GY | Carlstadt | Replacement of the Lindbergh School | The district proposed to close two schools and replaced this school with a larger school to accommodate all of the children in the district. | School Facility Project | New Construction | Executed | $25,055,592.28 | $10,456,572.00 | $4,182,629.00 | $20,872,963.28 |
0745-050-09-0JAW | Carlstadt-East Rutherford Regional High School Dis | Henry P. Becton Regional H.S. | New windows, HVAC system, sprinkler system; Reconfiguration of existing guidance and study team office. Realignment of existing general classrooms and addition of special education and small group instruction classrooms. | School Facility Project | Addition To Existing Facility | Offered | $33,050,536.00 | $27,701,390.00 | $11,080,556.00 | $21,969,980.00 |
0760-050-01-0474 | Cedar Grove Township | Cedar Grove (Memorial) H.S. | rehabilitation for Health and Life Safety | School Facility Project | Rehab of Existing Facility | Executed | $1,279,000.00 | $1,279,000.00 | $511,600.00 | $767,400.00 |
0760-050-02-0109 | Cedar Grove Township | Cedar Grove (Memorial) H.S. | replacement of auditorium roof | School Facility Project | Rehab of Existing Facility | Completed | $322,000.00 | $322,000.00 | $128,800.00 | $193,200.00 |
0760-060-01-0475 | Cedar Grove Township | North End E.S. | rehabilitation for H&S and ADA compliance | School Facility Project | Rehab of Existing Facility | Executed | $412,500.00 | $412,500.00 | $165,000.00 | $247,500.00 |
0760-090-01-0476 | Cedar Grove Township | South End E.S. | rehab for H&S, and ADA compliance | School Facility Project | Rehab of Existing Facility | Executed | $240,000.00 | $240,000.00 | $96,000.00 | $144,000.00 |
0760-x01-01-0473 | Cedar Grove Township | Ridge Road Middle School | rehab for H&S and an addition for educational adequacy | School Facility Project | Addition and Rehab of Existing Facility | Completed | $11,896,060.00 | $7,762,400.00 | $3,104,960.00 | $8,791,100.00 |
0770-030-01-0131 | Central Regional | Central Regional H.S. | New sewage pump station, install new electrical service panel and breakers. Replace roof and unit ventilators. | Waiver | Addition and Rehab of Existing Facility | Completed | $14,187,005.19 | $14,187,005.19 | $5,674,802.08 | $8,512,203.11 |
0770-050-01-0130 | Central Regional | Central Regional M.S. | | Waiver | Addition and Rehab of Existing Facility | Completed | $4,793,329.00 | $4,568,490.00 | $1,827,396.00 | $2,965,933.00 |
0785-010-00-0055 | Chathams, Sch Dist Of The | Chatham H.S. | additions-various upgrades and renovations | Retro | Addition and Rehab of Existing Facility | Completed | $18,394,736.00 | $8,514,499.00 | $3,405,799.60 | $14,988,936.40 |
0785-010-04-00SH | Chathams, Sch Dist Of The | Chatham H.S. | New roof at the High School. | School Facility Project | Rehab of Existing Facility | Completed | $468,136.25 | $468,136.25 | $187,254.50 | $280,881.75 |
0785-030-00-0054 | Chathams, Sch Dist Of The | Chatham M.S. | additions-various upgrades and renovations | Retro | Addition and Rehab of Existing Facility | Completed | $3,021,209.00 | $1,804,086.00 | $721,634.40 | $2,299,574.60 |
0785-030-05-0ANX | Chathams, Sch Dist Of The | Chatham M.S. | Proposed additions and alternations to existing school as part of referendum project. A window replacement project is also planned as a second referendum question. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $13,289,398.42 | $8,241,977.00 | $3,296,791.00 | $9,992,607.42 |
0785-030-05-0ANY | Chathams, Sch Dist Of The | Chatham M.S. | Field replacement at Haas Field. This is a separate referendum question. | School Facility Project | Rehab of Existing Facility | Executed | $871,270.65 | $421,000.00 | $168,400.00 | $702,870.65 |
0785-050-00-0053 | Chathams, Sch Dist Of The | Lafayette E.S. | 10,425 SF Addition, various/upgrades and replace roof | Retro | Rehab of Existing Facility | Completed | $2,728,658.00 | $1,568,113.00 | $627,245.20 | $2,101,412.80 |
0785-050-02-0745 | Chathams, Sch Dist Of The | Lafayette E.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Completed | $170,897.00 | $170,897.00 | $68,358.80 | $102,538.20 |
0785-050-05-0ANZ | Chathams, Sch Dist Of The | Lafayette E.S. | Proposed additions and alternations to existing school as part of referendum project. Window replacement of Lafayette school is proposed as a second referendum question. | School Facility Project | Rehab of Existing Facility | Executed | $5,357,000.00 | $2,985,122.00 | $1,194,049.00 | $4,162,951.00 |
0785-060-00-0152 | Chathams, Sch Dist Of The | Milton Avenue E.S. | 11,844 SF Additions and various upgrade/renovations | Retro | Addition and Rehab of Existing Facility | Completed | $2,850,595.00 | $1,792,713.00 | $717,085.20 | $2,133,509.80 |
0785-060-05-0AOA | Chathams, Sch Dist Of The | Milton Avenue E.S. | Proposed replacement of existing boiler. | School Facility Project | Rehab of Existing Facility | Completed | $220,497.16 | $220,497.16 | $88,198.86 | $132,298.30 |
0785-070-00-0052 | Chathams, Sch Dist Of The | Washington Avenue E.S. | 10,425 SF Addition and various upgrades/renovations | Retro | Addition and Rehab of Existing Facility | Completed | $255,038.00 | $122,357.00 | $48,942.80 | $206,095.20 |
0785-070-05-0AOB | Chathams, Sch Dist Of The | Washington Avenue E.S. | Proposed additions and alterartions | School Facility Project | Rehab of Existing Facility | Executed | $5,474,965.00 | $2,950,972.00 | $1,180,389.00 | $4,262,611.00 |
0785-080-00-0051 | Chathams, Sch Dist Of The | Southern Boulvard E.S. | 11,844 SF Addition and various upgrades/renovations | Retro | Addition and Rehab of Existing Facility | Completed | $3,228,201.00 | $1,664,783.00 | $665,913.20 | $2,562,287.80 |
0785-x01-05-0AOC | Chathams, Sch Dist Of The | Chatham HS Cougar Field | Replacement of existing grass athletic field with artificial turf and drainage and resurfacing of existing track. | School Facility Project | Rehab of Existing Facility | Executed | $1,276,409.14 | $608,000.00 | $243,200.00 | $1,033,209.14 |
0800-030-02-1045 | Cherry Hill Township | Cherry Hill High-East H.S. | ADA toilet rooms renovations, library roof replacment and various canopy replacements, auditorium HVAC replacement, ADA rescue areas, ADA exterior door replacements, science room electrical upgrade, gym lighting replacement. | School Facility Project | Rehab of Existing Facility | Executed | $1,295,472.00 | $1,139,580.00 | $455,828.00 | $839,644.00 |
0800-030-03-0501 | Cherry Hill Township | Cherry Hill High-East H.S. | SFP = Telecommunications Replacement | School Facility Project | Rehab of Existing Facility | Completed | $114,558.00 | $114,558.00 | $45,823.00 | $68,735.00 |
0800-030-03-1294 | Cherry Hill Township | Cherry Hill High-East H.S. | Emergent Roof Project- Remove and dispose of old roof. Install instalation, roof drains, roof ladder, coping system and roofing system. | School Facility Project | Rehab of Existing Facility | Completed | $423,875.00 | $423,875.00 | $169,550.00 | $254,325.00 |
0800-030-04-00SO | Cherry Hill Township | Cherry Hill High-East H.S. | Alteration of existing toilet rooms for improved health and safety and accessibility. | School Facility Project | Rehab of Existing Facility | Completed | $725,956.00 | $725,956.00 | $290,382.00 | $435,574.00 |
0800-030-05-0APH | Cherry Hill Township | Cherry Hill High-East H.S. | HVAC,Sanitary Lift, Floor Finishes, auditorium renovations | School Facility Project | Rehab of Existing Facility | Executed | $8,642,263.00 | $8,642,263.00 | $3,456,905.00 | $5,185,358.00 |
0800-030-05-0API | Cherry Hill Township | Cherry Hill High-East H.S. | Water coolers, toilet rooms, sanitary lift. | School Facility Project | Rehab of Existing Facility | Completed | $809,194.00 | $809,194.00 | $323,678.00 | $485,516.00 |
0800-040-02-0736 | Cherry Hill Township | Cherry Hill High-West H.S. | Installaton of 12 security cameras inside and outside of building and peripheral equiptment | School Facility Project | Rehab of Existing Facility | Completed | $49,755.20 | $44,530.56 | $17,812.00 | $31,943.20 |
0800-040-02-1044 | Cherry Hill Township | Cherry Hill High-West H.S. | Telecommunications Replacement, ADA Exterior Door Replacements, ADA toilet room renovations, ADA accessible route improvements, ADA Area of Rescue, Exterior Stair Reconstruction, Storm Drainage Extension, ADA Accessible Entrance, etc. | School Facility Project | Rehab of Existing Facility | Executed | $874,643.37 | $874,643.37 | $349,857.35 | $524,786.02 |
0800-040-05-0APJ | Cherry Hill Township | Cherry Hill High-West H.S. | Fire Alarms, clock system. HVAC, gym lighting | School Facility Project | Rehab of Existing Facility | Completed | $4,466,543.00 | $4,466,543.00 | $1,786,617.00 | $2,679,926.00 |
0800-040-05-0APK | Cherry Hill Township | Cherry Hill High-West H.S. | Sanitary lift, toilet rooms | School Facility Project | Rehab of Existing Facility | Executed | $1,731,623.00 | $1,731,623.00 | $692,649.00 | $1,038,974.00 |
0800-058-05-0AME | Cherry Hill Township | A. Russell Knight E.S. | Renovations to existing building | School Facility Project | Addition and Rehab of Existing Facility | Executed | $535,053.00 | $535,053.00 | $214,021.20 | $321,031.80 |
0800-058-05-0APL | Cherry Hill Township | A. Russell Knight E.S. | Toilet room renovations | School Facility Project | Rehab of Existing Facility | Completed | $209,945.00 | $192,195.00 | $76,878.00 | $133,067.00 |
0800-060-05-0AOD | Cherry Hill Township | Alternative High School | Roof, doors and window replacement | School Facility Project | Rehab of Existing Facility | Executed | $1,314,337.00 | $1,314,337.00 | $525,735.00 | $788,602.00 |
0800-062-02-1061 | Cherry Hill Township | Barclay School | Installlation of new instrusion alarm, DHW Heater replacment, ADA Ext Door & ADA Int. door replacements. | School Facility Project | Rehab of Existing Facility | Executed | $94,564.00 | $75,197.00 | $30,079.00 | $64,485.00 |
0800-062-05-0AOE | Cherry Hill Township | Barclay School | Replacement/Upgrade to telephone coomunication system. | School Facility Project | Rehab of Existing Facility | Completed | $28,568.91 | $28,568.91 | $11,427.56 | $17,141.35 |
0800-067-02-1068 | Cherry Hill Township | John A. Carusi M.S. | Telecommunications replacement, AHERA abatement, ADA stripes and signage and ADA door replacement. | School Facility Project | Rehab of Existing Facility | Completed | $124,001.02 | $124,001.02 | $49,600.41 | $74,400.41 |
0800-067-05-0AMF | Cherry Hill Township | John A. Carusi M.S. | Windows and doors | School Facility Project | Rehab of Existing Facility | Executed | $172,416.66 | $172,416.66 | $68,966.66 | $103,450.00 |
0800-067-05-0AOF | Cherry Hill Township | John A. Carusi M.S. | Renovate toilet facilities | School Facility Project | Rehab of Existing Facility | Completed | $541,645.90 | $541,645.90 | $216,658.36 | $324,987.54 |
0800-068-02-1075 | Cherry Hill Township | Bret Harte E.S. | Connectivity, ADA stripes and signage and AHERA compliance issues. | School Facility Project | Rehab of Existing Facility | Completed | $7,877.31 | $7,877.31 | $3,150.92 | $4,726.39 |
0800-068-05-0AMG | Cherry Hill Township | Bret Harte E.S. | Renovations to existing building. | School Facility Project | Rehab of Existing Facility | Completed | $35,279.26 | $35,279.26 | $14,111.70 | $21,167.56 |
0800-069-02-0725 | Cherry Hill Township | Clara Barton E.S. | conversions of classrooms | School Facility Project | Rehab of Existing Facility | Completed | $85,109.49 | $50,962.00 | $20,385.00 | $64,724.49 |
0800-069-02-1060 | Cherry Hill Township | Clara Barton E.S. | New ADA door replacement and installation of fiber optics for computers (connectivity) | School Facility Project | Rehab of Existing Facility | Completed | $41,046.98 | $41,046.98 | $16,418.79 | $24,628.19 |
0800-069-05-0AOG | Cherry Hill Township | Clara Barton E.S. | Renovate toilet facilities, upgrades to telecom system | School Facility Project | Rehab of Existing Facility | Completed | $283,100.00 | $283,100.00 | $113,240.00 | $169,860.00 |
0800-073-02-0357 | Cherry Hill Township | Henry C. Beck M.S. | rehab of 2 toilet rooms | School Facility Project | Rehab of Existing Facility | Completed | $141,102.00 | $141,102.00 | $56,441.00 | $84,661.00 |
0800-073-02-0722 | Cherry Hill Township | Henry C. Beck M.S. | Conversions of classrooms | School Facility Project | Rehab of Existing Facility | Completed | $81,087.74 | $47,305.25 | $18,922.00 | $62,165.74 |
0800-073-02-1064 | Cherry Hill Township | Henry C. Beck M.S. | Installation of Telecommunications, gym lighting, ADA toilets and ADA doors | School Facility Project | Rehab of Existing Facility | Completed | $161,196.00 | $161,196.00 | $64,478.00 | $96,718.00 |
0800-073-05-0AOH | Cherry Hill Township | Henry C. Beck M.S. | Replace exterior doors and windows | School Facility Project | Rehab of Existing Facility | Executed | $286,194.00 | $286,194.00 | $114,478.00 | $171,716.00 |
0800-074-02-1076 | Cherry Hill Township | Rosa International M.S. | ADA Area of Rescue Only | School Facility Project | Rehab of Existing Facility | Completed | $2,920.32 | $2,920.32 | $1,168.13 | $1,752.19 |
0800-074-05-0ARC | Cherry Hill Township | Rosa International M.S. | Roof Replacement and gym lighting | School Facility Project | Rehab of Existing Facility | Executed | $514,667.00 | $514,667.00 | $205,867.00 | $308,800.00 |
0800-075-05-0AQA | Cherry Hill Township | Horace Mann E.S. | Renovate toilet facilities and telecommunication system upgrade | School Facility Project | Rehab of Existing Facility | Completed | $288,784.00 | $288,784.00 | $115,513.60 | $173,270.40 |
0800-083-05-0AQX | Cherry Hill Township | James F. Cooper E.S. | Renovations to existing building. | School Facility Project | Rehab of Existing Facility | Completed | $1,186,279.00 | $1,186,279.00 | $474,511.60 | $711,767.40 |
0800-083-05-0AQY | Cherry Hill Township | James F. Cooper E.S. | Renovations to existing building. | School Facility Project | Rehab of Existing Facility | Executed | $245,658.00 | $245,658.00 | $98,263.00 | $147,395.00 |
0800-085-05-0AMH | Cherry Hill Township | James Johnson E.S. | Replace doors, telecom system, roof | School Facility Project | Rehab of Existing Facility | Executed | $959,400.21 | $959,400.21 | $383,760.08 | $575,640.13 |
0800-085-05-0AMI | Cherry Hill Township | James Johnson E.S. | Renovate toilet facilities | School Facility Project | Rehab of Existing Facility | Completed | $202,199.59 | $202,199.59 | $80,879.84 | $121,309.75 |
0800-100-02-0360 | Cherry Hill Township | Joseph D. Sharp E.S. | Rehab of a storage room into a toilet room | School Facility Project | Rehab of Existing Facility | Completed | $39,968.00 | $39,968.00 | $15,987.00 | $23,981.00 |
0800-100-03-1295 | Cherry Hill Township | Joseph D. Sharp E.S. | Emergent Roof Project - Remove and dispose of old roof. Provide and install layers of insulation | School Facility Project | Rehab of Existing Facility | Completed | $232,077.35 | $232,077.35 | $92,830.94 | $139,246.41 |
0800-100-05-0AOI | Cherry Hill Township | Joseph D. Sharp E.S. | Replace existing roof, upgrade to telephone intercom system. | School Facility Project | Rehab of Existing Facility | Completed | $439,407.00 | $439,407.00 | $175,763.00 | $263,644.00 |
0800-100-05-0AQZ | Cherry Hill Township | Joseph D. Sharp E.S. | Renovate toilet facilities | School Facility Project | Rehab of Existing Facility | Executed | $216,823.00 | $216,823.00 | $86,729.00 | $130,094.00 |
0800-105-02-1079 | Cherry Hill Township | Joyce Kilmer E.S. | rehabilitation of connectivity | School Facility Project | Rehab of Existing Facility | Completed | $7,644.70 | $7,644.70 | $3,057.88 | $4,586.82 |
0800-105-05-0AOJ | Cherry Hill Township | Joyce Kilmer E.S. | Upgrade to telephone intercom systems, renovate toilets, rooms, and classroom finishes. | School Facility Project | Rehab of Existing Facility | Completed | $352,943.00 | $352,943.00 | $141,177.00 | $211,766.00 |
0800-110-02-1080 | Cherry Hill Township | Kingston E.S. | rehabilitation of connectivity | School Facility Project | Rehab of Existing Facility | Completed | $7,691.12 | $7,691.12 | $3,076.45 | $4,614.67 |
0800-110-05-0AMJ | Cherry Hill Township | Kingston E.S. | Renovations to existing building | School Facility Project | Rehab of Existing Facility | Completed | $251,627.00 | $251,627.00 | $100,651.00 | $150,976.00 |
0800-113-02-1081 | Cherry Hill Township | Richard Stockton E.S. | New ADA door replacemetns and installation of Fiber Optics for computers | School Facility Project | Rehab of Existing Facility | Completed | $29,323.28 | $29,323.28 | $11,729.31 | $17,593.97 |
0800-113-05-0AMK | Cherry Hill Township | Richard Stockton E.S. | Roof and telecom system | School Facility Project | Rehab of Existing Facility | Executed | $635,159.00 | $635,159.00 | $254,064.00 | $381,095.00 |
0800-113-05-0AOK | Cherry Hill Township | Richard Stockton E.S. | Renovate toilet facilities, upgrades to telecom system, floor finishes. | School Facility Project | Rehab of Existing Facility | Completed | $247,553.00 | $210,386.00 | $84,154.00 | $163,399.00 |
0800-115-02-1082 | Cherry Hill Township | Thomas Paine E.S. | Connectvity, ADA, stripes and signage and AHERA compliance issues | School Facility Project | Rehab of Existing Facility | Completed | $7,668.25 | $7,668.25 | $3,067.30 | $4,600.95 |
0800-115-05-0AOL | Cherry Hill Township | Thomas Paine E.S. | Upgrade to telephone and intercom systems | School Facility Project | Rehab of Existing Facility | Completed | $31,528.00 | $31,528.00 | $12,611.00 | $18,917.00 |
0800-130-05-0AOM | Cherry Hill Township | Woodcrest E.S. | Renovate toilet facilities, upgrades to telecom system, floor finishes | School Facility Project | Rehab of Existing Facility | Executed | $285,933.00 | $285,933.00 | $114,373.00 | $171,560.00 |
0810-050-04-0AIK | Chesilhurst Borough | Shirley B. Foster E.S. | Replace telecommunications at Shirley B. Foster E.S. | School Facility Project | Rehab of Existing Facility | Completed | $31,864.00 | $31,864.00 | $25,665.62 | $6,198.38 |
0820-020-03-0703 | Chester Township | Black River M.S. | Replacement of Roof at Black River School | School Facility Project | Rehab of Existing Facility | Completed | $282,955.31 | $282,955.31 | $113,182.12 | $169,773.19 |
0820-020-04-0ACH | Chester Township | Black River M.S. | Renovation of entire school and 5200GSF addition | School Facility Project | Rehab of Existing Facility | Executed | $3,633,962.70 | $3,329,979.00 | $1,331,992.00 | $3,758,008.00 |
0820-020-05-0AZL | Chester Township | Black River M.S. | Repair heating, electrical, etc. | School Facility Project | Rehab of Existing Facility | Completed | $1,779,575.45 | $1,779,575.45 | $711,830.18 | $1,067,745.27 |
0820-020-09-0TAJ | Chester Township | Black River M.S. | Appro.4 sets of exterior aluminum and steel doors/frames will be replaced with aluminum FRP doors, and exisiting smoke doors will be replaced for updated door leafs with new hardware and gaskets. | School Facility Project | Rehab of Existing Facility | Offered | $86,000.00 | $86,000.00 | $34,400.00 | $51,600.00 |
0820-030-03-0702 | Chester Township | Bragg E.S. | Project will be phased in two parts. Phase 1 includes the reroofing the cafeteria at Bragg School. Replacement of roof as an emergent project in Phase 1. Phase II includes the reroofing of the rest of the school. | School Facility Project | Rehab of Existing Facility | Completed | $20,694.70 | $20,694.70 | $8,277.88 | $12,416.82 |
0820-030-03-0808 | Chester Township | Bragg E.S. | Phase II of SP #2030702. Re-roofing of the rest of the school. | School Facility Project | Rehab of Existing Facility | Completed | $156,446.18 | $156,446.18 | $62,578.47 | $93,867.71 |
0820-030-04-0ABA | Chester Township | Bragg E.S. | Renovation of entire existing school and 10,000 GSF Addition | School Facility Project | Rehab of Existing Facility | Completed | $6,248,733.36 | $4,162,217.00 | $1,664,887.00 | $5,345,113.00 |
0820-030-05-0AZM | Chester Township | Bragg E.S. | Repair heating, electrical, etc | School Facility Project | Rehab of Existing Facility | Completed | $1,401,109.08 | $1,401,109.08 | $560,443.63 | $840,665.45 |
0820-030-09-0TAK | Chester Township | Bragg E.S. | Existing wood doors/frames at exterior of school will be replaced with aluminum FRP doors, and existing wood fire doors will be replaced & updated doors leafs with new hareware. | School Facility Project | Rehab of Existing Facility | Offered | $38,000.00 | $38,000.00 | $15,200.00 | $22,800.00 |
0820-040-04-0ACI | Chester Township | Dickerson E.S. | Renovation of the entire existing school and addition | School Facility Project | Rehab of Existing Facility | Completed | $9,500,599.49 | $6,305,333.00 | $2,522,133.00 | $8,127,867.00 |
0820-040-05-0AZN | Chester Township | Dickerson E.S. | Repair heating, electrical, etc. | School Facility Project | Rehab of Existing Facility | Completed | $225,853.46 | $225,853.46 | $90,341.38 | $135,512.08 |
0820-040-09-0TAL | Chester Township | Dickerson E.S. | Approx. 3 sets of existng wood doors/frames at exterior of school will be replaced with aluminum FRP doors that are ADA accessible | School Facility Project | Rehab of Existing Facility | Offered | $46,100.00 | $46,100.00 | $18,440.00 | $27,660.00 |
0830-025-03-1213 | Chesterfield Township | Chesterfield E.S. | HVAC to upgrade speech room to code requirements | School Facility Project | Rehab of Existing Facility | Completed | $9,228.00 | $9,228.00 | $3,691.20 | $5,536.80 |
0840-030-05-0APM | Cinnaminson Township | Cinnaminson H.S. | The district is installing an interior Handicap lift in the lower section to achieve ADA compliance with associated ramps and needed cuts. | School Facility Project | Rehab of Existing Facility | Completed | $100,045.00 | $100,045.00 | $40,018.00 | $60,027.00 |
0850-035-04-1410 | Clark Township | Carl H. Kumpf M.S. | Immediate partial roof replacement at section with current severe leaks. This is a part of the LFRP Roof Replacement. | School Facility Project | Rehab of Existing Facility | Completed | $90,165.00 | $90,165.00 | $36,066.00 | $54,099.00 |
0860-030-01-0390 | Clayton | Clayton H.S. | Addition of Gym and team rooms; rehab of trainers room | School Facility Project | Addition and Rehab of Existing Facility | Completed | $1,286,324.00 | $1,286,324.00 | $792,224.00 | $494,100.00 |
0860-030-03-1068 | Clayton | Clayton H.S. | Repair of gym floor, Bleachers and folding partition | School Facility Project | Rehab of Existing Facility | Completed | $189,750.00 | $189,750.00 | $111,154.00 | $78,596.00 |
0860-030-05-0APV | Clayton | Clayton H.S. | State Aid request-Replacing existing telephone system- No final approval is necessary. Emergent Project Possible Future insurance settlement | School Facility Project | Rehab of Existing Facility | Completed | $68,676.00 | $68,676.00 | $38,321.00 | $30,355.00 |
0860-030-09-0OAB | Clayton | Clayton H.S. | Connect exisiting rain water leaders and provide curbing and drainage for parking lot ro be reconstructed; parking lot upgrades. | School Facility Project | Rehab of Existing Facility | Offered | $600,000.00 | $600,000.00 | $385,975.00 | $214,025.00 |
0860-030-09-0OAC | Clayton | Clayton H.S. | Grade realignment to add 6th graders to middle/high school. Renovations approximately 16,000 SF to the middle school and 14,000 SF to high school. Addition of 30, 343 SF to include 7 classrooms, 2 science and prep rooms, new IMC, etc. | School Facility Project | Rehab of Existing Facility | Offered | $14,447,813.00 | $9,969,535.00 | $6,413,318.00 | $8,034,495.00 |
0860-040-00-0367 | Clayton | Herma S. Simmons E.S. | Addition of Kindergarten and General classrooms; conversion of exisiting Kindergarten classrooms into Pre-K. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $1,602,220.88 | $1,602,220.88 | $986,780.60 | $615,440.28 |
0860-040-05-0APW | Clayton | Herma S. Simmons E.S. | State Aid Request- replacing existing telephone system and bolier system- No final approval is necessary. Emergent Project for the boilers. Possible Future insurance settlement | School Facility Project | Rehab of Existing Facility | Executed | $467,871.00 | $467,871.00 | $261,073.00 | $206,798.00 |
0860-040-09-0OAD | Clayton | Herma S. Simmons E.S. | New roof and roof top HVAC units. Repair Dryvit system at gym and auditorium walls. Replace exisiting chiller and electrical system. Revonate exisiting parking lot and play areas to correct existing storm water problems. Etc | School Facility Project | Rehab of Existing Facility | Offered | $4,959,325.00 | $4,959,325.00 | $3,190,292.00 | $1,769,033.00 |
0870-020-02-0465 | Clearview Regional | Clearview Regional H.S. | Addition of Auditorium, wrestling room, locker rooms, Child development rooms, auxiliary cafeteria, classrooms, etc. Renovation of clasrooms, conversion of classrooms for change of use, remove asbestos tile, etc. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $23,881,043.00 | $15,126,363.00 | $9,281,254.00 | $14,599,789.00 |
0870-020-09-0OAE | Clearview Regional | Clearview Regional H.S. | RE-roofing of approx. 21,300 sf. | School Facility Project | Rehab of Existing Facility | Executed | $522,602.00 | $522,602.00 | $262,805.00 | $259,797.00 |
0870-030-02-0464 | Clearview Regional | Clearview Regional M.S. | Addition of new classrooms, computer room, art room, music rooms, etc. Rehab including the renovation of classrooms, replacement of enterior doors for ADA compliance, relocation of emergency generator, etc. | School Facility Project | Addition and Rehab of Existing Facility | Completed | $14,019,421.76 | $9,256,032.00 | $5,679,329.00 | $8,340,092.76 |
0870-030-09-0OAF | Clearview Regional | Clearview Regional M.S. | Re-roofing and related work | School Facility Project | Rehab of Existing Facility | Executed | $1,211,561.00 | $1,211,561.00 | $616,944.00 | $594,617.00 |
0880-010-04-00HW | Clementon Borough | Clementon E.S. | Fire Alarm replacement. | School Facility Project | Rehab of Existing Facility | Completed | $275,604.35 | $275,604.35 | $160,638.48 | $114,965.87 |
0880-010-04-0AHH | Clementon Borough | Clementon E.S. | Complete projects in the LRFP and the locker room addition | School Facility Project | Addition To Existing Facility | Executed | $4,114,933.31 | $3,935,091.31 | $2,293,603.39 | $1,821,329.92 |
0890-030-05-0AFO | Cliffside Park | Cliffside Park H.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $779,192.29 | $779,192.29 | $311,676.92 | $467,515.37 |
0890-030-09-0JAX | Cliffside Park | Cliffside Park H.S. | Boiler replacement | School Facility Project | Rehab of Existing Facility | Offered | $680,120.00 | $680,120.00 | $272,048.00 | $408,072.00 |
0890-070-05-0AEJ | Cliffside Park | Number 5 E.S. | Roof replacement. | School Facility Project | Rehab of Existing Facility | Completed | $117,954.93 | $117,954.93 | $47,181.97 | $70,772.96 |
0890-080-05-0AFP | Cliffside Park | Number 6 E.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $377,250.00 | $377,250.00 | $150,900.00 | $226,350.00 |
0900-030-03-0415 | Clifton | Clifton H.S. | To replace existing roofing system with new EPDM system. | School Facility Project | Rehab of Existing Facility | Completed | $381,000.00 | $381,000.00 | $152,400.00 | $228,600.00 |
0900-030-04-0AUV | Clifton | Clifton H.S. | Renovate existing metal shop into technology lab and computer lab. | School Facility Project | Rehab of Existing Facility | Completed | $277,272.00 | $277,272.00 | $110,908.80 | $166,363.20 |
0900-030-05-0AEK | Clifton | Clifton H.S. | Acquisition of existing industrial building and renovation into the Clifton HS Annex. | School Facility Project | Rehab of Existing Facility | Executed | $15,153,548.00 | $10,010,000.00 | $4,004,000.00 | $11,149,548.00 |
0900-035-03-0416 | Clifton | Christopher Columbus M.S. | To replace interior doors throughout school. | School Facility Project | Rehab of Existing Facility | Completed | $106,000.00 | $106,000.00 | $42,400.00 | $63,600.00 |
0900-035-03-0926 | Clifton | Christopher Columbus M.S. | Reroofing the entire roofs; and rebuild/repair Parapet Walls; Replacing Steel Lintels selectively; Brick repointing, etc. | School Facility Project | Rehab of Existing Facility | Completed | $855,837.91 | $855,837.91 | $342,335.16 | $513,502.75 |
0900-100-04-0ARZ | Clifton | Number 3 E.S. | Repair small roof and brick wall including steel window lintel at kindergarten. | School Facility Project | Rehab of Existing Facility | Completed | $40,000.00 | $40,000.00 | $16,000.00 | $24,000.00 |
0900-140-04-0ASA | Clifton | Number 8 E.S. | Repair leaking roof and parapet wall at original building section. | School Facility Project | Rehab of Existing Facility | Completed | $249,977.78 | $249,977.78 | $99,991.11 | $149,986.67 |
0900-150-03-0417 | Clifton | Number 9 E.S. | To replace existing windows with new aluminum windows. | School Facility Project | Rehab of Existing Facility | Completed | $288,526.67 | $288,526.67 | $115,410.67 | $173,116.00 |
0900-N02-02-0214 | Clifton | New Elementary School | New Elementary School | School Facility Project | New Construction | Executed | $20,670,000.00 | $12,282,000.00 | $4,912,800.00 | $15,757,200.00 |
0910-030-05-0AOQ | Clinton Town | Clinton E.S. | replacement of six classroom unit ventilators and exhaust fans affecting + or - 4,800 SF. | School Facility Project | Rehab of Existing Facility | Completed | $137,550.00 | $137,550.00 | $55,020.00 | $27,510.00 |
0910-030-09-0OAW | Clinton Town | Clinton E.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Offered | $161,440.00 | $161,440.00 | $64,576.00 | $96,864.00 |
0910-030-99-0488 | Clinton Town | Clinton E.S. | | Retro | Addition and Rehab of Existing Facility | Completed | $3,948,513.55 | $3,948,513.55 | $1,579,405.42 | $2,369,108.13 |
0920-030-03-0130 | Clinton Township | Spruce Run E.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $148,404.81 | $148,404.81 | $59,361.92 | $89,042.89 |
0920-030-03-1109 | Clinton Township | Spruce Run E.S. | Renovations of interior space to create K and PreK Hdcp rooms with dedicated toilets, divisions of classrooms into small group and other support spaces, physical plant improvements. | School Facility Project | Rehab of Existing Facility | Completed | $1,537,832.00 | $1,537,832.00 | $615,133.00 | $922,699.00 |
0920-035-03-0131 | Clinton Township | Patrick McGaheran | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $474,530.34 | $474,530.34 | $189,812.14 | $284,718.20 |
0920-035-03-1110 | Clinton Township | Patrick McGaheran | Renovations of interior space to create K and PreK Hdcp rooms with dedicated toilets, alteration of existing toilet rooms. | School Facility Project | Rehab of Existing Facility | Executed | $796,630.00 | $796,630.00 | $318,772.00 | $477,858.00 |
0920-040-03-0132 | Clinton Township | Round Valley M.S. | Partial Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $430,763.60 | $430,763.60 | $172,305.44 | $258,458.16 |
0920-040-03-1111 | Clinton Township | Round Valley M.S. | Renovations and alterations of interior space to support the re-alignment of the school to grades 4-6, improvement of entry security, reconfiguration of office areas. | School Facility Project | Rehab of Existing Facility | Executed | $2,432,169.60 | $2,432,169.60 | $972,868.00 | $1,459,301.60 |
0920-n01-03-1112 | Clinton Township | New 7-8 Middle School | Construction of a new 7-8 middle school | School Facility Project | New Construction | Executed | $34,755,250.00 | $13,390,234.00 | $5,356,094.00 | $29,399,156.00 |
0930-050-03-1083 | Closter | Hillside E.S. | Additions and Renovations | School Facility Project | Addition and Rehab of Existing Facility | Executed | $3,617,402.30 | $2,020,200.00 | $808,080.00 | $2,816,170.00 |
0930-050-04-00QF | Closter | Hillside E.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $336,735.99 | $336,735.99 | $134,694.40 | $202,041.59 |
0930-060-03-0770 | Closter | Tenakill M.S. | Auditorium Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $67,521.16 | $67,521.16 | $27,008.46 | $40,512.70 |
0930-060-03-1101 | Closter | Tenakill M.S. | Additions and Renovations. | School Facility Project | Addition and Rehab of Existing Facility | Executed | $2,348,406.97 | $1,538,700.00 | $615,480.00 | $1,784,520.00 |
0940-030-02-0795 | Collingswood Borough | Collingswood Senior H.S. | Replacement of Corridor Lockers | School Facility Project | Rehab of Existing Facility | Completed | $52,037.68 | $52,037.68 | $22,900.33 | $29,137.35 |
0940-030-03-0743 | Collingswood Borough | Collingswood Senior H.S. | Locker Replacement Only | School Facility Project | Rehab of Existing Facility | Completed | $48,479.20 | $48,479.20 | $19,607.80 | $28,871.40 |
0940-030-04-00EV | Collingswood Borough | Collingswood Senior H.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Completed | $227,480.00 | $227,480.00 | $92,006.11 | $135,473.89 |
0940-030-05-0ALD | Collingswood Borough | Collingswood Senior H.S. | Additions and Rehabilitations | School Facility Project | Addition and Rehab of Existing Facility | Executed | $19,944,918.89 | $19,944,918.89 | $8,066,891.14 | $11,878,027.75 |
0940-030-05-0ARA | Collingswood Borough | Collingswood Senior H.S. | Renovations | School Facility Project | Rehab of Existing Facility | Completed | $145,000.00 | $145,000.00 | $58,646.00 | $86,354.00 |
0940-040-02-0511 | Collingswood Borough | Collingswood M.S. | Replacement of lockers VCT flooring repl in halls, stair landing reconfig HVAC upgrade in cafetorium and auditorium | School Facility Project | Rehab of Existing Facility | Completed | $574,760.00 | $522,790.00 | $230,065.00 | $344,695.00 |
0940-040-03-0744 | Collingswood Borough | Collingswood M.S. | Boiler and Roof Replacement | School Facility Project | Rehab of Existing Facility | Executed | $509,280.00 | $509,280.00 | $205,983.00 | $303,297.00 |
0940-040-04-00EZ | Collingswood Borough | Collingswood M.S. | Bathroom Renovations | School Facility Project | Rehab of Existing Facility | Completed | $60,840.00 | $60,840.00 | $24,607.00 | $36,233.00 |
0940-040-05-0ALE | Collingswood Borough | Collingswood M.S. | Additions and Rehabilitations | School Facility Project | Addition and Rehab of Existing Facility | Executed | $5,698,131.32 | $5,698,131.32 | $2,304,657.41 | $3,393,473.91 |
0940-040-05-0ARD | Collingswood Borough | Collingswood M.S. | Renovations | School Facility Project | Rehab of Existing Facility | Completed | $264,500.00 | $264,500.00 | $106,979.00 | $157,521.00 |
0940-050-04-00EY | Collingswood Borough | James A. Garfield E.S. | Bathroom Renovations | School Facility Project | Rehab of Existing Facility | Completed | $46,800.00 | $46,800.00 | $18,929.00 | $27,871.00 |
0940-050-05-0ALF | Collingswood Borough | James A. Garfield E.S. | Renovations to existing bldg. | School Facility Project | Rehab of Existing Facility | Executed | $975,811.53 | $975,811.53 | $394,674.78 | $581,136.75 |
0940-060-03-0745 | Collingswood Borough | Mark Newbie E.S. | Window Replacement | School Facility Project | Rehab of Existing Facility | Completed | $149,572.50 | $149,572.50 | $60,495.79 | $89,076.71 |
0940-060-04-00EW | Collingswood Borough | Mark Newbie E.S. | Bathroom Renovations | School Facility Project | Rehab of Existing Facility | Completed | $53,820.00 | $53,820.00 | $21,768.00 | $32,052.00 |
0940-060-05-0ALG | Collingswood Borough | Mark Newbie E.S. | Renovations to existing building | School Facility Project | Rehab of Existing Facility | Executed | $1,466,316.18 | $1,466,316.18 | $593,063.31 | $873,252.87 |
0940-060-05-0DAJ | Collingswood Borough | Mark Newbie E.S. | Renovation of 3536 sf to enable the Relocation of the school's main office from the basement level to the first floor next to the building entrance. | School Facility Project | Rehab of Existing Facility | Executed | $249,300.00 | $249,300.00 | $100,831.00 | $148,469.00 |
0940-070-05-0ALH | Collingswood Borough | Thomas Sharp E.S. | Renovations to existing building | School Facility Project | Rehab of Existing Facility | Executed | $1,458,844.03 | $1,458,844.03 | $590,041.14 | $868,802.89 |
0940-070-05-0ARF | Collingswood Borough | Thomas Sharp E.S. | Renovations | School Facility Project | Not Applicable | Completed | $231,150.00 | $231,150.00 | $93,491.00 | $137,659.00 |
0940-070-09-0MAJ | Collingswood Borough | Thomas Sharp E.S. | Roof replacement | School Facility Project | Rehab of Existing Facility | Executed | $312,500.00 | $312,500.00 | $125,000.00 | $187,500.00 |
0940-080-03-0746 | Collingswood Borough | William P. Tatem E.S. | Window Replacement | School Facility Project | Rehab of Existing Facility | Completed | $199,485.00 | $199,485.00 | $80,683.30 | $118,801.70 |
0940-080-05-0ALI | Collingswood Borough | William P. Tatem E.S. | Renovations to existing building | School Facility Project | Rehab of Existing Facility | Executed | $1,233,950.00 | $1,233,950.00 | $499,080.95 | $734,869.05 |
0940-090-04-00EX | Collingswood Borough | Zane North E.S. | Roof Replacement | School Facility Project | Rehab of Existing Facility | Completed | $182,820.00 | $182,820.00 | $73,943.01 | $108,876.99 |
0940-090-05-0ALJ | Collingswood Borough | Zane North E.S. | Renovations to existing building | School Facility Project | Rehab of Existing Facility | Executed | $1,212,377.27 | $1,212,377.27 | $490,355.69 | $722,021.58 |
0940-090-05-0ARE | Collingswood Borough | Zane North E.S. | Renovations | School Facility Project | Rehab of Existing Facility | Completed | $70,200.00 | $70,200.00 | $28,393.00 | $41,807.00 |
0945-030-04-000R | Colts Neck Township | Cedar Drive E.S. | Partial roofing replacement | School Facility Project | Rehab of Existing Facility | Completed | $369,633.39 | $369,633.39 | $147,853.36 | $221,780.03 |
0945-N01-00-0240 | Colts Neck Township | New Elementary School | Building new ES | School Facility Project | New Construction | Executed | $17,734,120.00 | $11,212,500.00 | $4,485,000.00 | $13,249,120.00 |
0950-025-03-1123 | Commercial Township | Haleyville-Mauricetown E.S. | New digital telecommunications system including telephones with hands free intercom capabilities and public address paging system | School Facility Project | Rehab of Existing Facility | Completed | $32,814.00 | $32,814.00 | $26,092.22 | $6,721.78 |
0950-025-03-1444 | Commercial Township | Haleyville-Mauricetown E.S. | Roof replacement. | School Facility Project | Rehab of Existing Facility | Executed | $125,915.00 | $125,915.00 | $100,121.94 | $25,793.06 |
0950-025-04-00RX | Commercial Township | Haleyville-Mauricetown E.S. | Schematic submission for a security system. | School Facility Project | Rehab of Existing Facility | Completed | $16,673.00 | $16,673.00 | $13,257.62 | $3,415.38 |
0950-025-09-0MAQ | Commercial Township | Haleyville-Mauricetown E.S. | Four PK classrooms and SGI room addition for full-day Pre-K program. | School Facility Project | Rehab of Existing Facility | Offered | $1,359,972.00 | $800,800.00 | $626,689.00 | $174,111.00 |
0950-050-03-1124 | Commercial Township | Port Norris E.S. | New digital telecommunications system including telephones with hands free intercom capabilities and public address paging system | School Facility Project | Rehab of Existing Facility | Completed | $25,921.00 | $25,921.00 | $20,611.21 | $5,309.79 |
0950-050-03-1445 | Commercial Township | Port Norris E.S. | Pre-Development Request for A/E selection for schematic submission for a roof replacement. | School Facility Project | Rehab of Existing Facility | Executed | $60,785.00 | $60,785.00 | $48,333.50 | $12,451.50 |
0950-050-04-00RY | Commercial Township | Port Norris E.S. | Schematic submission for a security system. | School Facility Project | Rehab of Existing Facility | Completed | $12,385.00 | $12,385.00 | $9,847.99 | $2,537.01 |
0970-030-02-0275 | Cranbury Township | Cranbury E.S. | Addition and renovation to existing elementary school | School Facility Project | Addition and Rehab of Existing Facility | Completed | $7,307,544.00 | $3,396,420.00 | $1,358,568.00 | $5,948,976.00 |
0970-030-03-0889 | Cranbury Township | Cranbury E.S. | Exterior site improvements including lighting and sidewalk repair | School Facility Project | Rehab of Existing Facility | Completed | $44,477.47 | $44,477.47 | $17,790.99 | $26,686.48 |
#Rows On Page: 501 | $1,119,685,368.88 | $856,672,731.57 | $366,204,259.82 | $755,911,173.62 |
#Rows On Report: 2990 | $7,435,067,267.41 | $5,575,427,198.94 | $2,347,778,126.06 | $5,090,907,372.43 |
Report Was Generated on 7/3/2009 9:33:54 PM Version .Net 7.1.200001 |