0100-010-00-0504 | Asbury Park | Asbury Park H.S. | Repairs include window replacements, door hardware upgrades, main wing roof replacement, repairs to masonry façade, and fire alarm system upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
0100-020-00-0505 | Asbury Park | Bangs Avenue E.S. | Rehab of the facility-skylight repairs, repair & repainting of stucco façade. Replace lintel, roof at various wings, new exterior unit ventilator grills, sprinklers in boiler room, upgrades to fire alarm sys. | Health & Safety | Rehab of Existing Facility | Completed |
0100-040-00-0391 | Asbury Park | Bradley Primary | Addition of classrooms, gym, art and music rooms; various classroom conversions. | School Facility Project | Addition and Rehab of Existing Facility | Completed |
0100-040-00-0433 | Asbury Park | Bradley Primary | New heating and air conditioning system and a new sprinkler system. | Health & Safety | Rehab of Existing Facility | Completed |
0100-070-00-0482 | Asbury Park | Asbury Middle School | Replacement of Window, Door hardware, Repair of steps, skylights, structural cracking, spalling and deteriorating walls on building exterior, fire alarm system upgrade, sprinkler heads replacement, unit ventilator grills replacement | Health & Safety | Rehab of Existing Facility | Completed |
0100-070-01-0633 | Asbury Park | Asbury Middle School | New Addition - 29,875 s.f. includes 45 classrms, 6 SGIs, new cafetorium, music/vocal rm, community rm & media ctr. Renov & upgrades to existing 87,480 s.f. bldg containing 760 students. | School Facility Project | Addition and Rehab of Existing Facility | Construction Bid |
0100-100-01-0631 | Asbury Park | T. Marshall Primary | Addition - 13,278 s.f., 3-story with 50 classrms for 814 students with new gym/office & locker rooms, stage area, music rm, resource center, conference rms, new kitchen/cafeteria and Renovations to the existing 75,000-s.f. bldg. | School Facility Project | Addition and Rehab of Existing Facility | Completed |
0540-020-00-0430 | Bridgeton | Bridgeton Senior H.S. | replacement of the curtain wall and doors | Health & Safety | Rehab of Existing Facility | Completed |
0540-020-02-0236 | Bridgeton | Bridgeton Senior H.S. | Media center & elevator additions | School Facility Project | Addition and Rehab of Existing Facility | Construction |
0540-020-04-00ES | Bridgeton | Bridgeton Senior H.S. | HVAC and ceiling replacement. | School Facility Project | Rehab of Existing Facility | Completed |
0540-030-00-0681 | Bridgeton | Broad Street Elementary School | Remove/install roof, stone coping, new ladders, mechl/elect modifications, skylights removal. Replace curtainwall, masonry repairs, doors and windows. | Health & Safety | Rehab of Existing Facility | Completed |
0540-050-00-0575 | Bridgeton | Buckshutem Road E.S. - G. Foster ECC | Roof removal/installation, mechanical/electrical modifications | Health & Safety | Rehab of Existing Facility | Completed |
0540-050-01-0524 | Bridgeton | Buckshutem Road E.S. - G. Foster ECC | 61,000 SF New Bldg Addition provides 24 new classrooms for 360 Pre-K & Kindergarten students and includes a gym, cafetorium w/stage, kitchen, SGI and Admin Offices. | School Facility Project | Addition and Rehab of Existing Facility | Completed |
0540-055-00-0478 | Bridgeton | Cherry Street E.S. | the replacement of windows and repair/replacement of doors. | Health & Safety | Rehab of Existing Facility | Completed |
0540-060-00-0498 | Bridgeton | Indian Avenue E.S. | the replacement of windows and repair/replacement of doors. | Health & Safety | Rehab of Existing Facility | Completed |
0540-100-00-0653 | Bridgeton | Quarter Mile Lane E.S. | replacing the roof | Health & Safety | Rehab of Existing Facility | Completed |
0540-130-00-0574 | Bridgeton | West Avenue E.S. | roof replacement | Health & Safety | Rehab of Existing Facility | Completed |
0600-020-00-0427 | Burlington City | Burlington City H.S. | Remove existing fire alarm system and control panel, provide new fire alarm system and control panel, furnish and install new exterior egress lighting. | Health & Safety | Rehab of Existing Facility | Completed |
0600-020-01-0957 | Burlington City | Burlington City H.S. | Pre-development request for A/E to do Ed Specs/Schematic design. Renovations & additons. Prior SOW for H&S. | School Facility Project | Addition and Rehab of Existing Facility | Construction |
0600-040-00-0615 | Burlington City | Captain James Lawrence E.S. | Upgrades to emergency and exit lighting, PA and sprinkler system, fire resistant upgrades to doors, frames and stair enclosures, heating, electric, and ventilation systems, new exhaust fans and asbestos abatement. | Health & Safety | Rehab of Existing Facility | Completed |
0600-050-01-1023 | Burlington City | Elias Boudinot E.S. | Upgrades to emergency and exit lighting, PA system, fire resistant upgrades to doors, frames and electric panels, new exhaust fans, fire alarm and asbestos abatement. | Health & Safety | Rehab of Existing Facility | Completed |
0600-080-00-0652 | Burlington City | Samuel Smith E.S. | Upgrades to emergency and exit lighting, PA system, fire resistant upgrades to doors, frames and electric panels, new exhaust fans, fire alarm and asbestos abatement. | Health & Safety | Rehab of Existing Facility | Completed |
0600-080-01-0488 | Burlington City | Samuel Smith E.S. | 12 pre-K classroom addition, 15K SF | School Facility Project | Addition To Existing Facility | Completed |
0600-085-01-0958 | Burlington City | Wilbur Watts Intermediate School | Pre-development request for A/E to do Ed Specs/Schematic design for a replacement middle school to Wilbur Watts Intermediate School. | School Facility Project | New Construction | Construction |
0600-085-01-1160 | Burlington City | Wilbur Watts Intermediate School | New unit ventilators and R.T.U’s, new general & classroom lighting and power, new public address and security systems, masonry repairs and cleaning; new int. and ext. doors and hardware; new windows, boiler repairs and other. | Health & Safety | Rehab of Existing Facility | Completed |
0680-010-01-1278 | Camden City | Jerrothia Riggs Adult Education Cnt | Electrical lighting and fire alarm system upgrades, and general construction, carpentry, masonry repairs and roofing upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
0680-010-03-0214 | Camden City | Jerrothia Riggs Adult Education Cnt | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-025-01-0929 | Camden City | Early Childhood Development Center #25 | Replacement construction in lieu of renovation and addition of the ECDC on existing site. | School Facility Project | New Construction | Construction |
0680-025-01-1314 | Camden City | Early Childhood Development Center #25 | Repairs/replacements include roof, electrical system, window replacements, asbestos abatement, fire alarm upgrades, structural repairs and boiler replacement. | Health & Safety | Rehab of Existing Facility | Completed |
0680-025-03-0207 | Camden City | Early Childhood Development Center #25 | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-027-01-1279 | Camden City | South Camden Alternative School | Repair/replace roof, repoint brick, skylight, stair, electrical system, fire alarm detection/escapes/doors, concrete sidewalks, copper water /cast iron pipe, rainwater conductors/scuppers, ceilings, floor drains | Health & Safety | Rehab of Existing Facility | Completed |
0680-027-03-0225 | Camden City | South Camden Alternative School | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-029-01-1312 | Camden City | Brimm Medical Arts H.S. | Repair/replace, roof, exterior masonry, trim, interior and exterior lighting fixture, exterior doors, fire alarm/detection system | Health & Safety | Rehab of Existing Facility | Completed |
0680-029-03-0217 | Camden City | Brimm Medical Arts H.S. | Install automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-030-01-1015 | Camden City | Camden H.S. | evaluation of design exterior masonry/re-pointing as conditions warrant, roof replacement, fire alarm systems/design of fire alarm upgrades, electrical system, lighting and control panel upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
0680-030-03-0199 | Camden City | Camden H.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-040-00-0429 | Camden City | Woodrow Wilson H.S. | Asbestos Abatement, door/hardware replacement, electrical upgrades, electrical lighting, exit signs, exterior wall repair, fire alarm system, interior finishes, window replacement and emergency generator. | Health & Safety | Rehab of Existing Facility | Completed |
0680-040-03-0229 | Camden City | Woodrow Wilson H.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-045-01-1032 | Camden City | East Camden M.S. | install new windows, roof, exterior doors, repair existing fire alarm, replace exit & egress lighting, repair/replace masonry, windows and install new windows. | Health & Safety | Rehab of Existing Facility | Completed |
0680-045-03-0206 | Camden City | East Camden M.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-070-01-0933 | Camden City | Pyne Poynt Family M.S. | Addition and renovation to existing facility. | School Facility Project | Addition and Rehab of Existing Facility | Construction |
0680-070-01-1010 | Camden City | Pyne Poynt Family M.S. | Investigation and evaluation for upgrading the building, exterior masonry wall, roof replacement, investigation and design of safety issues, building electrical system/design of lighting control panel upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
0680-070-03-0222 | Camden City | Pyne Poynt Family M.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-080-01-1319 | Camden City | Veterans Memorial M.S. | door/hardware replacement, electrical upgrades, electrical lighting, exit signs, exterior wall repair, fire alarm system, interior finishes, window replacement, emergency generator, fire suppression/standpipe, roofing | Health & Safety | Rehab of Existing Facility | Completed |
0680-080-03-0249 | Camden City | Veterans Memorial M.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-100-01-1322 | Camden City | Bonsall E.S. | Electrical lighting and fire alarm system upgrades, and general construction, carpentry, masonry repairs and roofing upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
0680-100-03-0196 | Camden City | Bonsall E.S. | Install Automatic ROL Flushing System on Bonsall E.S. Water Lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-110-01-1296 | Camden City | Broadway E.S. | Repair/replace roof, repoint brick, skylight, stair, electrical system, fire alarm detection/escapes/doors, concrete sidewalks, copper water/cast iron pipe, rainwater conductors/ scuppers, ceilings, floor drains | Health & Safety | Rehab of Existing Facility | Completed |
0680-110-03-0250 | Camden City | Broadway E.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-140-01-1280 | Camden City | Octavius V. Catto Community School | Repair/replace roof, rainwater conductors, exterior CMU walls, cornice, terra cotta, repoint exterior brick, stone windowsills, plaster ceilings, sidewalk, fire alarm /detection system, existing standpipe, lighting, electrical system. | Health & Safety | Rehab of Existing Facility | Completed |
0680-140-03-0201 | Camden City | Octavius V. Catto Community School | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-165-01-1011 | Camden City | Cooper's Poynt E.S. | Electrical lighting and fire system upgrade, and general construction, carpentry, masonry repairs, doors finishes and roofing upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
0680-165-03-0202 | Camden City | Cooper's Poynt E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-170-01-1016 | Camden City | Cramer E.S. | Repair/replace roof, rainwater conductors, exterior CMU walls, cornice, terra cotta, repoint exterior brick, stone windowsills, plaster ceilings, sidewalk, fire alarm /detection system, existing standpipe, lighting, electrical system. | Health & Safety | Rehab of Existing Facility | Completed |
0680-170-03-0251 | Camden City | Cramer E.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-175-01-0745 | Camden City | Riletta T. Cream E.S. | TCU site approval (2) | Other | Temporary Classroom Unit | Completed |
0680-175-01-1310 | Camden City | Riletta T. Cream E.S. | Electrical lighting and fire system upgrade and general construction, carpentry, masonry repairs, doors and finishes. | Health & Safety | Rehab of Existing Facility | Completed |
0680-175-03-0223 | Camden City | Riletta T. Cream E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-180-01-1008 | Camden City | Davis E.S. | Asbestos Abatement, door/hardware replacement, electrical upgrades, electrical lighting, exit signs, exterior wall repair, fire alarm system, interior finishes, window replacement and emergency generator | Health & Safety | Rehab of Existing Facility | Completed |
0680-180-03-0204 | Camden City | Davis E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-190-01-0927 | Camden City | Dudley E.S. | Replacement of existing Dudley ES on new site | School Facility Project | New Construction | Construction |
0680-190-01-1293 | Camden City | Dudley E.S. | Repair/replace roof, rainwater conductors, exterior CMU walls, cornice, terra cotta, repoint exterior brick, stone windowsills, plaster ceilings, sidewalk, fire alarm /detection system, existing standpipe, lighting, electrical system. | Health & Safety | Rehab of Existing Facility | Completed |
0680-190-03-0205 | Camden City | Dudley E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-205-01-1318 | Camden City | Forest Hill E.S. | Repairs/replacements include roof, electrical system, window replacements, asbestos abatement, fire alarm upgrades, structural repairs and boiler replacement | Health & Safety | Rehab of Existing Facility | Completed |
0680-205-03-0210 | Camden City | Forest Hill E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-210-01-1358 | Camden City | Hatch M.S. | Remove existing roof, install new multi-ply roof & equipment. Repair existing fire alarm detection system, supplemental lighting fixtures & switching, relamp & reballast existing fixtures, masonry/stone. Remove/replace glass block window. | Health & Safety | Rehab of Existing Facility | Completed |
0680-210-03-0211 | Camden City | Hatch M.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-215-03-0215 | Camden City | Lanning Square E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-230-01-1009 | Camden City | McGraw E.S. | Repair/replace roof, rainwater conductors, exterior CMU walls, cornice, terra cotta, repoint exterior brick, stone windowsills, plaster ceilings, sidewalk, fire alarm /detection system, existing standpipe, lighting, electrical system. | Health & Safety | Rehab of Existing Facility | Completed |
0680-230-03-0216 | Camden City | McGraw E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-240-01-1311 | Camden City | Creative and Performing Arts H.S. | Electrical lighting and fire alarm system upgrades, and general construction, carpentry, masonry repairs and roofing upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
0680-240-03-0203 | Camden City | Creative and Performing Arts H.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-245-01-0930 | Camden City | Morgan Village M.S. | Addition and renovations to Morgan Village. Land acquisition may be required for replacement of parking area. Addition footprint on existing parking lot. | School Facility Project | Addition and Rehab of Existing Facility | Design |
0680-245-01-1012 | Camden City | Morgan Village M.S. | install new windows, roof, exterior doors, repair existing fire alarm, replace exit & egress lighting, repair/replace masonry, windows and install new windows. | Health & Safety | Rehab of Existing Facility | Completed |
0680-245-03-0219 | Camden City | Morgan Village M.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-250-01-1034 | Camden City | Raphael Cordero Molina E.S. | Repairs/replacements include roof, electrical system, window replacements, asbestos abatement, fire alarm upgrades, structural repairs and boiler replacement | Health & Safety | Rehab of Existing Facility | Completed |
0680-250-03-0248 | Camden City | Raphael Cordero Molina E.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-260-01-1292 | Camden City | Parkside E.S. | Repairs/replacements include roof, electrical system, window replacements, asbestos abatement, fire alarm upgrades, structural repairs and boiler replacement | Health & Safety | Rehab of Existing Facility | Completed |
0680-260-03-0220 | Camden City | Parkside E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-270-01-1317 | Camden City | Powell E.S. | Electrical lighting and fire system upgrade, and general construction, carpentry, masonry repairs, doors finishes and roofing upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
0680-270-03-0221 | Camden City | Powell E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-300-01-1316 | Camden City | Sharp E.S. | Repair/replace roof, rainwater conductors, exterior CMU walls, cornice, terra cotta, repoint exterior brick, stone windowsills, plaster ceilings, sidewalk, fire alarm /detection system, existing standpipe, lighting, electrical system. | Health & Safety | Rehab of Existing Facility | Completed |
0680-300-03-0224 | Camden City | Sharp E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-305-01-1295 | Camden City | Challenge Square Academy | Replacement of unsafe playground equipment and subsurface material to bring in compliance with CPSC Playground safety guidelines | Health & Safety | Rehab of Existing Facility | Completed |
0680-305-03-0233 | Camden City | Challenge Square Academy | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-310-01-1007 | Camden City | Sumner E.S. | Repair/replace roof, repoint brick, skylight, stair, electrical system, fire alarm detection/escapes/doors, concrete sidewalks, copper water /cast iron pipe, rainwater conductors/scuppers, ceilings, floor drains | Health & Safety | Rehab of Existing Facility | Completed |
0680-310-03-0252 | Camden City | Sumner E.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-320-01-0744 | Camden City | U.S. Wiggins E.S. | TCU site approval (1) | Other | Temporary Classroom Unit | Completed |
0680-320-01-1033 | Camden City | U.S. Wiggins E.S. | Repair/replace roof, repoint brick, skylight, stair, electrical system, fire alarm detection/escapes/doors, concrete sidewalks, copper water /cast iron pipe, rainwater conductors/scuppers, ceilings, floor drains | Health & Safety | Rehab of Existing Facility | Completed |
0680-320-03-0228 | Camden City | U.S. Wiggins E.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-330-01-1294 | Camden City | Washington E.S. | Electrical lighting and fire system upgrade and general construction, carpentry, masonry repairs, doors and finishes. | Health & Safety | Rehab of Existing Facility | Completed |
0680-330-03-0226 | Camden City | Washington E.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-340-01-1315 | Camden City | Whittier E.S. | Repair/replace existing masonry and stone. Remove/replace glass block window, roofing. Electrical lighting and fire alarm system upgraded, and general construction, carpentry, masonry repairs, doors and finishes. | Health & Safety | Rehab of Existing Facility | Completed |
0680-340-03-0227 | Camden City | Whittier E.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-350-01-0938 | Camden City | H. B. Wilson E.S. | Replacement of existing HB Wilson ES on new site. | School Facility Project | New Construction | Construction |
0680-350-01-1006 | Camden City | H. B. Wilson E.S. | Electrical lighting and fire alarm system upgrades, general construction, carpentry, masonry repairs and roofing upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
0680-350-03-0212 | Camden City | H. B. Wilson E.S. | Install Automatic ROL Flushing Systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-360-01-1320 | Camden City | Yorkship E.S. | door/hardware replacement, electrical upgrades, electrical lighting, exit signs, exterior wall repair, fire alarm system, interior finishes, window replacement, emergency generator, fire suppression/standpipe, roofing | Health & Safety | Rehab of Existing Facility | Completed |
0680-360-03-0230 | Camden City | Yorkship E.S. | Install Automatic ROL flushing systems on water lines | School Facility Project | Rehab of Existing Facility | Completed |
0680-909-01-1313 | Camden City | Environmental Center | Repair/replace, roof, exterior masonry, trim, interior and exterior lighting fixture, exterior doors, fire alarm/detection system. | Health & Safety | Rehab of Existing Facility | Completed |
0680-917-01-1031 | Camden City | Fetters Alternative Sch | Repair/replace roof, repoint brick, skylight, stair, electrical system, fire alarm detection/escapes/doors, concrete sidewalks, copper water /cast iron pipe, rainwater conductors/scuppers, ceilings, floor drains | Health & Safety | Rehab of Existing Facility | Completed |
0680-X01-03-0209 | Camden City | Fetters Alternative HS | Install automatic ROL Flushing Systems on water lines. | School Facility Project | Rehab of Existing Facility | Completed |
0680-X04-03-0200 | Camden City | Camden Vocational School | Install automatic ROL Flushing Systems on water lines. | School Facility Project | Rehab of Existing Facility | Completed |
1210-010-00-0661 | East Orange | B.L. Edmonson Ctr. Adult H.S. | Exterior masonry repair, window replacement, door & hardware upgrade, electric light and wiring upgrades, fire alarm work and emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1210-030-00-0667 | East Orange | East Orange Campus 9 (aka Clifford J. Scott HS) | Asbestos abatement disposal; life safety improvements and building envelope restoration. | Health & Safety | Rehab of Existing Facility | Completed |
1210-030-01-0722 | East Orange | East Orange Campus 9 (aka Clifford J. Scott HS) | Extensive rehabilitation of building | School Facility Project | Rehab of Existing Facility | Completed |
1210-040-01-1181 | East Orange | East Orange H.S. | Life safety and building envelope restoration. | Health & Safety | Rehab of Existing Facility | Completed |
1210-040-02-0295 | East Orange | East Orange H.S. | Construction of an auditorium for the East Orange Campus High School | School Facility Project | Addition To Existing Facility | Completed |
1210-060-01-1182 | East Orange | G.W.Carver Institute | Window replacement, door & hardware upgrade, roof repairs, electric light and wiring upgrades, emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1210-080-01-1184 | East Orange | Langston Hughes School | Window replacement, door & hardware upgrade, roof repairs, electric light and wiring upgrades, emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1210-090-00-0577 | East Orange | Whitney E. Houston Academy E.S. | Life safety improvements and building envelope restoration. | Health & Safety | Rehab of Existing Facility | Completed |
1210-093-01-1183 | East Orange | Fourth Avenue E.S. | Window replacement, door & hardware upgrade, roof repairs, electric light and wiring upgrades, emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1210-100-00-0662 | East Orange | Mildred B. Garvin MicroSociety Sch | Life safety improvements and building envelope restoration. | Health & Safety | Rehab of Existing Facility | Completed |
1210-100-02-0613 | East Orange | Mildred B. Garvin MicroSociety Sch | Two additions equaling 50,000 sf and rehabilition of existing facility. | School Facility Project | Addition and Rehab of Existing Facility | Construction |
1210-110-01-1180 | East Orange | Dionne Warwick Institute | Window replacement, door & hardware upgrade, electric light and wiring upgrades and emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1210-120-01-1179 | East Orange | Ecole T.Louverture E.S. | Window replacement, door & hardware upgrade, roof repairs, electric light and wiring upgrades, emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1210-130-01-1185 | East Orange | Gordon Parks Academy E.S. | Electrical light and wiring upgrades and roofing repair. | Health & Safety | Rehab of Existing Facility | Completed |
1210-140-01-1176 | East Orange | Washington Academy E.S. | Window replacement, door & hardware upgrade, roof repairs, electric light and wiring upgrades, emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1210-150-01-1178 | East Orange | Cicely Tyson School | Window replacement, door & hardware upgrade, electric light and wiring upgrades and emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1210-170-01-1177 | East Orange | J. Garfield Jackson, Sr. Academy ES | Exterior masonry repair, window replacement, door & hardware upgrade, electric light and wiring upgrades, fire alarm work and emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1210-906-00-0668 | East Orange | Hart Middle School | Life safety and building envelope restoration. | Health & Safety | Rehab of Existing Facility | Completed |
1210-E01-01-0873 | East Orange | Wahlstrom Early Childhood Center | Roof replacement, boiler installation, Handicap modifications for ADA, cafetorium plumbing, Insulation of floors and piping, exterior fascia repair | School Facility Project | Rehab of Existing Facility | Completed |
1210-x05-01-0808 | East Orange | New ES #5 (-x05) | Site for new 90,000-s.f. ES to house pre-k thru 8th grade students. | School Facility Project | New Construction | Construction |
1210-x07-01-0792 | East Orange | New - Langston Hughes Replacement (-x07) | The 92,146-s.f. replacement school will be built next to the existing facility & house 516 pre-k thru 5th grade students. | School Facility Project | New Construction | Completed |
1320-025-00-0611 | Elizabeth | Elizabeth H.S. | New complete fire alarm. Replace exterior doors and hardware. Roofing repairs. | School Facility Project | Rehab of Existing Facility | Completed |
1320-025-03-0833 | Elizabeth | Elizabeth H.S. | Remodel of 17 classrooms/spaces in the Five House to create additional classroom space | School Facility Project | Rehab of Existing Facility | Completed |
1320-030-00-0639 | Elizabeth | Number 76, Reilly M.S. | Electrical modifications, general construction and roofing work, window replacement. | Health & Safety | Rehab of Existing Facility | Completed |
1320-035-00-0515 | Elizabeth | Number 75, Battin M.S. | New Roof, masonry, gym pads, radiator covers and exit signs. | Health & Safety | Rehab of Existing Facility | Completed |
1320-050-00-0606 | Elizabeth | Number 70, Cleveland M.S. | New roof, masonry, doors, stairs and auditorium lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1320-060-00-0512 | Elizabeth | Number 72, Hamilton M.S. | New roof, masonry, exit signs and windows | Health & Safety | Rehab of Existing Facility | Completed |
1320-090-00-0463 | Elizabeth | Number 1, George Washington E.S. | New roof, masonry, windows, exit signs and hallway walls | Health & Safety | Rehab of Existing Facility | Completed |
1320-100-00-0607 | Elizabeth | Number 2, Winfield Scott E.S. | New roof, masonry, windows, exit signs, handrails, toilet exhaust fans | Health & Safety | Rehab of Existing Facility | Completed |
1320-110-00-0604 | Elizabeth | Number 3, Peterstown E.S. aka Nicholas Lacorte | Roof repairs, door hardware, fire alarm. | School Facility Project | Rehab of Existing Facility | Completed |
1320-120-00-0609 | Elizabeth | Number 6, Marquis deLafayette E.S. | Electrical modifications, general construction and roofing work, window replacement. | Health & Safety | Rehab of Existing Facility | Completed |
1320-160-00-0464 | Elizabeth | Number 13, Benjamin Franklin E.S. | Emergency lighting, doors and hardware, gymnasium wall pads, exterior brick restoration, lead paint removal. | Health & Safety | Rehab of Existing Facility | Completed |
1320-170-00-0545 | Elizabeth | Number 14, Abraham Lincoln E.S. | Roofing, masonry work, general construction work, mechanical and electrical work. | Health & Safety | Rehab of Existing Facility | Completed |
1320-180-00-0603 | Elizabeth | Number 15, Christopher Columbus ES | New roof, masonry, doors and hardware, rubber stair tread, gym pads, exit signs, windows, radiator covers | Health & Safety | Rehab of Existing Facility | Completed |
1320-190-00-0608 | Elizabeth | Number 16, Madison-Monroe E.S. | New roof, masonry, doors and hardware, window, boilers, piping and unit ventilators. | Health & Safety | Rehab of Existing Facility | Completed |
1320-200-00-0640 | Elizabeth | Number 17, Theodore Roosevelt E.S. | New roof, masonry, transoms, gym wall pads and radiator covers. | Health & Safety | Rehab of Existing Facility | Completed |
1320-220-00-0677 | Elizabeth | Number 19, Woodrow Wilson E.S. | New doors and hardware, exhaust fans, unit ventilators, control wiring, exit and emergency lights. | Health & Safety | Rehab of Existing Facility | Completed |
1320-230-00-0610 | Elizabeth | Number 20, John Marshall E.S. | Door repairs, light installation, generator repairs. | School Facility Project | Rehab of Existing Facility | Completed |
1320-240-00-0678 | Elizabeth | Number 21, Victor Mravlag E.S. | New roof, door hardware, masonry and hand rails. | Health & Safety | Rehab of Existing Facility | Completed |
1320-240-03-0339 | Elizabeth | Number 21, Victor Mravlag E.S. | Rehab and addition to accommodate unhoused students and program needs | School Facility Project | Addition and Rehab of Existing Facility | Construction |
1320-250-00-0605 | Elizabeth | Number 22, William F. Halloran E.S. | New roof, door hardware, masonry improvements and hand rails. | Health & Safety | Rehab of Existing Facility | Completed |
1320-260-00-0513 | Elizabeth | Number 23, N.M. Butler E.S. | New masonry, doors and hardware and windows | Health & Safety | Rehab of Existing Facility | Completed |
1320-901-00-0461 | Elizabeth | Edison House School | Roofing, masonry, general construction, mechanical/electrical work; and window replacement. | Health & Safety | Rehab of Existing Facility | Completed |
1320-902-00-0462 | Elizabeth | Jefferson House | Replace windows, roofing and masonry. Repair Drywall partition, doors & hardware, misc. electrical work. | Health & Safety | Rehab of Existing Facility | Completed |
1320-903-00-0629 | Elizabeth | No 23 Annex - JP Mitchell Bldg | New door hardware and emergency lighting. | Health & Safety | Rehab of Existing Facility | Completed |
1320-904-00-0628 | Elizabeth | Sam Aboff House H.S. | Roofing, masonry, general construction, mechanical/electrical work. | Health & Safety | Rehab of Existing Facility | Completed |
1320-999-01-EA17 | Elizabeth | Elizabeth Multi-Facility/TCU | TCU AE Services - Temp | Multi-Facility/TCU | Temporary Classroom Unit | Completed |
1320-999-01-EA18 | Elizabeth | Elizabeth Multi-Facility/TCU | TCU AE Services - Temp | Multi-Facility/TCU | Temporary Classroom Unit | Completed |
1320-999-01-EA19 | Elizabeth | Elizabeth Multi-Facility/TCU | TCU AE Services - Temp | Multi-Facility/TCU | Temporary Classroom Unit | Completed |
1320-999-01-EA20 | Elizabeth | Elizabeth Multi-Facility/TCU | TCU AE Services - Temp | Multi-Facility/TCU | Temporary Classroom Unit | Completed |
1320-999-01-EA21 | Elizabeth | Elizabeth Multi-Facility/TCU | TCU AE Services - Temp | Multi-Facility/TCU | Temporary Classroom Unit | Completed |
1320-E02-01-0089 | Elizabeth | New pre K-8 #27 | Build replacement school PS 17, gsf, 650 Pre-K thru 8th grade students. | School Facility Project | New Construction | Construction |
1320-N14-03-0797 | Elizabeth | Dr. MLK Jr Center for ECC School # 52 | Construction of 55,000 s.f. single-story bldg - includes 20 classrms, courtyard play and reading areas, etc. for approx. 300 Pre-K students. | School Facility Project | New Construction | Completed |
1320-NS1-01-0906 | Elizabeth | Monsignor Joao S. Antao School No. 31 | acquisition of site and construciton of a pre-K-8 facility adjacent to an existing pre-K facility | School Facility Project | New Construction | Completed |
1320-x01-01-0087 | Elizabeth | Donald Stewart ECC #51 (aka ECC#44) | Construction of a 56,000 s.f. single-story bldg with 20 classrooms, outdoor courtyard play and reading areas, etc. for approx. 300 Pre-K students. | School Facility Project | New Construction | Completed |
1320-x04-01-0090 | Elizabeth | New pre K-8 #28 | Construction of new 119,000 s.f. facility includes classrooms, SGI rms, media ctr (library), art & music rms, science labs, cafetorium, gyms, computer labs, softball field, etc. for 750 Pre-K thru 8th grade students. | School Facility Project | New Construction | Construction |
1320-x05-01-0091 | Elizabeth | Dr. Albert Einstein School (aka #29) | Construction of new 118,452 s.f. facility will include classrooms, SGI rms, media ctr (library), art & music rms, science labs, cafetorium, gyms, computer labs, playgrounds for approx 750 Pre-K thru 8th grade students. | School Facility Project | New Construction | Completed |
1320-x06-01-0866 | Elizabeth | Ronald Reagan Academy School # 30 (pre K-8 #30) | Construction of new 119,860 s.f. facility will include classrooms, SGI rms, media ctr (library), art & music rms, science labs, cafetorium, gyms, computer labs, playgrounds for approx 750 Pre-K thru 8th grade students. | School Facility Project | New Construction | Completed |
1700-050-00-0453 | Garfield | Garfield H.S. | upgrade fire alarm systems, exit and emergency lighting systems, upgrade communication system, restoration of brickwork, and replacement of doors. | Health & Safety | Rehab of Existing Facility | Completed |
1700-060-00-0499 | Garfield | Columbus E.S. | upgrade fire alarm systems, exit and emergency lighting systems, upgrade communication system, restoration of brickwork, and replacement of doors. | Health & Safety | Rehab of Existing Facility | Completed |
1700-070-00-0563 | Garfield | Thomas Jefferson M.S. | upgrade fire alarm systems, exit and emergency lighting systems, upgrade communication system, restoration of brickwork, and replacement of doors. | Health & Safety | Rehab of Existing Facility | Completed |
1700-080-01-1110 | Garfield | Lincoln E.S. | upgrade fire alarm systems, exit and emergency lighting systems, upgrade communication system, restoration of brickwork, and replacement of doors. | Health & Safety | Rehab of Existing Facility | Completed |
1700-100-00-0562 | Garfield | Roosevelt E.S. | upgrade fire alarm systems, exit and emergency lighting systems, upgrade communication system, restoration of brickwork, and replacement of doors. | Health & Safety | Rehab of Existing Facility | Completed |
1700-100-02-0430 | Garfield | Roosevelt E.S. | Roof replacement, exterior moisture protection, renovation work consisting of a masonry re-pointing, EIFS work and caulking sealant work. Main entrance door assembly replacement work and interior restoration due to moisture damage. | Health & Safety | Rehab of Existing Facility | Completed |
1700-120-01-1070 | Garfield | Washington Irving E.S. | upgrade fire alarm systems, exit and emergency lighting systems, upgrade communication system, restoration of brickwork, and replacement of doors. | Health & Safety | Rehab of Existing Facility | Completed |
1700-130-00-0497 | Garfield | Woodrow Wilson E.S. | upgrade fire alarm systems, exit and emergency lighting systems, upgrade communication system, restoration of brickwork, and replacement of doors. | Health & Safety | Rehab of Existing Facility | Completed |
1700-205-03-0315 | Garfield | James Madison School #10 (Most Holy Name) | Purchase & rehab a facility leased by school district. Facility to be demolished & replaced with new construction. | School Facility Project | New Construction | Construction Bid |
1700-e01-01-0973 | Garfield | Garfield Early Childhood Center (aka New ECC) | Site analysis, land acquisition for new ECC. Swing space required (TCU) to be housed at site for MS see project #1700-N01-02-0114 | School Facility Project | New Construction | Completed |
1700-n01-02-0114 | Garfield | New Middle School | Site analysis, land acquisition for new MS. | School Facility Project | New Construction | Construction |
1770-050-00-0566 | Gloucester City | Gloucester City Jr. Sr. H.S. | Communication system, electric upgrades, emergency generator, lighting, exit lighting, exterior/interior doors/frames, wall repairs, fire alarm, fire suppression, hardware, HVAC, windows, plumbing, security and sitework. | Health & Safety | Rehab of Existing Facility | Completed |
1770-050-01-0078 | Gloucester City | Gloucester City Jr. Sr. H.S. | Replace existing boiler and related items, replace existing roofing system, roof drains and rain leaders | Health & Safety | Rehab of Existing Facility | Completed |
1770-050-03-0187 | Gloucester City | Gloucester City Jr. Sr. H.S. | Additions: Gymnasium & Library/Media Center. Complete upgrade of HVAC & electrical sys, & plumbing. Interior renovation to all Science and Elective Classrms. | School Facility Project | Addition and Rehab of Existing Facility | Completed |
1770-100-00-0565 | Gloucester City | Mary E. Costello E.S. | Communication system, electric upgrades, emergency generator, lighting, exit lighting, exterior/interior doors/frames, wall repairs, fire alarm, fire suppression, hardware, HVAC, windows, plumbing, security and sitework. | Health & Safety | Rehab of Existing Facility | Completed |
1770-160-01-0245 | Gloucester City | Cold Springs E.S. | New ECC addition consisting of 20 pre-K classrms, multi-purpose rm, storage, support kitchen, etc. Rehab to include toilet rooms. | School Facility Project | Addition To Existing Facility | Completed |
1770-160-01-0746 | Gloucester City | Cold Springs E.S. | TCU site approval - Removal of TCUs (18). This project is related to: 1770-160-01-0245 (addition to Cold Springs Elementary). | Other | Temporary Classroom Unit | Completed |
2060-050-00-0460 | Harrison | Harrison H.S. | Renovations to interior and exterior, including the basement, auditorium, gymnasium, and media center. | Health & Safety | Rehab of Existing Facility | Completed |
2060-060-00-0480 | Harrison | Lincoln No. 3 E.S. | Window replacement, metal stairs, lintel roofing & related masonry. | Health & Safety | Rehab of Existing Facility | Completed |
2060-070-00-0459 | Harrison | Washington No. 1 M.S. | Renovation primary focus handicap accessible. Remodel bathrooms, door entrances, add ramps and new elevator. The cafeteria and building's façade will be remodeled. | Health & Safety | Rehab of Existing Facility | Completed |
2060-x01-01-0832 | Harrison | New Harrison High School (-x01) | New 167,000 s.f. includes 30 general classrms, 4 special ed classrms, 2 SGI classrms. gym, music rm, cafeteria, auditorium, media ctr, science labs, computer rm and athletic fields on the site. Student capacity of 850. | School Facility Project | New Construction | Construction |
2210-005-00-0691 | Hoboken | Hoboken H.S. | Replace roofing system & flashing, skylights, rooftop exhaust fans and exterior doors. Upgrade emergency lighting, fire alarm, fire separation assembly, egress corridor. | Health & Safety | Rehab of Existing Facility | Completed |
2210-005-03-0786 | Hoboken | Hoboken H.S. | Resurfacing of field and replacement of running track | Health & Safety | Rehab of Existing Facility | Completed |
2210-010-00-0626 | Hoboken | A.J. Demarest M.S. | Restore masonry surface & cracks, repair parapet, lintels, electrical & fire alarm upgrade. Replace roofing system, flashing, skylights, rooftop exhaust fans, roof top play area. | Health & Safety | Rehab of Existing Facility | Completed |
2210-050-00-0624 | Hoboken | Joseph F. Brandt No. 2 E.S. | Replace roof sys, flashing, skylights, rooftop exhaust fans, ext windows, restore masonry & cracks, repair parapet, lintels, elect fire alarm, emer sys, upgrade egress corridor, lobby, stairs, stairways, fire supp sys, replace elevator. | Health & Safety | Rehab of Existing Facility | Completed |
2210-063-00-0625 | Hoboken | Salvatore R. Calabro, No. 4 E.S. | Replace roofing sys & flashing, skylights, rooftop exhaust fans, rooftop play area, curtain wall, exterior doors & frames, fire alarm sys & elect upgrades, exterior masonry repair, power washing and misc. work. | Health & Safety | Rehab of Existing Facility | Completed |
2210-063-01-0780 | Hoboken | Salvatore R. Calabro, No. 4 E.S. | Convert MS to ES. Renovation work results: 9 classrooms, admin offices, cafetorium, computer rms, gym, media ctr, art/music rm and stage. | School Facility Project | Rehab of Existing Facility | Construction |
2210-065-00-0627 | Hoboken | Thomas G. Connors | Upgrade/reno egress corridor, lobby, exit stairs, handrails, fire suppr sys, rebld wall, replace elect fire alarm & emerg sys, ext windows, doors, frames, constr exterior fire stair, repair fire escape, parapet, masonry cracks, lintels. | Health & Safety | Rehab of Existing Facility | Completed |
2210-065-01-0783 | Hoboken | Thomas G. Connors | Renovations to Thomas G. Connors E.S. will result in 18 classrooms, administrative offices, cafetorium, computer room, gymnasium, media center, art/music room, stage, science rooms and renovated playground. | School Facility Project | Rehab of Existing Facility | Design |
2210-070-00-0692 | Hoboken | Wallace No. 6 E.S. | Replace roof sys, flashing, skylights, rooftop exhst fans, extr windows, doors, frames, parapet,masonry cracks, lintels,elect fire alarm & emerg sys, generator, fire suppr system, stair treads, upgrade egress corridors, lobby & exit stairs. | Health & Safety | Rehab of Existing Facility | Completed |
2330-050-00-0684 | Irvington Township | Irvington H.S. | Masonry repairs, door replacement, fire detection & intercom upgrades, and lighting protection system. Windows replacement, curtain wall rehabilitation and related masonry work. | Health & Safety | Rehab of Existing Facility | Completed |
2330-070-00-0578 | Irvington Township | Augusta Street Preschool | Replace roofing sys, rain conductors, doors, misc, flashing, infrared surveying, refurb canopy, chimney repair/replacement, windows. Masonry repairs and electrical upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
2330-070-03-0754 | Irvington Township | Augusta Street Preschool | Demolition, rehabilitation, addition and correction of deficiencies to existing facility for conversion into a kindergarten facility | School Facility Project | Addition and Rehab of Existing Facility | Construction |
2330-080-00-0570 | Irvington Township | Berkeley Terrace E.S. | Replace roofing sys, infrared surveying, rain conductors, flashing, doors, chimney & pkgd air-cooled AC units . Masonry repairs, fire & smoke detection & electrical upgrades, replace pkgd air cooled AC units & refurbish canopy & windows. | Health & Safety | Rehab of Existing Facility | Completed |
2330-090-00-0655 | Irvington Township | Chancellor Avenue E.S. | Masonry repairs, door & window replacement, fire alarm, plumbing and electrical upgrades. | Health & Safety | Rehab of Existing Facility | Completed |
2330-100-00-0669 | Irvington Township | Florence Avenue E.S. | Replace roofing sys, doors, infrared surveying, rain conductors, misc. flashing, refurb canopy & windows, balances, shoes, chimney repair/replace. Masonry repairs, elect, fire & smoke detect upgrade, repair air cooled AC units. | Health & Safety | Rehab of Existing Facility | Completed |
2330-110-00-0670 | Irvington Township | Grove Street E.S. | Replace roofing sys, doors, infrared surveying, rain conductors, misc. flashing, refurb canopy & windows, balances, shoes, chimney repair/replace. Masonry repairs, elect, fire & smoke detect upgrade, repair air cooled AC units. | Health & Safety | Rehab of Existing Facility | Completed |
2330-120-00-0685 | Irvington Township | Madison Avenue E.S. | Masonry repairs, doors replacement, window repair/replacement. Replace existing roofing sys, infrared surveying, existing rain conductors, misc. flashing, refurbish existing canopy, chimney repair/replacement. | Health & Safety | Rehab of Existing Facility | Completed |
2330-130-00-0683 | Irvington Township | Mt. Vernon Avenue E.S. | Masonry repairs, window replacement, window repairs, electrical upgrades and environmental work. | Health & Safety | Rehab of Existing Facility | Completed |
2330-130-02-0432 | Irvington Township | Mt. Vernon Avenue E.S. | The new 93,821-sf replacement ES will be a multi-level facility with 31 classrms housing 582 Pre-K thru 5th grade students and include a media center, gymnasium, and auditorium. | School Facility Project | New Construction | Construction |
2330-137-01-0720 | Irvington Township | University Six School | Purchase and renovation of bldg currently leased | School Facility Project | Rehab of Existing Facility | Construction |
2330-137-01-1038 | Irvington Township | University Six School | Windows replacement, curtain wall rehabilitation and related masonry work. | Health & Safety | Rehab of Existing Facility | Completed |
2330-137-04-000S | Irvington Township | University Six School | Replace existing roof | School Facility Project | Rehab of Existing Facility | Completed |
2390-050-00-0696 | Jersey City | Henry Snyder H.S. | Replace doors & hardware, interior finishes, exit signs, emergency egress lighting and new ductwork for boiler room. Masonry restoration & repairs, waterproofing, lintel repair or replacement, plaster repairs and asbestos abatement. | Health & Safety | Rehab of Existing Facility | Completed |
2390-050-01-0877 | Jersey City | Henry Snyder H.S. | Renovation of school - lockers and walks: Removal and replacement of existing wardrobe and athletic lockers, wall patching and painting at Basement, Sub-Basement, First Floor and Third Floor. | Health & Safety | Rehab of Existing Facility | Completed |
2390-060-01-1041 | Jersey City | James J. Ferris H.S. | Health & Safety Full-Scope and Electrical Work - Masonry restoration, concrete stair, doors & frames, boiler room roof. Ferris HS HVAC Upgrade | Health & Safety | Rehab of Existing Facility | Completed |
2390-070-01-0582 | Jersey City | Lincoln H.S. Dr. C. T. Epps Freshman Academy | Renovation of two buildings. Renovation of existing 17,300-s.f. of space and of a 24,500-s.f. addition. Replacement of boiler sys. The new facility will create 29 classrms for 480 students. | School Facility Project | Rehab of Existing Facility | Completed |
2390-070-01-1121 | Jersey City | Lincoln H.S. Dr. C. T. Epps Freshman Academy | Electrical & HVAC | Health & Safety | Rehab of Existing Facility | Completed |
2390-080-01-1122 | Jersey City | William L. Dickinson H.S. | Health and Safety improvements. Note: Terra Cotta Restoration scheduled for completion June 2006. | Health & Safety | Rehab of Existing Facility | Completed |
2390-080-04-00DG | Jersey City | William L. Dickinson H.S. | Replacement of Boilers | School Facility Project | Rehab of Existing Facility | Construction |
2390-095-01-1109 | Jersey City | The Academy I M.S. | Door & Hardware Replacement, Window Replacement & Repairs, Structure Repairs and Electrical & Mechanical Work | |